21/03/2012

Royal Commonwealth Pool Splashes Back Into Action

The Royal Commonwealth Pool (RCP) was formally reopened on Tuesday in a star-studded celebration featuring swimming and diving legends past and present.

Former Olympic swimming champion David Wilkie performed the honours, declaring the Grade A-listed facility officially open again following its major revamp.

The £37.2m refurbishment by GRAHAM Construction was funded by the City of Edinburgh Council and sportscotland and the RCP is reopening as expected in Spring 2012 after a two and a half year construction project.

The facility reopens fully to the public at 10am on Wednesday 21 March.

The RCP will host the diving events as part of the Glasgow 2014 Commonwealth Games and the British Swimming squad have selected the facility as the venue for their final training camp in July 2012 ahead of the London Olympics.

Compered by former Scotland rugby star Scott Hastings, the official reopening event also included speeches by the Deputy Lord Provost Rob Munn,; Deputy First Minister Nicola Sturgeon; Louise Martin CBE, Chair of sportscotland; and Sue Bruce, Chief Executive of the City of Edinburgh Council.

There was a synchronised diving display featuring Commonwealth Games athlete Grace Reid, who was also interviewed poolside by Scott Hastings, together with fellow divers James Heatly and his grandfather Sir Peter Heatly, who took part in the original opening ceremony of the RCP in 1970.

As part of the ceremony, David Wilkie swam the first breadth in the 50m pool alongside 30 children who won a competition run in the Edinburgh Evening News

He said: "It is a great privilege to be back at the RCP, considering that this is where I did a lot of my training when I was a schoolboy in Edinburgh. This is also the pool where I won my first international cap for Great Britain and won my first major international medal at the 1970 Commonwealth Games.

"I have some fond memories of the place. It’s great to see the ‘old lady’ reformed in all her old glory and to play a part in her reopening."

Deputy First Minister Nicola Sturgeon said: "With five Scots swimmers already qualifying for the London Olympics and the 2014 Games less than 900 days away, there has never been a more exciting time for sport in Scotland.

-- Advertisement --
NorthernAsbestosServicesLtd

"The reopening of this spectacular venue, which will host the diving competition during the 2014 Commonwealth Games, marks yet another significant milestone on the journey towards 2014.

"This world class facility will encourage participation in sport and physical activity locally and support elite athletes. The pool will also welcome the GB swimming squad for their final training camp ahead of the 2012 Olympics raising Edinburgh and Scotland’s profile as an outstanding place to stage major events."

Deputy Lord Provost Rob Munn said: "The RCP's refurbishment has been an incredibly complex engineering project. In just four months' time, the pool will play host to the British Swimming squad as they make their final training preparations ahead of London 2012 Olympic Games.

"We now know that two Edinburgh swimmers will be among them: on behalf of the City of Edinburgh, I would like to offer heartfelt congratulations to Craig Benson, of Warrender Baths Club and Michael Jamieson, of the University of Edinburgh, whose success at the recent British Gas Swimming Championships 2012 saw them qualify."

Louise Martin, Chair of sportscotland, said: “We are delighted to have played our part in bringing this exciting project to life. At sportscotland, one of our priorities is to promote the positive power of sport, and the extensive refurbishment of the Royal Commonwealth Pool will provide the people of Edinburgh, and further afield, with a world-class facility they can really be proud of. Generations of Scottish swimmers learned their craft in this historic pool and now more swimmers – of all ages and abilities – have a fantastic opportunity to benefit from all that the revamped pool has to offer.

"Sportscotland has a close working relationship with City of Edinburgh Council, and we were pleased to offer advice on the design of the refurbishment and provide £5 million of Scottish Government and Lottery funding from our Sports Facilities Fund. The Royal Commonwealth Pool is now the ideal venue to host the diving competition when the Commonwealth Games return to Scotland in 2014."

Edinburgh Leisure Chief Executive John Comiskey said: "The wait is finally over and Edinburgh Leisure is delighted to welcome back our customers, old and new, to the much-loved Royal Commonwealth Pool once again.

"We are incredibly proud to be managing this outstanding venue on behalf of The City of Edinburgh Council and have put in place an exceptional team of staff and programme of activities for all ages. We are looking forwarding to delivering the highest possible customer experience in a safe and enjoyable environment to help all of our customers get active, stay active and achieve more."

