Seagreen Wind Farm has celebrated a new milestone in the construction of the world's deepest fixed bottom offshore wind farm, which is also Scotland's largest, with more than 50% of the jacket foundation substructures having now been installed.
The three-legged jacket foundations each weigh approx. 2,000 tonnes and will play a critical role in safely supporting the wind turbines during Seagreen's 25 year operational lifespan.
Situated around 27km off the Angus coast, the £3bn wind farm is a joint venture between SSE Renewables (49%) and TotalEnergies (51%).
When complete, Seagreen will consist of 114 Vestas V164-10.0 MW turbines, the first of which started generating power to the UK national grid last week. The wind farm will be capable of generating around 5,000 GWh of renewable energy annually which is enough clean and sustainable electricity to power more than 1.6m UK homes.
SSE Renewables is leading the development and construction of the Seagreen project and will operate Seagreen on completion for its expected 25-year lifetime. Installation of the foundations is being carried out by Aberdeen-based Seaway 7.
John Hill, Seagreen's Project Director, said: "Seeing the jacket installation process reach the halfway point demonstrates successful innovation with the largest ever deployment of foundations using suction caissons in offshore wind. Reaching this milestone is a testament to the hard work and determination of everyone involved in the construction of Scotland's largest and the world's deepest fixed bottom offshore wind farm.
"This achievement follows the significant announcement last week where first power was generated from the first turning turbines. Once operational in the first half of 2023, Seagreen will make a significant contribution to Scotland's and the UK's net zero targets."
The overall turbine foundations installation campaign is supporting over 140 skilled jobs at Port of Nigg, delivering a green jobs boost and significant economic benefit to the Highlands and Scotland.
Construction News
13/09/2022
Seagreen Wind Farm Development Celebrates Installation Milestone


16/06/2025
Work has commenced on a major project to transform the Watersports Centre at Strathclyde Country Park into a multi-purpose community facility, with an ambitious target to reduce the building's carbon footprint by at least 80%.
The initial stage, focusing on improving the building's entrance and ac

16/06/2025
Work is expected to commence this summer on the site for the new Mayfield Community Learning Campus, following Midlothian Council's appointment of Kier as the main contractor.
The £41.8 million project is expected to complete its construction phase by spring 2027, with the overall campus fully ope

16/06/2025
McLaughlin & Harvey has officially handed over the keys to the Ayrshire Hospice's significantly redeveloped facility, marking the completion of an £18.8 million capital build project.
The extensive works were undertaken in close collaboration with the Ayrshire Hospice to substantially improve its

16/06/2025
Aberdeenshire Council has announced the opening of the latest round of its Coastal Communities Challenge Fund (CCCF), making grants of up to £49,999 available to support initiatives along its coastline.
The fund, which distributes revenues generated by Crown Estate Scotland, targets community group

16/06/2025
A crucial route into Stewarton, the B778 Holm Street, is scheduled for closure for approximately two months as Scottish Water proceeds with a significant £16 million package of investments in the town's water infrastructure.
The closure will take effect from Monday, 30th June 2025, impacting Holm S

16/06/2025
Stirling Council is moving forward with plans to deliver 36 high-quality, energy-efficient homes for social rent at Brucefields, a key component of the South Stirling gateway strategic housing site. The Council has now received approval to initiate the procurement process for their construction.
Th

16/06/2025
Significant progress is being made towards the reinstatement of Dunrod Road, a crucial rural link between Greenock and Inverkip that has been closed for some time due to a partial failure and movement of the road caused by various factors, including landslip. Ground investigation works are scheduled

16/06/2025
Bonnybridge is set for significant infrastructure upgrades this summer, with Falkirk Council investing £460,000 in a coordinated programme of resurfacing, regeneration, and accessibility improvements.
The work will focus on Bonnybridge Toll, Memorial Park, and surrounding public spaces.
Funding f

13/06/2025
The first completed section of Glasgow's ambitious £120 million-plus Avenues programme, the Holland and Pitt Street Avenue, has officially opened, marking a significant milestone in the ongoing regeneration of the city centre.
The newly completed avenue features a comprehensive transformation, incl

13/06/2025
Construction has officially commenced on the Dumfries Zero Waste Park (Dumfries ZWP), marking a significant milestone in Dumfries and Galloway Council's commitment to its Waste, Recycling and Reuse Strategy 2023–2030.
The £11.197m investment, drawn from the Council's approved 10-year Capital Invest