The world's first unmanned High Voltage Direct Current (HVDC) offshore substation has been successfully installed at the site of what will be the world's largest offshore wind farm, Dogger Bank.
The substation is the first of three platforms, supplied by Aibel, to be installed at Dogger Bank, which is being constructed in three 1.2GW phases known as A, B and C.
The Dogger Bank A platform measures 65 x 36 metres across and 39 metres high and sits on a four-legged steel jacket foundation structure which is fixed to the seabed, at a water depth of around 28m. Approximately 146km from the nearest point of land at Flamborough Head, near Bridlington in East Riding of Yorkshire, the platform installation was delivered by principal contractor Sapiem.
The innovative offshore platform has a lean design and is the first unmanned HVDC platform which will be operated from shore and accessed only by a Service Operations Vessel. The platform will receive 1.2GW of AC power from Dogger Bank A's 95 offshore wind turbines and convert it to DC, which will then be sent ashore to an onshore convertor station near Beverley in East Riding of Yorkshire.
Fitted with Hitachi Energy's latest generation HVDC converter technology, Dogger Bank will be the first offshore wind project in the UK to use this technology to transmit the electricity produced back to shore, ensuring that the electricity is transmitted efficiently over long distances while minimising losses.
Olly Cass, Project Director for Dogger Bank Wind Farm, said: "The safe and successful installation of the offshore platform marks a major milestone in the Dogger Bank project. As the UK's first HVDC platform for an offshore windfarm it is also a major milestone for the UK industry more widely.
"The platform will be controlled from shore and by removing the need for personnel to stay on the platform meant it has been possible to eliminate elements such as the living quarters, helideck and sewage systems, resulting in a 70% reduction in weight (per megawatt) of the topside compared to previous platforms installed, and cost savings of hundreds of millions of pounds.
"Teams continue to make good progress with the installation of turbine foundations and later in Q2 specialist cable installation and support vessels will start to install the inter-array network of cables that will connect the turbines to the offshore platform to enable transmission of first power in the summer."
Dogger Bank Wind Farm, a joint venture between SSE Renewables, Equinor, and Vårgrønn, is set to be the world's largest offshore wind farm consisting of 277 wind turbines. The wind farm will be capable of of generating 3.6GW of renewable energy which is enough clean and sustainable electricity to power more than 6 million homes.
Construction News
20/04/2023
Dogger Bank: World's First Unmanned HVDC Offshore Substation Installed


07/05/2025
Scottish housebuilder Cruden Homes, in a joint venture with Evantyr Properties, has acquired a new development site on Salamander Street in Leith, Edinburgh. The acquisition is part of the ongoing regeneration efforts in the formerly industrial area.
The proposals for the site outline plans for a n

07/05/2025
Architect and television presenter George Clarke visited a housing development in Banchory, Aberdeenshire, this past weekend to draw attention to the critical importance of home and the pressing need for increased housebuilding levels across Scotland.
The visit, facilitated by industry body Homes f

07/05/2025
The Engineering Construction Industry Training Board (ECITB) has committed £400,000 to support the delivery of the new Energy Transition Skills Hub in the North East of Scotland.
This investment will specifically fund the equipping and fitting out of a modern welding academy within the facility, f

07/05/2025
The finalists for the 18th annual Scottish Home Awards, sponsored by Ross & Liddell, have been announced today (Wednesday, 7 May 2025).
Following a rigorous judging session last week where a panel of industry experts reviewed over 140 entries, a strong shortlist has been selected across 19 diverse

07/05/2025
Fife Council is pushing forward with its affordable housing ambitions, with new council house developments progressing in Dunfermline, Lochgelly, and Cowdenbeath.
In Dunfermline, the council is finalising an agreement with Campion Homes to deliver 41 new council houses on the site of the former cou

07/05/2025
An innovative research project led by Wheatley Group, one of Scotland's largest housing groups, aims to transform future social housing construction and reduce tenant energy bills. The Scottish-first trial is being conducted at Wheatley's new Shandwick Street development in Easterhouse, Glasgow, in

07/05/2025
CCG (Scotland) and its private housing arm, CCG Homes, have been named as finalists in multiple categories at the prestigious Scottish Home Awards 2025. The 18th annual awards ceremony is a major event for Scotland's housing industry.
Following their 2024 win for Excellence in Sustainability for th

07/05/2025
Seven rising stars in Scotland's green energy sector were recognised for their outstanding contributions at the Young Professional Green Energy Awards 2025.
The annual event, organised by Scottish Renewables, highlights the pioneering individuals poised to reshape the nation's clean power future.

07/05/2025
Mears Group has announced its reappointment as the repairs and maintenance contractor for Govanhill Housing Association, continuing its responsibility for the upkeep of approximately 3,000 properties in the area.
The new contract is valued at £2 million per annum and will run for an initial five-ye

07/05/2025
Twenty newly built homes have been handed over to Perth & Kinross Council at the new Kinloch Gardens development, located adjacent to Glenalmond Road in Rattray.
This project is a key component of the council's ongoing multi-million-pound new build housing programme, which has successfully deliver