Michael Graham, executive chairman of GRAHAM Group, said: "Transforming the Royal Commonwealth Pool to provide a modern, world-class sports facility while protecting the legacy of such a well-loved Scottish landmark has been a showcase project for GRAHAM Construction.

"The extent of the redevelopment coupled with the historic nature of the building made this an incredibly complex project, but by applying precise planning and expertise, GRAHAM Construction is incredibly proud to have delivered an outstanding facility for Scotland and its sporting stars of the future."

The new features sported by the revamped RCP include:

- a 50m, eight-lane pool for community and specialist swimming use with a boom capable of subdividing the pool into two areas;

- a re-orientated 25m diving pool up to 5m deep with moveable floor which can be used for swimming when not in use for diving;

- a dry dive facility including trampoline and springboards to allow divers to practise out of the pool;

- a 25m pool with moveable floor to accommodate warm-up provision, swimming lessons and informal play utilising pool toys;

- new dry soft play facilities;

- a refurbished and expanded gym and fitness studios; and

- a refurbished and redesigned changing village, meeting and conference rooms

RCP REFURB: Some facts and figures

•6.5 million man hours worked

•5.5 million litres of water to fill the pool

•380,000 tiles laid

•25,000m² floor area

•821 seats on seating deck

•12 days to empty all three pools

The Royal Commonwealth Pool reopened to the public at 10am on Wednesday 21 March 2012.

Opening hours are:

Monday to Friday: 5.30am to 10pm; Saturdays: 5.30am to 8pm; Sundays 7.30am to 8pm

(GK)

Latest Construction News

02/05/2024

Malin Group has secured planning permission in principle for its proposed development of the Scottish Marine Technology Park (SMTP). Malin Group's vision for the site is to deliver a state-of-the-art marine excellence hub which will bring together manufacturers with marine and renewables ...
02/05/2024

Fleming Building has officially broken ground on the development of the multi-million pound Bishopton Dargavel Satellite Facility. Working alongside Hub West Scotland and NHS Greater Glasgow & Clyde through a detailed pre-construction period, designs were developed to meet a range of requirements ...
02/05/2024

Aberdeenshire Council has announced the installation of a downstream defender as part of ongoing works to restore and improve the ponds at Denman Park in Westhill. The popular ponds in Denman Park are home to a wide variety of pondlife and wildlife but have been subject to pollution from a range ...
02/05/2024

Contractors RJ McLeod are on schedule to complete the construction of a new Largs seawall in North Ayrshire. The £4.6m project is almost complete with the northern section of the promenade expected to re-open to pedestrians before the summer season gets under way. The project has seen the ...
02/05/2024

Scottish Water has announced the successful completion of a major technological transformation of Glasgow's Victorian era Partick Pumping Station. Built some 120 years ago, the pumping station remains a key part of the city's waste water infrastructure and still serves 170,000 people. It is one of ...
02/05/2024

SSEN Transmission has committed to consider community and landowner proposed alignments as part of its Kintore-Tealing 400kV project. These alignments - which will be assessed in parallel with other alignment options within the refined routes SSEN Transmission recently consulted on - are around ...
02/05/2024

SSEN Distribution has announced that it has chosen Electron's 'ElectronConnect' platform to streamline and expand its procurement of Flexibility Services. The company's DSO Acceleration Action Plan identified the selection of a new Flexibility Market Platform during the Spring of 2024 as a key ...
02/05/2024

West Dunbartonshire Council has declared a housing emergency, highlighting the unprecedented pressures on the ability to meet the needs of those in social housing or seeking a Council property. Councillor Gurpreet Singh Johal, who is the Convener of Housing and Communities, made the declaration ...
02/05/2024

The Highland Council has submitted its response to the Scottish Government's consultation on Masterplan Consent Areas (MCA), developed by members of the Economy and Infrastructure Committee. The Scottish Government is proposing the introduction of discretionary powers to establish Masterplan ...
02/05/2024

As part of its ongoing efforts to improve biodiversity across the region, Perth and Kinross Council has announced an extension of its Grassland Management Trials, following successes at 42 other sites. These areas of longer grass will create space for nature and help attract bees, butterflies and ...
RBT Underfloor LimitedMorris & Spottiswood LtdRBT Underfloor LimitedBurnside Plant Hire LtdKattrak International Hidromek SalesRBT Underfloor LimitedScotdeck LtdThe Big Block Co LtdSafe Access (Highland) Ltd.Bairds Windows Ltd
Terms and Conditions
2024/05/02 21:55:39