Skye Members of The Highland Council visited the Island of Raasay earlier this week to inspect progress on the Council's biggest current construction contract – a new £12 million ferry terminal to link the island with Sconser, Skye.
The terminal is being built at Churchton Bay and will provide a sheltered roll on roll off facility for the Caledonian MacBrayne car ferry, Loch Striven, and overnight berthage.
Work began in March, last year, and has been continuing on a 24-hour daily basis through the summer months by contractor Balfour Beatty Civil Engineering Ltd. Their workforce of 60 has increased the island population by 40%.
The new terminal is two kilometres from the existing terminal at Suisnish, which was constructed at the beginning of the 20th century for the transportation of iron ore from Raasay.
In the early 1970s Suisnish was enhanced to provide a slipway and berthing structure for the introduction of a new Island Class ferry direct to Sconser rather than Portree. Suisnish pier has now reached the end of it’s life, and is in a very poor state of repair suffering from both corrosion of the precast concrete sections and accelerated low water corrosion of the sheet piles and does not provide the shelter that a modern day roll on/roll off ferry service requires.
The pier is in such a poor state that contingency measures have been put in place to maintain the ferry service in case of collapse.
The new terminal is 150 meters long and will have a 40 metre dog leg to provide shelter. Councillors were told that good progress has been achieved on the casting of the underwater concrete foundations for the new pier structure, which is presently 70% complete. Placement of the pre-cast concrete "Lego Blocks" is also advancing with 40% in place and progressing seaward.
Drilling, blasting and dredging rock from the new inner harbour seabed is close to completion. Protective armouring work to the new terminal is progressing well, with regular deliveries of armour stone by sea from Kishorn Quarry.
Construction of a new 0.5km single track road serving the marine facility is progressing steadily.
Balfour Beatty is targeting the end of the year to complete the underwater elements of the project. However, this is subject to the vagaries of the upcoming autumn/winter weather.
Councillor John Laing, Chairman of the Transport Environmental and Community Services Committee, is delighted that the lifeline link between Skye and Raasay is being secured with such a major investment.
He said that the new ferry terminal will provide opportunities for Raasay to encourage visitors and improve the economy and sustainability of this remote island community.
(GK/KMcA)
Construction News
08/09/2009
Councillors Given Progress Report On Raasay Ferry Terminal

16/06/2025
Work has commenced on a major project to transform the Watersports Centre at Strathclyde Country Park into a multi-purpose community facility, with an ambitious target to reduce the building's carbon footprint by at least 80%.
The initial stage, focusing on improving the building's entrance and ac

16/06/2025
Work is expected to commence this summer on the site for the new Mayfield Community Learning Campus, following Midlothian Council's appointment of Kier as the main contractor.
The £41.8 million project is expected to complete its construction phase by spring 2027, with the overall campus fully ope

16/06/2025
McLaughlin & Harvey has officially handed over the keys to the Ayrshire Hospice's significantly redeveloped facility, marking the completion of an £18.8 million capital build project.
The extensive works were undertaken in close collaboration with the Ayrshire Hospice to substantially improve its

16/06/2025
Aberdeenshire Council has announced the opening of the latest round of its Coastal Communities Challenge Fund (CCCF), making grants of up to £49,999 available to support initiatives along its coastline.
The fund, which distributes revenues generated by Crown Estate Scotland, targets community group

16/06/2025
A crucial route into Stewarton, the B778 Holm Street, is scheduled for closure for approximately two months as Scottish Water proceeds with a significant £16 million package of investments in the town's water infrastructure.
The closure will take effect from Monday, 30th June 2025, impacting Holm S

16/06/2025
Stirling Council is moving forward with plans to deliver 36 high-quality, energy-efficient homes for social rent at Brucefields, a key component of the South Stirling gateway strategic housing site. The Council has now received approval to initiate the procurement process for their construction.
Th

16/06/2025
Significant progress is being made towards the reinstatement of Dunrod Road, a crucial rural link between Greenock and Inverkip that has been closed for some time due to a partial failure and movement of the road caused by various factors, including landslip. Ground investigation works are scheduled

16/06/2025
Bonnybridge is set for significant infrastructure upgrades this summer, with Falkirk Council investing £460,000 in a coordinated programme of resurfacing, regeneration, and accessibility improvements.
The work will focus on Bonnybridge Toll, Memorial Park, and surrounding public spaces.
Funding f

13/06/2025
The first completed section of Glasgow's ambitious £120 million-plus Avenues programme, the Holland and Pitt Street Avenue, has officially opened, marking a significant milestone in the ongoing regeneration of the city centre.
The newly completed avenue features a comprehensive transformation, incl

13/06/2025
Construction has officially commenced on the Dumfries Zero Waste Park (Dumfries ZWP), marking a significant milestone in Dumfries and Galloway Council's commitment to its Waste, Recycling and Reuse Strategy 2023–2030.
The £11.197m investment, drawn from the Council's approved 10-year Capital Invest