Major Milestone Reached Of Final Concrete Pour At Viking Energy Wind Farm

The concrete has been successfully poured for the final wind turbine base at the ongoing Viking Energy Wind Farm development.

The concrete pour process started in September 2021 and since then over 70,246m³ of concrete has been poured across 103 of the foundations. Concrete was produced from two batching plants that were created on site due to the high volumes required. Each concrete pour on average took 11 hours to complete, with over 30 people involved in each concrete pour from start to finish.

The turbine foundations were designed by engineering consultants Tony Gee and Partners LLP and construction operations were carried out by principal contractor RJ McLeod and its sub-contractors.

The construction process involved teams excavating material from site before installing the reinforcement which was then followed by the pouring of concrete. Once the concrete had cured, the base was then backfilled with the excavated material, leaving only the centre ring showing, ready for the turbine tower to be bolted on.

In early 2023, the next phase of the project will begin with the arrival of the 4.3MW Vestas turbines on site. The turbines will have a maximum tip height of 155m.

Derek Hastings Head Of Onshore Projects For SSE Renewables, said: "The last concrete pour was completed on Saturday 12 November, and it marks a significant construction milestone at Viking Wind Farm. From the first concrete pour in September 2021, it's been a real team effort to get to 103 bases poured on site and it's a huge success to deliver this milestone ahead of programme.

-- Advertisement --
NorthernAsbestosServicesLtd

"We're now looking forward to the next stage of the project which will see Vestas turbines being delivered on site in early 2023 ahead of installation. Viking Energy Wind Farm is on course to go into renewable energy production in 2024 and is expected to be the most productive onshore wind farm in the UK when complete."

Peter Mcdonald Power Group Director For Tony Gee, said: "With COP27 well underway, at Tony Gee we are celebrating a milestone in helping the UK get one step closer to de-carbonising the energy sector.

"Having been involved with Viking Energy Wind Farm since 2015 it is fantastic to see the scheme reach this significant milestone and recognises the hard work from the whole project team. It has been great to see the implementation of our innovative design for the turbine base. Our solution resulted in greater than 30% reduction in concrete volume compared to previous design techniques."

Ryan Maclean Project Manager For RJ McLeod, said: "Completing the final foundation concrete pour is a massive achievement for the whole project. The production of large concrete foundation pours had many challenges including weather, material transportation and the logistical issues that come with being in a remote island. To have now reached this milestone is testament to the hard work and dedication of all involved, not least the local Contractors whose island expertise was essential to the smooth running and programming of the foundation construction works.

"We look forward to welcoming Vestas onto the project early next year for the turbine installation and the construction completion of Viking Energy Wind Farm."

Shetland contractors and suppliers are continuing to play a key part in wind farm construction. The project is supporting the islands', Scottish and wider UK supply chains during delivery, creating around 400 jobs at peak construction with turbine supplier Vestas now also awarding contracts and recruiting long-term local operations and maintenance teams, including apprentices.

Viking will be the UK's largest onshore wind farm in terms of annual electricity output once complete in 2024, playing a crucial role in contributing towards the UK and Scotland's net zero targets. It will be able to meet the needs of 475,000 homes and save half a million tonnes of carbon dioxide every year.

Latest Construction News

20/10/2026
Scotland's leading public sector framework provider has opened bidding for a £900 million Refurbishment and Modernisation programme aimed at delivering urgent and planned works across housing and public buildings. The Scottish Procurement Alliance's Refurbishment and Modernisation framework (RM4S)
Read More
20/10/2026
A £1 million grant programme has been launched to help owners return vacant listed buildings across Glasgow to productive use. The Heritage Building Viability Grant Scheme, funded by Glasgow City Council and administered by Glasgow City Heritage Trust, is designed to bring floorspace in some of the
Read More
20/10/2026
Road resurfacing on the A702 at West Linton will take place over six nights from Monday 9 to Friday 13 November, and on Monday 16 November 2026, requiring overnight closures. Transport Scotland's operating company, BEAR Scotland, will deliver the scheme. For safety, the A702 will be closed each ni
Read More
20/10/2026
SP Energy Networks chief executive Nicola Connelly has welcomed the launch of a new industry plan setting out how the biggest grid upgrade in living memory will boost employment and economic growth across the UK. The Electricity Networks Sector Growth Plan – led by the Energy Networks Association (
Read More
20/10/2026
An £8 million scheme is under way to enhance accessibility for passengers at Dalwhinnie and improve performance on the Highland Main Line. The project will install a new crossover so trains can switch between tracks, enabling northbound services to use Platform 1 when step-free access is required.
Read More
20/10/2026
The Scottish Government intends to award Wills Bros Civil Engineering Ltd the contract to dual the A9 between Pitlochry and Killiecrankie, Economy, Tourism and Transport Secretary Stephen Flynn has announced. The move represents the final stage of procurement for the fifth A9 Dualling scheme to rea
Read More
20/10/2026
Residents in Clackmannanshire are already benefiting from a new electric nine-seater minibus provided by Robertson Construction Central East, part of the contractor's social value commitments linked to the Wellbeing Village and Lochies School development in Alloa. During construction, the vehicle i
Read More
20/10/2026
A major new study will examine how climate change could trigger cascading disruption across Scotland's critical infrastructure, giving organisations a clearer view of risks to the services people rely on daily. Commissioned by the Climate Ready Infrastructure Scotland Forum (CRIS) — a partnership o
Read More
20/10/2026
Clark Contracts has secured a place on Pagabo's Major Works Framework, enhancing its ability to support public sector bodies in delivering major construction and refurbishment schemes. The framework, expected to be worth up to £5bn over four years, follows the creation of a 10-year strategic delive
Read More
20/10/2026
North Ayrshire Council has carried out its annual winter dry run this month as it gets ready for the colder months. Roads staff took part in the exercise as part of preparations to keep roads, footways and communities safe and accessible during severe weather. It follows a meeting of Cabinet at wh
Read More
SEEIT3DDiscount Kitchens and Bathrooms LtdDunedin Stone LtdMaterials Market UK Trading LtdForde Training Services LtdGreater Good Glass LtdCountryside KitchensDenfind Stone LimitedKattrak International LtdVisual Precision Ltd