Realm Construction is to begin bridge strengthening works in Fife.
The contractor will start refurbishing the A917 Kilrenny Bridge between Anstruther and Crail in May. Completion is scheduled for August.
The works, which are part of the Fife Bridge Works Programme, will include;
• installing a steel tunnel liner over the Kilrenny Burn.
• infilling beneath the bridge deck with concrete.
• the new arch bridge and concrete parapets will be clad in natural stone sympathetic to the Kilrenny Conservation Area.
• the road will be resurfaced with junctions realigned to suit the new arrangement.
Frances Ratcliffe, consultant engineer said: "The existing concrete bridge dates from 1937 and is in poor condition. Since 2001, it has been limited to single lane operation controlled by traffic lights. Temporary props are in place beneath the deck to avoid imposing a weight restriction.
"This proposal to infill the bridge will result in a significant cost saving compared to demolition, it’s far less disruptive to road users and local residents, and has a reduced environmental impact.
"The concrete parapets, road surface, temporary kerbs and handrails, which need to be removed, will all be recycled off site."
(LM)