09/08/2024

SSE's Coire Glas Exploratory Tunnel Complete

The completion of the 1.2-kilometre tunnel represents a significant milestone in the Coire Glas project, which, once fully constructed, could offer the UK 30 GWh of long-duration energy storage.

Located at Loch Lochy in the Great Glen, the proposed Coire Glas project would have an installed capacity of 1,300MW and be capable of delivering 30GWh of long duration electricity storage – enough to be able to provide firm, flexible renewable power for three million British homes for up to 24 hours non-stop.

SSE Renewables hopes to make a final investment decision on the project in late 2025 or early 2026, allowing for main construction to commence in the second half of 2026, subject to being successful in the administrative allocation of an investable cap and floor mechanism.

Exploratory works at Coire Glas commenced in December 2022 and are being conducted by STRABAG UK, a world leader in mining and tunnelling projects.

In early 2023, SSE announced a £100-million investment boost to further develop Coire Glas to include the construction of a major exploratory tunnel as part of a comprehensive package of site investigation works.

-- Advertisement --
NorthernAsbestosServicesLtd

SSE's technical partners, Stantec and COWI, have designed and supervised the unique and complex ground investigation programme which is being delivered by STRABAG.

The works included the creation of a tunnel approximately five metres high and four and a half metres wide which cuts into the hillside around the proposed location of the underground powerhouse complex. Construction of the tunnel will allow the project team to gather accurate information on the geological conditions to inform the detailed design for the main works.

Now that tunnel construction is complete, a programme of exploratory drilling and testing will continue for the next three months to further investigate the ground in the area of the proposed underground powerhouse excavations.

Once complete, Coire Glas would provide 30GWh of long duration electricity storage. The scheme would take excess energy from the grid and use it to pump water 500 meters uphill from Loch Lochy to an upper reservoir created by the construction of a 90m high dam. The vast reservoir could store enough water equivalent to nearly 11,000 Olympic-sized swimming pools. At the flick of a switch this water could be released to power the grid when required including at times when wind power output is low and customer demand is high.

Subject to being successful in the administrative allocation of an investable cap and floor mechanism for UK long-duration electricity storage projects, SSE Renewables hopes to make a final investment decision on Coire Glas (1,300MW) in late 2025 or early 2026, allowing for main construction to commence in the second half of 2026. Construction is expected to last up to seven years, which means the project could be operating in 2032 and fully completed during 2033.

Latest Construction News

17/07/2026
Construction has begun on a new £3.3 million paint facility at BAE Systems’ Govan shipyard in Glasgow as part of a wider programme to modernise the city's naval shipbuilding infrastructure. The new facility will allow ship blocks to be painted in a dedicated space, freeing up existing areas at the
Read More
17/07/2026
Retrofit and energy-efficiency specialist Procast Group has secured two awards at the Energy Efficiency Awards, with apprentice electrician Cameron Sleith also recognised as Apprentice of the Year. The company was named Regional Insulation & Fabric Installer and Contractor of the Year at the awards
Read More
17/07/2026
Residential management specialist Fresh has been appointed by Ropemaker to manage two purpose-built student accommodation (PBSA) developments in Edinburgh. Fresh took over management of Meadow Court and Norton's Student Living on 1 July 2026, expanding its existing partnership with Ropemaker, for w
Read More
17/07/2026
Essential resurfacing on the A721 Carnwath Road in Carluke will require a section of the route to be closed for up to four days this month. The works are scheduled to begin on Tuesday 21 July and will cover the stretch between Stanistone Road and Crawfordwalls Bridge. Traffic will be diverted via
Read More
17/07/2026
Aberdeenshire Council is inviting feedback on proposed changes to its Council Tax approach for long‑term empty properties and second homes, with new mitigations being considered alongside a premium due to take effect on 1 September. From 1 September this year, owners of homes left empty for m
Read More
17/07/2026
Grampian Housing Association has appointed David Fisher as its new group chief executive, succeeding Craig Stirrat who is due to retire later this year. Fisher will take up the role in August 2026 following a competitive recruitment process. The housing association said the Board’s recruitment pane
Read More
17/07/2026
Maryhill Housing Association (MHA) has lodged a planning bid for a 108-home neighbourhood on the long-vacant Collina Street plot in north Maryhill, with most properties proposed as affordable. The association has submitted its application to Glasgow City Council, seeking permission to redevelop the
Read More
17/07/2026
Kier has been appointed by the City of Edinburgh Council to deliver a £23m retrofit of residential accommodation in the Craigmillar and Peffermill districts of Edinburgh. Procured via the Scottish Procurement Alliance (SPA) framework, the scheme underpins the council’s environmental objectives. Kie
Read More
17/07/2026
BEAR Scotland, working on behalf of Transport Scotland, will carry out a series of resurfacing schemes at multiple locations on the A83 between Tarbert and Inveraray from Wednesday 29 July. Crews will operate between 7pm and 6am on working nights, with completion anticipated by Thursday 20 August.
Read More
17/07/2026
Investigations into pollution affecting the Kinghorn Burn in Fife are continuing, with public health advice to avoid contact with the water remaining in place. The Scottish Environment Protection Agency (SEPA) and Scottish Water are working alongside partners including Fife Council, NHS Fife and Fi
Read More
SEEIT3DCarla MacKay InteriorsKFP Services LTDWindow StoreAberroof AberdeenArctic Spas RosebankBairds Windows LtdJRF Chimney Specialists and Heating DistributorsEuro-Fab (Scotland)James Smith Fencing Ltd