Major engineering works will stretch over a 16-week period, beginning from January, as part of upgrades to electrify the railway between East Kilbride and Glasgow.
To help deliver these vital improvements, from Saturday, January 25 until Sunday, May 18, no trains will run on the line between East Kilbride and Thornliebank stations while work is carried out to the track, bridges and overhead line equipment along the route.
This critical period in the electrification project will also see 22km of new overhead power cables installed and the lengthening of the double-track between East Kilbride and Hairmyres.
The existing track will also be lowered at locations near Busby, Clarkston and Giffnock stations so that overhead line equipment can be accommodated under some bridges on the route.
The £140m project will help to decarbonise rail services as well as improve reliability for passengers and has an overall completion date of December 2025.
By that stage, the investment in the line will see: Electrification of the railway from Glasgow to East Kilbride; A new station at East Kilbride; A new station with two platforms and accessible footbridge at Hairmyres; A new footbridge at Busby station; Improved access at Giffnock, with a new accessible footbridge; and a new station entrance at Clarkston.
The project is being delivered by Network Rail and is part of a Scottish Government investment in the line.
Gerry McQuade, Network Rail capital delivery director, said: "This programme of extended engineering works is a critical point in the delivery of the electrification of the East Kilbride line.
"Closing the railway is never an easy decision, but the engineering work taking place over these 16 weeks can only be done when no trains are running. This approach allows the completion of these major works in the most efficient, fastest way.
"We do appreciate the impact this will have both on those living closest to the line and to our passengers. We hope that by advising people three-months ahead of the work starting, this raises awareness and allows people the time to consider alternative travel arrangements."
Meanwhile, Mark Ilderton, ScotRail service delivery director, said: "The works being carried out by Network Rail are absolutely critical in the latest phase of the project to electrify the railway on the East Kilbride line.
"Unfortunately, during the 16-week closure, we will be unable to operate trains to and from East Kilbride and an alternate transport plan will help to make sure customers are still able to travel.
"In the coming weeks, we will communicate the plan through all our customer information channels, including where replacement buses will operate, and the other routes available for customers."
Damian Briody, Transport Scotland’s head of rail projects and technical services, added: "This announcement marks the build-up to the latest phase of progress on the East Kilbride electrification project.
"Whilst any disruption to passengers is unwelcome, we acknowledge the careful consideration which has gone into delivering the significant improvement works taking place during the closure.
"It is welcome that Network Rail and ScotRail have listened to passengers in planning these works and that they will continue to work closely together to ensure these passengers can make informed journey planning choices."
Throughout the works, no train services will run to East Kilbride. To help minimise disruption for passengers, a replacement bus service will be in place during this period.
At the same time as the 16-weeks of work finishes, in May 2025, the new Hairmyres station is scheduled to open to the public.
Information on the bus replacement service will be available in the coming weeks and customers are advised to check at www.scotrail.co.uk or via www.nationalrail.co.uk when planning their journeys over this period.
Construction News
04/11/2024
Line Closure To Facilitate £140m Electrification Upgrade


20/06/2025
Stirling Council has taken a significant step towards transforming the city's riverside, giving the green light to begin marketing a key residential plot within the landmark Forthside development.
This strategically located site could accommodate up to 120 new homes, marking a pivotal moment in re

20/06/2025
Glasgow City Council has approved a total of £290,000 in funding for the Glasgow Building Preservation Trust (GBPT) and the Glasgow City Heritage Trust (GCHT) for the upcoming 2025/26 financial year.
This significant investment underlines the council's commitment to protecting and enhancing the ci

20/06/2025
Construction is set to commence next week on the River Park Routes project, an ambitious initiative to create a high-quality, fully accessible shared path network alongside the River Leven in Levenmouth.
This development will link the area's new rail stations at Leven and Cameron Bridge, significa

20/06/2025
Moray Council has officially approved a new Masterplan for Buckie Harbour, paving the way for significant redevelopment aimed at bolstering the region's long-term economic aspirations.
The comprehensive plan envisions Buckie Harbour evolving into a versatile maritime facility capable of accommodat

20/06/2025
Residents and interested stakeholders are encouraged to share their views on a new housing development proposed for Nursery Place in Ardrossan.
The plans outline the construction of six new homes, which will replace existing flatted blocks slated for demolition as part of North Ayrshire Council's

20/06/2025
Owners of empty business properties across Argyll and Bute could now be eligible for a new grant scheme aimed at revitalising vacant commercial spaces.
The Empty Business Property Grant Scheme, recently approved by the council's Environment, Development and Infrastructure committee, targets proper

20/06/2025
The Scottish Government has announced a series of new, legally binding Carbon Budgets, establishing concrete limits on the nation's greenhouse gas emissions for the coming decades.
These five-year statutory targets, spanning from 2026 to 2045, mark a significant step in Scotland's ongoing efforts

20/06/2025
SSE has welcomed the UK Government's new Infrastructure Strategy as a "timely and ambitious blueprint for building essential new infrastructure".
The strategy outlines a 10-year vision for the delivery of critical infrastructure across the UK, with a strong focus on clean energy, resilience, and re

20/06/2025
Work on Scottish Water's £38 million investment project to enhance water network resilience between Peterhead and Ellon is progressing faster than anticipated, with 12 kilometres of new trunk water main already laid.
This marks significant advancement on the planned 7.5km for this phase, attribute

20/06/2025
West Lothian Council has taken a significant step forward in shaping the future development of the area, having approved the submission of its Evidence Report for the new Local Development Plan (LDP2) to the Scottish Government.
This marks a key milestone in the early stages of preparing the compr