Fife College's new Dunfermline City Campus has successfully passed independent verification for its embodied and whole-life carbon assessments, setting a new standard for sustainable construction in Scotland. The campus, due to open later this year, is the country's first net-zero-ready tertiary education building and has been closely watched by public sector projects nationwide.
The project has achieved an industry-leading embodied carbon footprint of just over 560kg CO2e/m2 for the Teaching Building and a total embodied carbon footprint of 601kg CO2e/m2 for the three buildings comprising the new campus development. This surpasses the initial embodied carbon target of 650kg CO2e/m2, a result achieved through collaborative efforts between all project partners, including architects Reiach and Hall, project managers A10, structural engineers Woolgar Hunter, M&E consultants Horner and McLellan, main contractor Balfour Beatty, and their supply chain.
As a pathfinder project for the Net Zero Public Sector Buildings Standard in Scotland, sustainability has been a core principle of the Dunfermline City Campus from its inception. Cutting-edge construction techniques have been employed to significantly reduce embodied carbon emissions – the carbon footprint associated with materials and construction – which can account for up to 70% of a building's total emissions over its lifetime.
Key sustainability design measures implemented at the new campus include the replacement of traditional concrete floor slabs with Cross Laminated Timber (CLT) planks and innovative green ‘Delta Beams’, fabricated from 95% recycled steel. This combination of CLT and recycled steel has enabled a lighter structural design, thereby reducing the volume of concrete required for both the superstructure and foundations. This approach has resulted in an approximate 20% reduction in the typical embodied carbon expected for a development of this scale.
Fife College, a signatory to the Race to Zero initiative, is committed to addressing all aspects of carbon emissions to align with the 1.5°C global warming limit set by the Intergovernmental Panel on Climate Change (IPCC).
Jim Metcalfe, Fife College Principal, said: "Throughout the construction of our new Dunfermline City Campus, Scotland's first net-zero ready tertiary education building, we have been fully committed to the latest low-energy and net-zero processes. The innovative design of this campus has been a core part of this commitment, and we are immensely proud to have not only met but exceeded our carbon targets."
Stewart MacPhail, Project Director for Balfour Beatty, commented: "Close collaboration with Fife College, the design teams, and our supply chain has been key to delivering the industry-leading carbon performance achieved in the Teaching Building. The successful external verification gives us confidence in the accuracy and integrity of our carbon figures and reinforces what can be achieved through innovation and partnership.”
Jamie Goth, Associate Director - Net Zero for Scottish Futures Trust, which developed the Net Zero Standard for Public Sector Buildings, said: "We are delighted to see this milestone for one of our pathfinder projects. Fife College's Dunfermline City Campus is the first of the pathfinder projects to undertake and confirm external verification of objectives 2 and 4 of the Standard."
Leanne Hannah, Managing Director of external verification body ARMILA Sustainability Services, stated the importance of independent checks: "External verification is an important part of the Net Zero Standard and helps give assurance that the targets set for the project are achievable and that the carbon and whole life models have sufficient detail and include all relevant elements of the build."
Beyond reducing embodied carbon, the construction process incorporated other pioneering sustainability initiatives. Balfour Beatty, in collaboration with Whitecroft Lighting, introduced Geopak, a reusable packaging system for lighting deliveries that eliminated an estimated two tonnes of single-use plastic and cardboard waste. The project also utilised off-site fabrication for several mechanical and electrical components, minimising material waste and reducing on-site labour.
The Dunfermline City Campus, set to welcome students later this year, is part of the new Dunfermline Learning Campus, an integrated project that will also house St Columba's RC High School and Woodmill High School.