04/04/2019

New Phase Of Great Glen Water Works Underway

A new phase of work has begun to install around 5 miles of new water main along the Great Glen Way, between Fort Augustus and Glenmoriston, as part of a £21 million investment in the area's water supply. The work is being carried out on Scottish Water's behalf by its alliance partner, Efficient Service Delivery (ESD).

Since work began in December, around 2 miles of water main has already been laid. The second phase of planned closures affecting the normal route of the Great Glen Way is now beginning, with signposted alternatives in place and a shuttle vehicle operating between Allt na Criche and Fort Augustus.

The new water main is a key part of a major project to provide a single, improved water supply to around 1250 Scottish Water customers in Fort Augustus and Glenmoriston, as well as catering to significant seasonal demand in the area from tourism.

The second phase of work on the Great Glen Way will involve closure of the normal route between Allt na Criche and Fort Augustus for around 6 weeks. A higher alternative route will be signposted using forestry tracks and part of the Old Military Road, which adds just over 4 miles to the route. Over this period, a shuttle vehicle will also operate every day from 8:30am until 4:30pm between the Allt na Criche car park and Fort Augustus village hall car park.

-- Advertisement --
NorthernAsbestosServicesLtd

As during the earlier phase of work, the lower route of the Great Glen Way will also remain closed between Allt na Criche and Invermoriston with a signposted diversion via the established higher route.

ESD's Project Manager Kelton Bennett said: "Our team on site is continuing to work to install the section of water main that follows the Great Glen Way efficiently and safely, so that the route can be returned to normal as quickly as possible. 

"We have been encountering some challenging, rocky ground conditions so we are also deploying a specialised trenching machine to speed up progress.

"So far, the signposted diversions have been working smoothly over a period where user numbers on the Great Glen Way are relatively low. During the phase of work ahead, we are also providing a shuttle vehicle between Allt na Criche and Fort Augustus for anyone who does not wish to take the longer alternative route."

Scottish Water Corporate Affairs Manager Gavin Steel added: "The investment that we are making will bring lasting benefits to the local area and its economy. We recognise that it also involves some short term disruption, particularly to the Great Glen Way. 

"The phase of work now beginning involves a longer and more challenging alternative route. Following engagement with the local community and with Highland Council last year, we are providing a shuttle vehicle as an alternative option to ensure that local residents and visitors can continue to enjoy the Great Glen Way safely. We would encourage people either to follow the signposted alternative route or to make use of the shuttle vehicle, as there is no footpath on this section of the A82.

"We will continue to work with local residents and businesses as work progresses to keep them informed and listen to any feedback on the arrangements."

Latest Construction News

24/07/2026
SSE has received Section 36 planning consent from the Scottish Government to upgrade its 152.5MW Sloy Hydro-electric Power Station at Inveruglas on the western shore of Loch Lomond. The consent provides the option to convert the existing plant into a pumped storage hydro scheme capable of deliverin
Read More
24/07/2026
Scotland's essential mineral producers have published a new report calling on the Scottish Government to unlock economic growth, streamline planning procedures, and support the construction supply chain. In its publication, Priorities for Scotland, the Mineral Products Association Scotland (MPAS) w
Read More
24/07/2026
Scotland's National Retrofit Centre (SNRC) has been shortlisted in the AJ Retrofit & Reuse Awards' Adaptive Reuse into Other category, recognising an ambitious decarbonisation demonstrator delivered with BE-ST, Clark Contracts and John Gilbert Architects (JGA). Run by The Architects' Journal, the a
Read More
24/07/2026
The veteran-owned company, staffed by former military combat medics, delivers on-site emergency care during working hours for teams installing the mainland cable between Dundonnell and Beauly. Backed by SSEN Transmission and contractor RJ McLeod, Spark Medical Ltd has joined GoodSAM, the volunteer
Read More
24/07/2026
Harry has completed a four-week paid work placement with Maxi Construction through the Career Ready programme. He began with Health and Safety Awareness training to build a solid foundation before joining site teams. During the placement he worked alongside Site Managers and shadowed a range of tra
Read More
24/07/2026
McTaggart Construction, a leading affordable housing contractor in Scotland, is marking a notable double milestone as four long-serving colleagues celebrate 20 years with the business in the same year the company turns 80. Office Manager Kim Easton, Payroll Manager Lorraine Brackenridge, Site Manag
Read More
24/07/2026
Bucksburn Swimming Pool has reopened following a £2.5m upgrade delivered by Morrison Construction on behalf of Aberdeen City Council, transforming the venue to improve accessibility and energy efficiency. The community facility welcomed visitors back with Olympic swimmer Hannah Miley joining local
Read More
24/07/2026
More than 100 builders came together in Oxfordshire for the FMB's National Conference, which doubled as a milestone celebration of the Federation's 85 years supporting the trade. Staged on 9–10 July at the Oxford Belfry Hotel & Spa, the event welcomed 156 delegates for a Business Conference under t
Read More
23/07/2026
GRAHAM has formally handed over the 321-studio St Vincent Studios purpose-built student accommodation to developer Artisan Real Estate, completing the £38m scheme in Glasgow city centre ahead of the 2026/27 academic year. The development on St Vincent Street was delivered by GRAHAM on behalf of Art
Read More
23/07/2026
SP Energy Networks has submitted a Section 37 consent application to the Scottish Government's Energy Consents Unit (ECU) for major upgrades to the electricity transmission network between Denny in Stirlingshire and Wishaw in Lanarkshire. Known as the Denny to Wishaw Network Upgrade (DWNO), the sch
Read More
SEEIT3DElectrac NISOLV GROUPDryburgh Associates LimitedFyfe BrickworkInverness Core Drilling LtdStuart King Architecture & Design LtdNew Home Quality ControlRural House LtdJames Macqueen Building Contractors Ltd