Subscribe to our Construction Newsfeed
Scotland Construction Directory
Search our 14,045 companies....

Construction News

15/01/2026

Scottish Govt Unveils Plan To Complete A9 Dualling by 2035

Transport Secretary Fiona Hyslop MSP has announced the Scottish Government's 2026 Delivery Plan for the A9 Dualling Programme, confirming that all remaining sections of the multi-billion-pound project will now be delivered using capital funding.

This shift in strategy follows the decision to move away from previously considered private finance models to ensure the programme meets its final completion target of 2035.

The updated plan introduces a new ordering of works that prioritises safety improvements in the Highlands. Specifically, construction on three busy grade-separated junctions serving Carrbridge and Aviemore will be brought forward. These upgrades are scheduled as part of the section between Dalraddy and Slochd, which is expected to be operational by 2032. Once finished, this will create approximately 38 miles of continuous dual carriageway between Inverness and Kincraig.

The 2026 Delivery Plan also accelerates the delivery of the grade-separated junction at Dalnaspidal and the Aviemore to Carrbridge Non-Motorised User Route (ACNMU). To improve efficiency, the government will establish a Framework Agreement to streamline the procurement of the five remaining contracts.

-- Advertisement --
NorthernAsbestosServicesLtd

Cabinet Secretary for Transport, Fiona Hyslop MSP said: "This announcement maintains the Scottish Government commitment to having dualling operational between Perth and Inverness by the end of 2035.

"Our 2026 Delivery Plan provides more detail and certainty for the market and brings forward key elements of the Programme in the North section of the Programme. This will be reassuring news for local communities in Aviemore and Carrbridge.

"With construction activity already taking place on 11 miles of the corridor, our plan will continue to ramp up that work, with 50% of the route between Perth and Inverness to be operating as dual carriageway by the end of 2030 – rising to 67% by the end of 2032. With 100% dualling achieved by the end of 2035.

"The 2026 Delivery Plan and establishment of the Framework Agreement will be subject to further market consultation with the industry, which is expected to commence on 19 January 2026.

"It is expected the Framework will commence procurement in Spring 2026 with participants being appointed to the Framework by the end of 2026. This will assist in securing market capacity giving more certainty to communities and drivers that this Plan will complete dualling by 2035."

Industry leaders have welcomed the move toward capital-funded contracts. David Macdonald, Chairman of the Civil Engineering Contractors Association (CECA) Scotland, stated: "CECA welcome the news that the remaining A9 Dualling Programme sections will be taken forward as capitally-funded contracts, providing more certainty for Scotland's contracting industry of the opportunities available on this major infrastructure programme for Scotland. We look forward to continuing to engage with Transport Scotland throughout the procurement process."

The massive engineering undertaking involves the construction of over 130 new structures and the movement of 20 million cubic metres of earthworks. Beyond infrastructure, the programme aims to deliver social value by supporting SMEs, creating apprenticeships, and prioritising low-carbon construction methods on-site.

Latest Construction News

20/07/2026
SSEN Transmission has begun drilling at Rattray Head, near Peterhead, marking a key construction milestone for the Spittal to Peterhead High Voltage Direct Current (HVDC) scheme. Work that commenced this month involves Horizontal Directional Drilling (HDD) beneath the coastline to forge the critica
Read More
20/07/2026
Family-owned, Glasgow-based housebuilder AS Homes Scotland has submitted a planning application for 59 new affordable homes in Glasgow's East End, in partnership with Home Group, one of the UK's largest providers of high-quality housing and integrated health and social care support. Located on the
Read More
20/07/2026
The Construction Industry Training Board (CITB) and the Federation of Master Builders (FMB) have launched a new RMI (Retrofit) Sector Skills Plan, developed with input from the Sector Advisory Group on which NFRC sits. NFRC has welcomed the plan and its aims. Focusing on domestic retrofit and on he
Read More
20/07/2026
Three Robertson-delivered projects have been recognised by the Royal Institution of Chartered Surveyors (RICS) as exemplars of the built and natural environment across the UK at recent regional ceremonies. In Scotland, the comprehensive refurbishment of BlackRock's Edinburgh office secured the Comm
Read More
20/07/2026
Glasgow city centre will be handed over to families for a celebratory weekend as the refurbishment of George Square reaches its next milestone. The phased reopening is already under way, with the north carriageway returning to use on 26 June following works that began in May last year. Plans are b
Read More
20/07/2026
As Andy Burnham prepares to enter Downing Street, the Federation of Master Builders (FMB) has urged the incoming Prime Minister to prioritise rapid housing delivery and targeted support for small construction firms as the economy stagnates. Making the call, Brian Berry, Chief Executive of the FMB s
Read More
20/07/2026
Scottish Ministers have granted consents and marine licences for the North and South Caledonia offshore wind farms in the Moray Firth. Together, the schemes will cover around 429 km² and host up to 140 wind turbines. According to the projects, they could generate enough electricity annually to supp
Read More
20/07/2026
SSEN Transmission has revised plans for a temporary construction compound near Contin after listening to concerns raised by the local community during consultation and engagement. The facility, which will support delivery of the mainland underground cable section of the Western Isles HVDC Link, wil
Read More
17/07/2026
Construction has begun on a new £3.3 million paint facility at BAE Systems’ Govan shipyard in Glasgow as part of a wider programme to modernise the city's naval shipbuilding infrastructure. The new facility will allow ship blocks to be painted in a dedicated space, freeing up existing areas at the
Read More
17/07/2026
Retrofit and energy-efficiency specialist Procast Group has secured two awards at the Energy Efficiency Awards, with apprentice electrician Cameron Sleith also recognised as Apprentice of the Year. The company was named Regional Insulation & Fabric Installer and Contractor of the Year at the awards
Read More
SEEIT3DTennants (Elgin) LtdCF Concrete PumpingDiscount Kitchens and Bathrooms LtdTREND Transformations PerthMediaCo GroupCRGP LimitedK & I Paterson LtdAtlas Winch & Hoist Services LtdDublcheck Cleaning Glasgow