Construction of the new Ferrybridge Multifuel 2 (FM2) project in West Yorkshire is to begin later this year, following a decision by SSE to approve its funding.
The project was awarded planning consent by the Secretary of State in October 2015 and will be built next to the recently completed FM1 project, on land at Ferrybridge 'C' Power Station in Knottingley, West Yorkshire. The completed plant will be able to generate around 70MW of electricity, enough to power around 170,000 homes.
An EPC contract has now been signed with Hitachi Zosen Inova (HZI), a Swiss headquartered company who are a market leader in building energy from waste projects, who were also the main EPC contractor on the neighbouring FM1 plant.
FM2 is expected to bring similar benefits to the local area as FM1, including in excess of 500 construction jobs during the three year build, a number of contract opportunities and an estimated £10 million of additional economic benefits to the local economy, through spending in restaurants, hotels and local businesses.
Charlie Cryans, Head of Construction for SSE said: "SSE's decision to take the FM2 project through to construction is positive for our businesses, but also represents a £360 million investment, which will provide a range of benefits for the local area which we have a long association with. We will be holding a Meet the Buyer event in the coming weeks which will provide local businesses and suppliers with the opportunity to meet the main contractor for the project, and pitch their products and services."
Franz-Josef Mengede, CEO of HZI said: "We are delighted to be working with SSE to build the second Multifuel project at Ferrybridge. Our experience during the construction of the now operational FM1 plant will be invaluable in helping us to deliver this second plant and meet the high standards required by SSE."
(MH)
Construction News
29/06/2016
Funding Approved For Ferrybridge Multifuel 2 Project


17/06/2025
Sypro has announced a major milestone in its long-standing partnership with SSEN Transmission, having now managed over £5 billion in contracts supporting the UK’s critical energy infrastructure across more than 250 projects in the north of Scotland.
For more than a decade, Sypro's digital contract

17/06/2025
Stirling Council has approved the sale of the former Beech Gardens Care Home in Torbrex.
At a recent council meeting, Urban Nest Scotland Ltd was confirmed as the preferred bidder. The company plans to redevelop the vacant site for private residential use, with proposals that aim to complement the

17/06/2025
Two sod-cutting ceremonies have marked the official start of new housing developments in the west of Dumfries and Galloway, as Wheatley Homes and McTaggart Construction begin delivering vital social housing in Stranraer and Leswalt.
The ceremonies celebrated the beginning of construction on two sit

17/06/2025
Fife Council is inviting residents to take part in a public consultation on short-term lets, seeking views on the potential introduction of Short-Term Let Control Areas across the region.
The consultation, now open, aims to gather public opinion on whether areas should be designated where planning

17/06/2025
Highland charity DAY1 is exploring opportunities for an ambitious new centre of learning, capitalising on the opportunities in construction and green energy revolution, expanding its services to support more disengaged youths across the Highlands
Since 2005, the Inverness-based charity has been pro

17/06/2025
AS Homes (Scotland) has secured planning permission from East Renfrewshire Council for a new social housing development in partnership with Barrhead Housing.
The project will see 12 new flats built for social rent on Cross Arthurlie Street, a brownfield site near Barrhead Park and the town's train

17/06/2025
Whiteinch & Scotstoun Housing Association (WSHA) has officially launched its new business plan for 2025–2030, outlining a bold and community-focused vision to strengthen its role as both a leading housing provider and a key anchor organisation within the local area.
The five-year strategy sets out

17/06/2025
Balfour Beatty has announced the appointment of Nick Rowan as Managing Director of its UK Construction Services Regional Scotland business, effective from 4 August 2025.
Rowan, who began his career with Balfour Beatty 30 years ago as a Graduate Surveyor, steps into the top regional role following a

16/06/2025
Work has commenced on a major project to transform the Watersports Centre at Strathclyde Country Park into a multi-purpose community facility, with an ambitious target to reduce the building's carbon footprint by at least 80%.
The initial stage, focusing on improving the building's entrance and ac

16/06/2025
Work is expected to commence this summer on the site for the new Mayfield Community Learning Campus, following Midlothian Council's appointment of Kier as the main contractor.
The £41.8 million project is expected to complete its construction phase by spring 2027, with the overall campus fully ope