Scottish Govt Unveils Plan To Complete A9 Dualling by 2035

Transport Secretary Fiona Hyslop MSP has announced the Scottish Government's 2026 Delivery Plan for the A9 Dualling Programme, confirming that all remaining sections of the multi-billion-pound project will now be delivered using capital funding.

This shift in strategy follows the decision to move away from previously considered private finance models to ensure the programme meets its final completion target of 2035.

The updated plan introduces a new ordering of works that prioritises safety improvements in the Highlands. Specifically, construction on three busy grade-separated junctions serving Carrbridge and Aviemore will be brought forward. These upgrades are scheduled as part of the section between Dalraddy and Slochd, which is expected to be operational by 2032. Once finished, this will create approximately 38 miles of continuous dual carriageway between Inverness and Kincraig.

The 2026 Delivery Plan also accelerates the delivery of the grade-separated junction at Dalnaspidal and the Aviemore to Carrbridge Non-Motorised User Route (ACNMU). To improve efficiency, the government will establish a Framework Agreement to streamline the procurement of the five remaining contracts.

-- Advertisement --
NorthernAsbestosServicesLtd

Cabinet Secretary for Transport, Fiona Hyslop MSP said: "This announcement maintains the Scottish Government commitment to having dualling operational between Perth and Inverness by the end of 2035.

"Our 2026 Delivery Plan provides more detail and certainty for the market and brings forward key elements of the Programme in the North section of the Programme. This will be reassuring news for local communities in Aviemore and Carrbridge.

"With construction activity already taking place on 11 miles of the corridor, our plan will continue to ramp up that work, with 50% of the route between Perth and Inverness to be operating as dual carriageway by the end of 2030 – rising to 67% by the end of 2032. With 100% dualling achieved by the end of 2035.

"The 2026 Delivery Plan and establishment of the Framework Agreement will be subject to further market consultation with the industry, which is expected to commence on 19 January 2026.

"It is expected the Framework will commence procurement in Spring 2026 with participants being appointed to the Framework by the end of 2026. This will assist in securing market capacity giving more certainty to communities and drivers that this Plan will complete dualling by 2035."

Industry leaders have welcomed the move toward capital-funded contracts. David Macdonald, Chairman of the Civil Engineering Contractors Association (CECA) Scotland, stated: "CECA welcome the news that the remaining A9 Dualling Programme sections will be taken forward as capitally-funded contracts, providing more certainty for Scotland's contracting industry of the opportunities available on this major infrastructure programme for Scotland. We look forward to continuing to engage with Transport Scotland throughout the procurement process."

The massive engineering undertaking involves the construction of over 130 new structures and the movement of 20 million cubic metres of earthworks. Beyond infrastructure, the programme aims to deliver social value by supporting SMEs, creating apprenticeships, and prioritising low-carbon construction methods on-site.

Latest Construction News

04/09/2026
Morgan Sindall Construction has been appointed by the Scottish Fire and Rescue Service (SFRS) to demolish and rebuild the Liberton station in the capital. Procured via the SCAPE Scotland Construction Framework, the £10m scheme marks a significant investment in SFRS infrastructure and will create a
Read More
03/09/2026
Network Rail says it has hit a key milestone in efforts to strengthen Scotland's railway against severe weather, with £130m invested in resilience over the last two years. The move comes amid tougher operating conditions, including higher temperatures, increasingly unpredictable rainfall and more f
Read More
04/09/2026
ESB has reached Final Investment Decision (FID) and executed the principal construction agreements for the 96MW Chleansaid Wind Farm, near Lairg in the Scottish Highlands. The move signals the start of delivery for one of the utility's most strategic renewable projects and its first ESB-developed on
Read More
04/09/2026
Glasgow City Region has welcomed confirmation of £22.7 million in first-year funding from the UK Government's Local Growth Fund, aimed at accelerating business growth, improving skills and employability, and creating new commercial space across the area. The award represents the opening phase of a
Read More
04/09/2026
A major planned maintenance scheme has begun across East Renfrewshire, with 190 council homes set to receive new kitchens in the first year of works. The initiative is part of East Renfrewshire Council's longer-term investment in its housing stock. Approximately 300 kitchens are due to be replaced
Read More
04/09/2026
A £9.8m Local Growth Fund programme for the Forth Valley has moved into delivery after the UK Government approved the region's Investment Plan, paving the way for projects to boost businesses, skills, housing and infrastructure across Falkirk, Stirling and Clackmannanshire. Following approval of th
Read More
04/09/2026
Approval of a new Local Growth Fund Investment Plan will deliver £11.8 million to Ayrshire between 2026 and 2029, targeting higher household incomes and stronger local economies through infrastructure, business support and skills. The funding reflects the collective ambition of the Ayrshire Regiona
Read More
04/09/2026
SNIPEF's State of Trade Survey for the first quarter of 2026 points to steady activity tempered by growing caution. Work volumes have held up, payment performance is broadly consistent and product availability remains manageable. However, order books are more finely balanced, margins are under press
Read More
04/09/2026
Farrans has been appointed by ESB to deliver the Civil Balance of Plant (CBoP) for the 96MW Chleansaid Wind Farm near Lairg in the Scottish Highlands. The contract signals the start of delivery on one of ESB's most strategically important renewable schemes and marks its first onshore wind project i
Read More
03/09/2026
Sky has secured planning permission for its new Livingston Campus, unlocking a major investment and underscoring the company's long-term commitment to Scotland. The decision marks a key step towards delivering a significant new workplace development in West Lothian. The approved plans will bring Sk
Read More
SEEIT3DCF Concrete PumpingDublcheck Cleaning GlasgowCRGP LimitedKrew-basePro Vent ComplianceKelly TanksDiscount Kitchens and Bathrooms LtdDunedin Stone LtdGreater Good Glass Ltd