Four Transformer Units To Be Delivered For Shetland HVDC Project

Four new transformer units are set to be delivered for the project to connect Shetland to the GB transmission network.

The Shetland HVDC link team will take delivery of the first two transformers at their new locations later this week.

The four transformer units – weighing around 168 tonnes each – are key components in the operation of Kergord substation and will play a vital role in the Shetland HVDC link. Once complete, the link will enable the connection of renewable electricity generation and help Shetland's future security of supply.

On Sunday 01 May the first two transformers arrived in Lerwick Harbour from Sweden via specialist vessel MV Eemslift Ellen. The transformers have been loaded onto a multi-axle vehicle with specialist haulier, Allelys, ready to transport the units from Lerwick to their final destination at Kergord.

The first transformer delivery is expected to take place from 10.30pm on Friday 6 May, with the second delivery taking place from 10.30pm on Monday 9 May.

To minimise disruption to local residents, businesses and road users, SSEN Transmission has agreed with Shetland Islands Council and Police Scotland for each of the transformer deliveries to take place overnight, under the guidance and supervision of Police Scotland. The transformer convoy will depart from Lerwick Harbour at approximately 10.30pm and progress along the A970 road before arriving at Kergord.

-- Advertisement --
NorthernAsbestosServicesLtd

Due to their size, the delivery vehicles will be travelling at a reduced speed for safety, and it is expected the journey will take between three and five hours. No road closures are required to facilitate the movement of the transformers, and vehicles should be able to pass the convoy at regular opportunities on the road network under guidance from Police Scotland, when safe to do so.

The second delivery of the remaining two transformers is expected to arrive in June.

Transformers for SSE Renewables' Viking Energy Wind Farm project are also expected to arrive early next month, with a similar arrangement expected to be in place to transport the transformers to the wind farm site. A second transformer delivery for Viking Energy Wind Farm is also planned for early August.

SSEN Transmission Assistant Project Manager Jared Deeney said: "The delivery of the four new transformers from Hitachi Energy is a key milestone in the construction of the Shetland HVDC link.

"The complex delivery has been carefully coordinated by our project teams, working with our specialist haulier, Allelys, Petersons Shetland, Shetland Islands Council and Police Scotland, to ensure disruption can be kept to a minimum for the local community and road users on Shetland.

"We would like to take this opportunity to thank the local community in advance for their patience and understanding while we transport these transformers onto their final destination in Kergord."

Any changes to the delivery dates of the transformers will be publicised on the Shetland HVDC link project webpage and communicated to local stakeholders, including the media.

Latest Construction News

21/10/2026
Senior figures from Great British Energy are currently in Shetland until 22 October to meet island leaders, businesses and community groups, and to hear first-hand about local energy opportunities and challenges. The delegation, headed by CEO Dan McGrail and Chair Juergen Maier, will focus on commu
Read More
21/10/2026
North Ayrshire Council has secured funding to press ahead with demolishing the structurally unsafe Valefield pedestrian bridge in Kilbirnie. A funding commitment from the Scottish Government, working in partnership with Walk Wheel Cycle Trust, will enable the bridge to be removed, with plans alread
Read More
21/10/2026
SSE has named Aberdeen-based Seaway7, part of the Subsea7 group, as preferred supplier for the Engineering, Procurement, Construction and Installation (EPCI) scope on its 1.4GW Berwick Bank B offshore wind project, a move expected to support 465 UK jobs, including 400 in Scotland. The agreement li
Read More
21/10/2026
An Inverness electrician has been named Scottish Joint Industry Board (SJIB) Apprentice of the Year 2026 in recognition of her technical skills, professionalism and commitment to the electrical industry. Katie Munro, 25, who works for SELECT member firm Ross-Shire Engineering (RSE) Ltd, won the top
Read More
21/10/2026
Overnight closures will take place on the A1 at Wallyford from Monday 2 November, as BEAR Scotland carries out resurfacing on behalf of Transport Scotland. Work is scheduled over five nights between 20:30 and 06:00, with completion expected by 06:00 on Saturday 7 November. The scheme will repair d
Read More
21/10/2026
Queen Margaret University (QMU) has submitted a planning application for a new solar energy scheme at its Musselburgh campus, which could generate around a quarter of the university’s annual electricity requirements. The proposed development forms part of QMU’s wider sustainability programme and wo
Read More
21/10/2026
Highlands and Islands Enterprise (HIE) has welcomed the official launch of the UK’s first high-voltage direct current (HVDC) subsea cable factory at the Port of Nigg in Easter Ross. The £350 million facility will be key to expanding the UK's electricity transmission network and enabling the efficie
Read More
21/10/2026
When people see the glitz and glamour of casinos on the surface, there's a whole lot of other things going on beneath the surface to ensure that everyone has a nice time. The modern casino floor is one of the most carefully engineered rooms on earth, all the way down to the playing chips. In Decemb
Read More
21/10/2026
Glasgow Chamber of Commerce, supported by Developing the Young Workforce (DYW) Glasgow, has launched the third phase of its industry-led Construction Aware programme following a £3,000 investment from delivery partner RJ McLeod. The firm is the first business to invest directly in the initiative,
Read More
21/10/2026
The eastbound on-slip to the M8 at Junction 3 in Livingston will be closed from 20:30 to 06:00 on Monday 9 November 2026 while Transport Scotland’s operating company, BEAR Scotland, undertakes painting inspection works on two bridges over the motorway. A signed diversion will direct drivers seeking
Read More
SEEIT3DPentland Building & JoineryWestermans International LtdGMAC Utilities LtdGrampian Steel Buildings LtdAtlas Winch & Hoist Services LtdB Home DesignCF Concrete PumpingDublcheck Cleaning GlasgowCRGP Limited