Viking Wind Farm Turbine Components Convoy Underway

Convoys of wind turbine components for the Viking Wind Farm in Shetland have begun their journey today (07 February) from Lerwick Port to the Viking site in central Mainland Shetland.

Vestas, which is supplying the 103 wind turbines which make up the wind farm, is responsible for safely managing the process of getting the components from their factories to Lerwick and then delivering them from there to the Viking site.

Robert Yeates, Lead Project Manager with Vestas, said: "The first convoy this morning went to plan thanks to the expertise, of McFadyen’s Transport Ltd and the wider supporting team.

"I am pleased that with the help of specialist Police Scotland officers who escorted the loads, the journey was completed safely and with the minimum of disruption to road users."

-- Advertisement --
NorthernAsbestosServicesLtd

Aaron Priest, Stakeholder Manager for Viking Wind Farm, said: "Delivery of the first turbine components marks a significant milestone in the construction of Viking Wind Farm.

"It’s great to see the first components arrive on site, we would like to thank all those involved in the delivery process, it was excellent co-ordination which ensured road users journeys were not significantly impacted."

The first turbines at the Viking Wind Farm site are scheduled to be erected during March. The wind turbine component convoys are expected to conclude in July at the latest.

Convoy timing details

• There will be up to three convoys per day, 6 days a week (Mon – Sat) with up to four wind turbine components per convoy.

• Convoy travel time is estimated to be around 1 hour from leaving the port to entering the site.

• The times the convoys are expected to leave the port on weekdays (Mon-Fri) are between: 6am – 7am; 11am – 12noon; 1pm – 2pm

The times the convoys are expected to leave the port on Saturdays are between: 6am – 7am; 10am – 11am; 12 noon – 2pm

The timing of the movements has also been planned to seek to ensure that the early morning convoy will be off the public highway by 8am and the mid-afternoon convoy will be off the public highway by 3pm to avoid the relevant peak travel periods.

Latest Construction News

17/07/2026
Construction has begun on a new £3.3 million paint facility at BAE Systems’ Govan shipyard in Glasgow as part of a wider programme to modernise the city's naval shipbuilding infrastructure. The new facility will allow ship blocks to be painted in a dedicated space, freeing up existing areas at the
Read More
17/07/2026
Retrofit and energy-efficiency specialist Procast Group has secured two awards at the Energy Efficiency Awards, with apprentice electrician Cameron Sleith also recognised as Apprentice of the Year. The company was named Regional Insulation & Fabric Installer and Contractor of the Year at the awards
Read More
17/07/2026
Residential management specialist Fresh has been appointed by Ropemaker to manage two purpose-built student accommodation (PBSA) developments in Edinburgh. Fresh took over management of Meadow Court and Norton's Student Living on 1 July 2026, expanding its existing partnership with Ropemaker, for w
Read More
17/07/2026
Essential resurfacing on the A721 Carnwath Road in Carluke will require a section of the route to be closed for up to four days this month. The works are scheduled to begin on Tuesday 21 July and will cover the stretch between Stanistone Road and Crawfordwalls Bridge. Traffic will be diverted via
Read More
17/07/2026
Aberdeenshire Council is inviting feedback on proposed changes to its Council Tax approach for long‑term empty properties and second homes, with new mitigations being considered alongside a premium due to take effect on 1 September. From 1 September this year, owners of homes left empty for m
Read More
17/07/2026
Grampian Housing Association has appointed David Fisher as its new group chief executive, succeeding Craig Stirrat who is due to retire later this year. Fisher will take up the role in August 2026 following a competitive recruitment process. The housing association said the Board’s recruitment pane
Read More
17/07/2026
Maryhill Housing Association (MHA) has lodged a planning bid for a 108-home neighbourhood on the long-vacant Collina Street plot in north Maryhill, with most properties proposed as affordable. The association has submitted its application to Glasgow City Council, seeking permission to redevelop the
Read More
17/07/2026
Kier has been appointed by the City of Edinburgh Council to deliver a £23m retrofit of residential accommodation in the Craigmillar and Peffermill districts of Edinburgh. Procured via the Scottish Procurement Alliance (SPA) framework, the scheme underpins the council’s environmental objectives. Kie
Read More
17/07/2026
BEAR Scotland, working on behalf of Transport Scotland, will carry out a series of resurfacing schemes at multiple locations on the A83 between Tarbert and Inveraray from Wednesday 29 July. Crews will operate between 7pm and 6am on working nights, with completion anticipated by Thursday 20 August.
Read More
17/07/2026
Investigations into pollution affecting the Kinghorn Burn in Fife are continuing, with public health advice to avoid contact with the water remaining in place. The Scottish Environment Protection Agency (SEPA) and Scottish Water are working alongside partners including Fife Council, NHS Fife and Fi
Read More
SEEIT3DG M Joinery Scotland LtdLogical Insulation Solutions LimitedK A Tree SurgeryClaymore Training LimitedCross BlindsK&C LandscapesThomas Haywood Aerial PhotographyEnvironmental Dust Solutions LtdIBT Building & Timber (Merchants) Ltd