A new report commissioned by Transport Secretary Fiona Hyslop has recommended against rescheduling or accelerating the A9 Dualling Programme.
The report, which was requested following recommendations from the A9 Inquiry Petitions Committee, considered whether to prioritise sections of the programme based on safety records or potential disruption caused by road closures.
It concluded that maintaining the current schedule would achieve the overall completion of the dualling programme more quickly than any proposed rescheduling.
The report also recommends that the delivery plan is not accelerated, because of the likelihood that this would negatively impact procurement, construction, supply chains and increase disruption for road users.
The report highlights a potential opportunity to bring forward construction of the improved Dalnaspidal Junction through an advance works contract, subject to further assessment and the availability of funding. This would involve extending the existing Glen Garry dual carriageway north by approximately 1km.
The A9 Dualling Programme aims to upgrade 83 miles of the A9 between Perth and Inverness from single to dual carriageway.
Cabinet Secretary for Transport Fiona Hyslop said: "This report considers proposals that the delivery plan for the A9 Dualling programme be rescheduled and/or accelerated. That plan was developed to balance market capacity, impacts on road users and challenging financial constraints and it provides much-needed certainty for road users, local communities and the construction industry on when works all along the A9 are expected.
"I appreciate that there are a range of views on how completion of the dualling programme should be achieved. I believe that the report demonstrates that the delivery plan is a robust and practical approach to undertaking this large programme of work in the years ahead, and the Scottish Government remains fully focused and committed to taking these projects forward as set out in that plan. This is supported by a Cabinet decision to prioritise completion of the A9 dualling programme within our available budgets.
"We are already making real progress in delivering on the plan. In the next few months, I expect to see main construction work start on the Tomatin to Moy project, publication of draft Orders for the Pass of Birnam to Tay Crossing project, contract award for the Tay Crossing to Ballinluig project and commencement of procurement for the Pitlochry to Killiecrankie project.
"In parallel with this, we expect to complete works on the £5m package of short term measures by the end of March this year, and the A9 Safety Group will continue to work together to explore any measures to positively influence driver behaviour to help reduce the numbers of people being injured or killed on the road.
"However, I have asked Transport Scotland to assess the potential to undertake an advance works contract for the Dalnaspidal Junction, as recommended in the report. I am wholly committed to progressing the A9 dualling programme, to listening to and keeping Parliament and local residents, businesses and communities informed of and engaged with our delivery plan. Where improvements can be made, within budget, which enhance delivery and/or the timetable, then we will make them."
Construction News
16/01/2025
A9 Dualling Programme To Proceed As Planned


16/06/2025
Work has commenced on a major project to transform the Watersports Centre at Strathclyde Country Park into a multi-purpose community facility, with an ambitious target to reduce the building's carbon footprint by at least 80%.
The initial stage, focusing on improving the building's entrance and ac

16/06/2025
Work is expected to commence this summer on the site for the new Mayfield Community Learning Campus, following Midlothian Council's appointment of Kier as the main contractor.
The £41.8 million project is expected to complete its construction phase by spring 2027, with the overall campus fully ope

16/06/2025
McLaughlin & Harvey has officially handed over the keys to the Ayrshire Hospice's significantly redeveloped facility, marking the completion of an £18.8 million capital build project.
The extensive works were undertaken in close collaboration with the Ayrshire Hospice to substantially improve its

16/06/2025
Aberdeenshire Council has announced the opening of the latest round of its Coastal Communities Challenge Fund (CCCF), making grants of up to £49,999 available to support initiatives along its coastline.
The fund, which distributes revenues generated by Crown Estate Scotland, targets community group

16/06/2025
A crucial route into Stewarton, the B778 Holm Street, is scheduled for closure for approximately two months as Scottish Water proceeds with a significant £16 million package of investments in the town's water infrastructure.
The closure will take effect from Monday, 30th June 2025, impacting Holm S

16/06/2025
Stirling Council is moving forward with plans to deliver 36 high-quality, energy-efficient homes for social rent at Brucefields, a key component of the South Stirling gateway strategic housing site. The Council has now received approval to initiate the procurement process for their construction.
Th

16/06/2025
Significant progress is being made towards the reinstatement of Dunrod Road, a crucial rural link between Greenock and Inverkip that has been closed for some time due to a partial failure and movement of the road caused by various factors, including landslip. Ground investigation works are scheduled

16/06/2025
Bonnybridge is set for significant infrastructure upgrades this summer, with Falkirk Council investing £460,000 in a coordinated programme of resurfacing, regeneration, and accessibility improvements.
The work will focus on Bonnybridge Toll, Memorial Park, and surrounding public spaces.
Funding f

13/06/2025
The first completed section of Glasgow's ambitious £120 million-plus Avenues programme, the Holland and Pitt Street Avenue, has officially opened, marking a significant milestone in the ongoing regeneration of the city centre.
The newly completed avenue features a comprehensive transformation, incl

13/06/2025
Construction has officially commenced on the Dumfries Zero Waste Park (Dumfries ZWP), marking a significant milestone in Dumfries and Galloway Council's commitment to its Waste, Recycling and Reuse Strategy 2023–2030.
The £11.197m investment, drawn from the Council's approved 10-year Capital Invest