Trams To Newhaven Project Enters Final Testing Stage

The first tram has run down Leith Walk in Edinburgh in over 65 years as official testing got underway in the final stages of the Trams to Newhaven project.

Ahead of the route opening for service in spring 2023, a period of testing and commissioning is required to ensure the newly constructed line, software and signals work effectively and safely.

On Monday (13 March), the first stage of testing began, which involves trams travelling at walking pace along small sections of the route, starting at Picardy Place. This will continue through the week, taking place during the night to minimise traffic disruption.

Once the first stage is completed, the frequency and speed of tram testing will increase, and trams will start running to a timetable. Drivers on the route have carried out significant training in the lead-up to testing, including on a state-of-the-art simulator. People are still being encouraged to take care and be aware of the presence of trams on the route for the first time over the coming weeks.

Councillor Scott Arthur, Transport and Environment Convener, said: "This is a huge milestone for Trams to Newhaven as we see the first trams on Leith Walk in my lifetime. We’re fast approaching the start of passenger services this spring, and that the project is set to be delivered on time and within budget, despite the challenges of recent years, is testament to the hard work of all those involved.

-- Advertisement --
NorthernAsbestosServicesLtd

"Bringing the tram to Newhaven will be transformative for the area, and the wider city. As well as boosting the economy and providing sustainable, high-capacity public transport to this densely populated part of Edinburgh, the project has significantly improved the entire route, with new cycle links, spaces to relax and spend time and newly planted trees and shrubs.

"As we enter the final phase of the project, testing and commissioning will make sure the line and infrastructure works safely and efficiently, while also confirming service capacity. Of course, this is the first time there will be trams on Leith Walk and in Leith in recent years so I would urge people to take extra care when in the area."

Lea Harrison, Managing Director of Edinburgh Trams, said: "To see one of our trams running along Leith Walk was a proud moment for us, and this latest milestone in the project will enable us to step up our own preparations for the launch of passenger services to Newhaven.

"This includes real-world driver training on the new section of line following an intense period of familiarisation involving our state-of-the-art tram simulator."

The Trams to Newhaven project remains on schedule for completion by spring 2023 and within the £207.3m budget, with all major construction now complete. A specific date for when the route will be open for passengers will be announced in due course.

As part of the commissioning process every aspect of the new infrastructure will be thoroughly tested to ensure it meets the required safety standards.

There will be some bus diversions around Leith Walk in place overnight during the week commencing 13 March to allow for the testing. The latest information on diversions is available on the Lothian Buses website.

Due to industry wide challenges with the availability of materials and skilled labour, impacted by Brexit and the war in Ukraine along with significant demand for labour in the UK and overseas, there are small pockets of public realm works that will now be completed over the coming months.

Latest Construction News

04/09/2026
Morgan Sindall Construction has been appointed by the Scottish Fire and Rescue Service (SFRS) to demolish and rebuild the Liberton station in the capital. Procured via the SCAPE Scotland Construction Framework, the £10m scheme marks a significant investment in SFRS infrastructure and will create a
Read More
03/09/2026
Network Rail says it has hit a key milestone in efforts to strengthen Scotland's railway against severe weather, with £130m invested in resilience over the last two years. The move comes amid tougher operating conditions, including higher temperatures, increasingly unpredictable rainfall and more f
Read More
04/09/2026
ESB has reached Final Investment Decision (FID) and executed the principal construction agreements for the 96MW Chleansaid Wind Farm, near Lairg in the Scottish Highlands. The move signals the start of delivery for one of the utility's most strategic renewable projects and its first ESB-developed on
Read More
04/09/2026
Glasgow City Region has welcomed confirmation of £22.7 million in first-year funding from the UK Government's Local Growth Fund, aimed at accelerating business growth, improving skills and employability, and creating new commercial space across the area. The award represents the opening phase of a
Read More
04/09/2026
A major planned maintenance scheme has begun across East Renfrewshire, with 190 council homes set to receive new kitchens in the first year of works. The initiative is part of East Renfrewshire Council's longer-term investment in its housing stock. Approximately 300 kitchens are due to be replaced
Read More
04/09/2026
A £9.8m Local Growth Fund programme for the Forth Valley has moved into delivery after the UK Government approved the region's Investment Plan, paving the way for projects to boost businesses, skills, housing and infrastructure across Falkirk, Stirling and Clackmannanshire. Following approval of th
Read More
04/09/2026
Approval of a new Local Growth Fund Investment Plan will deliver £11.8 million to Ayrshire between 2026 and 2029, targeting higher household incomes and stronger local economies through infrastructure, business support and skills. The funding reflects the collective ambition of the Ayrshire Regiona
Read More
04/09/2026
SNIPEF's State of Trade Survey for the first quarter of 2026 points to steady activity tempered by growing caution. Work volumes have held up, payment performance is broadly consistent and product availability remains manageable. However, order books are more finely balanced, margins are under press
Read More
04/09/2026
Farrans has been appointed by ESB to deliver the Civil Balance of Plant (CBoP) for the 96MW Chleansaid Wind Farm near Lairg in the Scottish Highlands. The contract signals the start of delivery on one of ESB's most strategically important renewable schemes and marks its first onshore wind project i
Read More
03/09/2026
Sky has secured planning permission for its new Livingston Campus, unlocking a major investment and underscoring the company's long-term commitment to Scotland. The decision marks a key step towards delivering a significant new workplace development in West Lothian. The approved plans will bring Sk
Read More
SEEIT3DHBB GeoSales LtdFP McCann LtdContainexSEEIT3DHutton Stone Co LtdPinecrest Floors LTDACCON UK LtdContainer Hire Services LtdA.G.S Steel Erectors Ltd