SSE Granted Consent For Sloy Upgrades, Opening Path To Pumped Storage

Construction News Image

SSE has received Section 36 planning consent from the Scottish Government to upgrade its 152.5MW Sloy Hydro-electric Power Station at Inveruglas on the western shore of Loch Lomond.

The consent provides the option to convert the existing plant into a pumped storage hydro scheme capable of delivering up to 16GWh of long-duration electricity storage. It also keeps open the possibility of increasing Sloy's installed generation capacity to 160MW through future asset improvement works.

Commissioned in 1950, Sloy remains the UK's largest conventional hydro-electric power station. The facility plays a key role in providing system flexibility and peak-demand support for Great Britain's electricity system.

-- Advertisement --
NorthernAsbestosServicesLtd

The plant generates around 130,000MWh of renewable electricity annually, can reach full output in under five minutes and is able to run continuously for up to 100 hours.

Robert Bryce, Director of Hydro for SSE Renewables, said: "We're delighted our upgrade proposals for Sloy have received planning consent from the Scottish Government. This provides SSE with important optionality for our iconic Sloy Power Station plant, whether as a new pumped storage hydro facility or as a conventional hydro-electric plant with increased generation capacity, and will help ensure Sloy continues to play a vital role in Scotland's energy future.

"We would also like to take this opportunity to thank key stakeholders, local residents and community groups who have engaged with us so positively throughout the development of these proposals. We greatly value the time, feedback and insights shared during the planning process, which have helped shape our approach. Maintaining open and constructive relationships with the communities around Sloy remains extremely important to us."

Latest Construction News

20/10/2026
Scotland's leading public sector framework provider has opened bidding for a £900 million Refurbishment and Modernisation programme aimed at delivering urgent and planned works across housing and public buildings. The Scottish Procurement Alliance's Refurbishment and Modernisation framework (RM4S)
Read More
20/10/2026
A £1 million grant programme has been launched to help owners return vacant listed buildings across Glasgow to productive use. The Heritage Building Viability Grant Scheme, funded by Glasgow City Council and administered by Glasgow City Heritage Trust, is designed to bring floorspace in some of the
Read More
20/10/2026
Road resurfacing on the A702 at West Linton will take place over six nights from Monday 9 to Friday 13 November, and on Monday 16 November 2026, requiring overnight closures. Transport Scotland's operating company, BEAR Scotland, will deliver the scheme. For safety, the A702 will be closed each ni
Read More
20/10/2026
SP Energy Networks chief executive Nicola Connelly has welcomed the launch of a new industry plan setting out how the biggest grid upgrade in living memory will boost employment and economic growth across the UK. The Electricity Networks Sector Growth Plan – led by the Energy Networks Association (
Read More
20/10/2026
An £8 million scheme is under way to enhance accessibility for passengers at Dalwhinnie and improve performance on the Highland Main Line. The project will install a new crossover so trains can switch between tracks, enabling northbound services to use Platform 1 when step-free access is required.
Read More
20/10/2026
The Scottish Government intends to award Wills Bros Civil Engineering Ltd the contract to dual the A9 between Pitlochry and Killiecrankie, Economy, Tourism and Transport Secretary Stephen Flynn has announced. The move represents the final stage of procurement for the fifth A9 Dualling scheme to rea
Read More
20/10/2026
Residents in Clackmannanshire are already benefiting from a new electric nine-seater minibus provided by Robertson Construction Central East, part of the contractor's social value commitments linked to the Wellbeing Village and Lochies School development in Alloa. During construction, the vehicle i
Read More
20/10/2026
A major new study will examine how climate change could trigger cascading disruption across Scotland's critical infrastructure, giving organisations a clearer view of risks to the services people rely on daily. Commissioned by the Climate Ready Infrastructure Scotland Forum (CRIS) — a partnership o
Read More
20/10/2026
Clark Contracts has secured a place on Pagabo's Major Works Framework, enhancing its ability to support public sector bodies in delivering major construction and refurbishment schemes. The framework, expected to be worth up to £5bn over four years, follows the creation of a 10-year strategic delive
Read More
20/10/2026
North Ayrshire Council has carried out its annual winter dry run this month as it gets ready for the colder months. Roads staff took part in the exercise as part of preparations to keep roads, footways and communities safe and accessible during severe weather. It follows a meeting of Cabinet at wh
Read More
SEEIT3DWestermans International LtdGMAC Utilities LtdGrampian Steel Buildings LtdAtlas Winch & Hoist Services LtdB Home DesignCF Concrete PumpingDublcheck Cleaning GlasgowCRGP LimitedKrew-base