Network Rail has announced that they have successfully completed work to install a new railway bridge at Ravenscraig, on the West Coast Mainline (WCML), on-time over the Easter weekend.
Engineers worked around-the-clock for nine days, from April 01 to the early hours of April 10, to successfully move the new 5,000-tonne bridge into position as part of a £16.9 million investment from North Lanarkshire Council and Glasgow City Region City Deal.
Network Rail and STORY Contracting have been working since May 2022 to construct the enormous concrete structure at a compound next to the WCML and had a tight window of opportunity to move it into position over Easter.
The new bridge deck was installed on April 04 after engineers had excavated over 36,000 tonnes of material from the railway embankment to create space for the new structure.
Once in position, the structure was built into the embankment and over the Easter weekend the overhead line equipment and track were reinstated before tamping compacted the new ballast under the railway track.
The bridge enables North Lanarkshire Council to construct a new dual carriageway, with pedestrian and cycle paths from Airbles Road/Windmillhill Street to Robberhall Road, as part of a wider investment to open the area for future development.
Councillor Paul Kelly, depute leader of North Lanarkshire Council, said: "This marks a significant moment in our ambitious plans to redevelop the area. The new road will boost the economy, provide new well-paid jobs and allow so many other exciting developments to take place. I’d like to congratulate everyone involved."
Jeremy Spence, senior programme manager for Network Rail, said: "The successful delivery of this project took many months of meticulous planning and preparation, followed by a huge effort by those on-site working to construct the bridge.
"By working collaboratively with Story Contracting and North Lanarkshire Council, we been able to make sure we seamlessly delivered the work over the crucial last nine days.
"I would also like to thank the local community for the patience they have shown throughout the work."
John MacArthur, managing director of Story Contracting (Scotland), said: "The successful delivery of Europe’s largest concrete structure lift at Ravenscraig is a significant milestone for Story Contracting and testament to the hard work and dedication of the team and our supply chain partners.
"This project showcases our commitment to excellence and our ability to collaborate as Scotland's Railway to deliver high-quality solutions. I am extremely proud of everyone involved in bringing this ambitious project to life."
Construction News
17/04/2023
Network Rail Completes Ravenscraig Bridge Works


12/06/2025
Glasgow City Council has developed a pipeline of potential projects for four city neighbourhoods, aiming to create more walkable, wheelable, and cyclable environments where residents' daily needs can be met within a short distance of their homes. These initiatives, shaped by extensive community inpu

12/06/2025
The UK Government's Spending Review, unveiled on Wednesday 11 June, is set to inject billions of pounds into Scotland, aiming to create thousands of high-skilled jobs and solidify the nation's position as a leader in the clean energy revolution.
The Scottish Government will receive a record real-t

12/06/2025
Perth and Kinross Council is set to invest £97 million in an ambitious overhaul of its leisure facilities, including two options for a new PH2O centre in Perth city centre that incorporate flumes and enhanced leisure water features.
The updated proposals, responding to a mandate from Councillors to

12/06/2025
Roger Bullivant Limited (RBL) has announced the successful installation of its in-house designed and manufactured precast foundation system for a new 46-unit residential development by Dundas in Bishopton. The project highlights RBL's focus on delivering sustainable and cost-effective value-engineer

12/06/2025
A new £115,000 solar project at the waste water treatment works serving Milnathort and surrounding areas has been completed. The initiative involved the installation of 172 solar panels at the site, which are expected to generate 0.07 GWh of green energy annually, fulfilling almost a quarter of the

12/06/2025
Construction of the ambitious "Gro For You" community innovation campus in Tain has taken a significant leap forward, following a crucial £250,000 funding boost from responsible finance provider Social Investment Scotland (SIS). This investment is specifically earmarked to support the initial stages

12/06/2025
Renewable energy company Low Carbon has formally submitted a Section 36 application to the Scottish Government's Energy Consents Unit (ECU) for the proposed Glen Lednock Wind Farm, signalling a significant step forward for the substantial onshore development.
The planned wind farm, located approxim

12/06/2025
Scotland has launched a new £400,000 funding initiative, the Zero Emissions Heavy Duty Vehicle (HDV) Skills Challenge Fund, to prepare its workforce for the transition to zero-emission heavy duty vehicles.
This move is crucial for decarbonising the HDV sector, which involves moving from diesel-pow

12/06/2025
Glasgow has made significant strides in its ambitious plan to expand the city's active travel network, with a recent funding bid submitted to Transport Scotland for 11km of new walking, wheeling, and cycling routes in the Inner North and South areas.
This development is part of a broader initiative

12/06/2025
The first phase of restoration work has begun at Langgarth House in Stirling, over a year after a fire caused extensive damage to the historic building.
This initial stage, which commenced in late May, focuses on securing the structure, salvaging key architectural elements, and carefully removing