Components for the UK’s first 15-megawatt offshore wind turbines are heading to Inch Cape's North Sea site aboard the jack-up installation vessel Wind Mover, operated by Cadeler.
The vessel left Forth Ports' Port of Dundee on 20 November, taking advantage of favourable weather. It is carrying two nacelles, six blades and two pre-erected towers, each 127 metres tall, for installation off the Angus coast.
Built 12 months ago, Wind Mover is undertaking its first UK assignment at Inch Cape. Its initial departure marks the start of a programme to install 72 Vestas V236-15.0 MW turbines at the wind farm.
The vessel will return regularly to Dundee over the coming months to collect more nacelles, blades and erected towers for the site, which lies 15 kilometres from the Angus coast.
Deliveries of the remaining 115-metre-long blades, nacelles and tower sections to Dundee will continue until all 576 components have arrived.