Key Milestone For Trams To Newhaven Project

Construction News Image
The City of Edinburgh Council has announced a key milestone for the Trams to Newhaven project.

Leith Walk between Pilrig Street and London Road has re-opened, with the main construction works between Montgomery Street/Annandale Street and Pilrig Street are now complete and fencing will be removed from outside businesses and homes.

The project remains on schedule for completion by spring 2023 and within the £207.3m budget, with all major construction anticipated to be complete by the end of 2022 ahead of a testing and commissioning period.

Progress to date includes:

• Almost 3,900 metres of track laid, 84% of the total

• Main construction works completed on three out of the eight new tram stops with works progressing well at the Balfour Street, Foot of the Walk and Newhaven stops

• Over 4,000 metres of communications ducting installed (87% of the total) serving the tram and future communication requirements in the area

• More than 4,000 metres of drainage installed (89% of the total)

• Over 60,000 deliveries from the logistic hubs to local businesses

• Almost 24,500 itison vouchers sold, generating over £240,000 potential spend in participating businesses on the route.

• Over £175,000 spend on open for business campaigns

• Main construction works complete on several sections, including Ocean Terminal to Rennie's Isle and between Tower Street and Constitution Place and Tower Street and Baltic Street

However, the programme for some specific sections of the route has changed due to industry wide challenges with the availability of materials and skilled labour, as well as other issues including complex utility conflicts.

As a result, some stretches are scheduled to take longer than originally planned, including Melrose Drive and outside Ocean Terminal. Full details of the updated programme are available on the Trams to Newhaven website.

-- Advertisement --
NorthernAsbestosServicesLtd

Councillor Scott Arthur, Transport and Environment Convener, said: "It's great news that this key section of Leith Walk will soon reopen and will start its transition to becoming a vibrant multi-modal transport corridor. Not only does it mark a major milestone for the Trams to Newhaven project but I'm sure it will be most welcome to businesses and residents along this part of the route. I'd like to thank all those living and working nearby for their patience throughout the programme of work.

"As the project nears completion, the progress made so far is clear to see. Once finished, it will be transformative for the area and beyond. As well as delivering a low-carbon, high capacity and clean mode of transport to this densely populated part of Edinburgh, it will create improved public spaces, active travel links and support future growth and development.

"I do of course recognise that changes to the programme, which are down to issues outwith our control, are likely to affect people and we'll be working hard to share the latest information and will continue to look at ways in which we can mitigate against some of these delays. To ensure residents are kept safe, I have also asked that parking restrictions are robustly enforced along the route.

"I'd like to thank the Trams to Newhaven project team for all their hard work. Despite the pandemic and global logistics problems, the project is on track to welcome its first passengers in spring 2023 and will be delivered within budget."

Maria Ortega, SFN Project Director on Edinburgh Trams York Place to Newhaven, said: "We continue to make excellent progress on this project on behalf of our client The City of Edinburgh Council and we are delighted to be reopening this key section of Leith Walk to two-way traffic.

"As contractors we are working hard to ensure that continued progress is made throughout the remaining section of works. Despite the challenges of the pandemic and industry wide issues, we are proud of the progress we have made by working successfully alongside our partners, supply chain and client.

"We look forward to this line being operational in spring 2023."

Steve Jackson, Project Director, Turner & Townsend said: "As a project we have experienced numerous challenges, as well as industry wide issues, however collaborative working has played a key role to ensure that we have remained on track throughout the life cycle of the project.

"As we enter the final phase of construction works to deliver the Edinburgh Trams to Newhaven line, achievements such as this begin to bring the project together in real life and allow people to see the positive transformational impact this system will have for them.

"I would like to thank all project partners for their efforts to date and we look forward to making continued progress across the route."

As part of the changes, there is no waiting or stopping between Pilrig Street and Annandale Street, though there is designated loading and parking provision on both the east and west side of Leith Walk. Logistics hubs to support businesses on Albert Street and Montgomery Street with deliveries and dispatches will also remain on this section of Leith Walk.

Latest Construction News

07/05/2024

CCG (Scotland) and Westscot Living has announced the launch of the largest development of 'Passivhaus' affordable homes in Glasgow. This landmark project, located in Dundashill, north of Glasgow's city centre, consists of 90 highly energy-efficient mid-market rent homes. The development, ...
07/05/2024

Glasgow City Council has announced that the £5.827 million Argyle Street West Avenue scheme will begin on Monday, 13 May. This Avenue will stretch from under the Kingston Bridge to the junction between Argyle Street, Jamaica Street and Union Street. It will bring significant improvement to the ...
07/05/2024

SSEN Transmission has announced the launch of preparatory works for a new electricity substation at Creag Dhubh south of Cladich, Argyll, set to begin this week. Creag Dhubh substation iSSEM Transmission Launch New Argyll Development s one of five substations to be built as part of SSEN ...
07/05/2024

Moray Council has announced the appointment of Page \ Park Architects, to lead efforts to bring Grant Lodge in Elgin "back to life". The experienced team will lead the re-design and restoration of the heritage gem in the heart of Moray, bringing this much-loved building back to life after a long ...
07/05/2024

North Lanarkshire Council has announced the successful completion of a new housing development, delivering 31 new modern homes at Northburn Avenue and Northburn Place, Airdrie. The new homes have been built on the site where 28 flats were demolished as part of the council's re-provisioning ...
07/05/2024

Network Rail has announced the successful completion of a programme of vital repair works at Harbour Road in Inverness. Engineers works across the Bank Holiday weekend, to address deteriorated road surfaces on the approach to the level crossing. Stuart Colvin, Infrastructure Maintenance Engineer ...
07/05/2024

Midlothian Council has announced that it will progress plans to decarbonise all its buildings and set up district heating zones. The plans are part of the recently approved Local Heat and Energy Efficiency Strategy (LHEES). The LHEES will help the council meet Scotland's statutory greenhouse gas ...
07/05/2024

The Retail Trust charity has appointed Clark Contracts to complete a £1m renovation within its Hugh Fraser Retirement Estate in Newton Mearns to create a new community hub for older people and the community across East Renfrewshire. Three disused spaces within the estate's Crookfur House are being ...
07/05/2024

Marshall Construction has been awarded certification to BS ISO 45001: 2018 Occupational Health and Safety Management Systems, following a rigorous auditing process by certificating body, BM Trada. This certification adds to the existing ISO 9001 Quality and ISO 14001 Environmental Management ...
07/05/2024

Construction firms and property owners in Dundee have been urged to remove scaffolding as quickly as possible once works are completed. While praising proprietors for their efforts to prevent structural damage, a senior city councillor has also voiced concerns about the problems posed by ...
RBT Underfloor LimitedMorris & Spottiswood LtdBurnside Plant Hire LtdKattrak International Hidromek SalesScotdeck LtdThe Big Block Co LtdSafe Access (Highland) Ltd.Bairds Windows LtdThe Human Touch Scaffolding Co LtdBabbity Environmental
Terms and Conditions
2024/05/07 22:48:02