Scotland TranServ is to begin a £700,000 motorway barrier refurbishment project in Glasgow.
The company will start carrying out maintenance to the central reserve barrier of the M8 at Charing Cross.
The first phase of the project will take place from Monday, 21 November until Friday, 02 December. Phase two will begin on Sunday, 08 January until Friday, 03 March.
Works will take place between 10pm and 6am. Lane closures and diversions will be in place.
Scotland TranServ's operating company representative, Andy Fraser, said: "This vital programme of works will ensure that the central reserve barrier is safe, fit for purpose and meets modern day standards.
"We have programmed the works carefully overnight when traffic flows are expected to be lighter however road users should follow the signed diversion route during the works."