SSEN Transmission has revised plans for a temporary construction compound near Contin after listening to concerns raised by the local community during consultation and engagement.
The facility, which will support delivery of the mainland underground cable section of the Western Isles HVDC Link, will now be built approximately 500 metres south-east of the original proposal, moving it further from Loch Kinellan and nearby breeding bird habitats. The change is being taken forward in partnership with local contractor RJ McLeod.
The footprint has been cut to less than two hectares. The new site benefits from stronger natural screening to help reduce visual and lighting effects, while a new access arrangement is intended to minimise construction traffic and lower the amount of tree removal required.
Preparatory works are due to begin on Monday 27 July, a week ahead of main construction starting on 3 August, and are expected to last about 12 weeks. Activity will include creating a temporary hardstanding and compound, providing access to the mainland cable route corridor, and accommodating project offices, welfare facilities, and equipment and material storage during construction.
Traffic flows for residents and pedestrians will be maintained throughout, with continued access to the core path network. No disruption to local residents, pedestrians or road users is expected as a result of the works.
Niall Macleod, Project Director for SSEN Transmission, said: "We are committed to working closely with local communities and our partners to ensure the mainland cable section of the Western Isles HVDC Link is delivered safely and responsibly.
"The relocation of the temporary compound is a direct result of feedback from the local community, including community councils and The Highland Council. It demonstrates our willingness to listen to concerns and adapt our plans where possible.
"The Western Isles HVDC Link is a vital project that will enable new clean power generation, strengthen energy security, and deliver substantial economic and lasting local benefits.
"The mainland underground cable connection is a key part of the project, and we'd like to thank local communities for engaging with us as we work to deliver it in a way that reflects their views. We will continue to engage openly throughout construction and provide regular updates as the project progresses."