Super Grid Transformers Set To Be Delivered To Creag Dhubh

Construction News Image

Traffic restrictions will be brought in along sections of the A82 from this week to facilitate the movement of two new Super Grid Transformers to SSEN Transmission's Creag Dhubh substation in Argyll.

The staged deliveries, due to take place between Thursday 4 June and Thursday 18 June, are part of a carefully co‑ordinated logistics operation. The transformers are being shipped from Poland to Clydebank before continuing by road to the substation site near Cladich, a journey of around 90 miles.

Super Grid Transformers are among the largest assets on the electricity network, typically weighing several hundred tonnes. They step voltage up or down to enable the efficient transmission of power across the grid.

Moving equipment of this scale requires specialist transport, detailed planning and robust traffic management. SSEN Transmission has worked closely with Transport Scotland, BEAR Scotland, Police Scotland and local authorities to organise the operation and limit disruption as far as possible.

To allow the heavy loads to safely cross infrastructure near Crianlarich, temporary overnight closures are planned on a short stretch of the A82 between Crianlarich and Tyndrum at:

-- Advertisement --
NorthernAsbestosServicesLtd

- Sunday 7 June to Monday 8 June (10pm to 5am)

- Tuesday 16 June to Wednesday 17 June (10pm to 5am)

This will involve closing the A82 at Inverherive at the Herive Burn so the convoy can pass safely. A purpose-built bridging deck will be installed over the existing bridge to provide extra reinforcement during the crossing. Diversions and signage will be in place, and access for emergency services will be maintained.

Further traffic management will support the wider delivery programme. An inside-lane layby between Firkin and Rossdarroch on the A82 south of Tarbet will be closed from Tuesday 2 June to Friday 19 June, with temporary overnight traffic signals in use while the layby is operational to manage flows.

Temporary parking restrictions are also scheduled on Dumbarton Road on Thursday 4 June to Friday 5 June, and Wednesday 10 June to Thursday 11 June, to ensure the safe passage of delivery vehicles.

Drivers are advised to plan ahead, allow extra time and follow all signage and diversion routes. All dates remain weather-dependent and subject to ongoing co‑ordination with partner organisations.

Lee Biddulph, SSEN Transmission's Project Manager for the Creag Dhubh substation project, said: "We recognise these restrictions may cause some disruption and would like to thank local communities and road users for their patience while this complex operation is carried out.

"These transformers are critical to strengthening the local transmission network and supporting the growth of renewable energy in Argyll.

"Transporting components of this scale is a complex operation, which is why we have worked closely with our road traffic partners to plan deliveries carefully and keep disruption to a minimum, with all scheduled closures and restrictions dependent on weather conditions and coordination with key partner organisations.

"We encourage people to plan ahead, allow extra time for their journeys, and follow all signage and diversion routes to help keep everyone safe."

Latest Construction News

23/07/2026
GRAHAM has formally handed over the 321-studio St Vincent Studios purpose-built student accommodation to developer Artisan Real Estate, completing the £38m scheme in Glasgow city centre ahead of the 2026/27 academic year. The development on St Vincent Street was delivered by GRAHAM on behalf of Art
Read More
23/07/2026
SP Energy Networks has submitted a Section 37 consent application to the Scottish Government's Energy Consents Unit (ECU) for major upgrades to the electricity transmission network between Denny in Stirlingshire and Wishaw in Lanarkshire. Known as the Denny to Wishaw Network Upgrade (DWNO), the sch
Read More
23/07/2026
NFRC is urging members to help shape a new Government strategy for built environment professions, as the sector adjusts to the Building Safety Regime and renewed expectations on competence, professionalism and accountability. NFRC recently took part in a Build UK forum with the Building Professions
Read More
23/07/2026
Scottish Renewables has opened entries for The Scottish Green Energy Awards 2026, inviting nominations across 12 categories ahead of a December ceremony in Edinburgh. Submissions close at 5pm on Tuesday 8 September. Nominations are open now for The Scottish Green Energy Awards 2026, billed as the U
Read More
23/07/2026
Scottish and Southern Electricity Networks (SSEN) has launched a pilot to upgrade domestic electricity connections, aiming to help households adopt cost-saving, low-carbon technologies more easily. The programme will initially deliver improvements for hundreds of customers as part of SSEN's broader
Read More
23/07/2026
Ferryhill Road is set to reopen by late August while SSEN Transmission pursues investigations on South College Street to fix a damaged duct; a further short closure of around four weeks will follow to complete cable installation and permanently reinstate the road. Traffic restrictions on Ferryhill
Read More
23/07/2026
The Engineering Construction Industry Training Board's (ECITB) Project Management Steering Group (PMSG) has unveiled a new e-learning academy to strengthen project management capability across the engineering construction industry (ECI). Hosted on ECITB's award-winning Learning Experience Platform
Read More
23/07/2026
Energy remains front of mind for many Glasgow firms, from controlling spend and tracking usage to meeting rising expectations on sustainability. In a conversation with the Glasgow Chamber of Commerce, Andrew Ward, CEO of Customer Business at ScottishPower, described the support on offer to help comp
Read More
22/07/2026
The £26m Grade A office at Dundee Waterfront, delivered by Robertson for Dundee City Council as part of the city's £1.6bn regeneration programme, has reached full occupation after global software firm N-able joined existing tenant Thorntons. Built by Robertson Construction Tayside, the six-storey J
Read More
22/07/2026
Ground has broken on a permanent spectator stand and team dugouts at the Meadowbank grass pitch at Kirkwall Grammar School (KGS). The project is fully funded by the Scottish Football Association and was proposed by the newly formed Orkney Football Hub, which brings together representatives from Ork
Read More
SEEIT3DTHE HOME ARCHITECTWT ConsultancyDonnelly Safety ServicesCTW Safety LTDBusiness Solutions (SW) LTD123vNormac Oils LtdRox ElectricalCaledonia Crane Hire Ltd