Dumfries and Galloway councillors will be asked to approve £6.19 million to advance the Kirkcudbright Bridge replacement to its next stage at a meeting of Full Council on Thursday 24 September.
The funding would cover the preparatory work needed before any decision on building the new bridge, including developing the design, undertaking ground and site investigations, progressing statutory approvals, completing pre-construction procurement and engagement, and producing a final business case to test affordability, deliverability and value for money.
Kirkcudbright Bridge carries the A755 over the River Dee, linking Kirkcudbright, the Merse and the wider Stewartry. Opened in 1926, the structure has deteriorated significantly.
The council closed the bridge on safety grounds in March 2025. It later reopened with single-lane traffic management to cars, light vans and motorcycles, subject to a 3-tonne weight limit.
Larger vehicles continue to divert, affecting residents, businesses, visitors and the delivery of council services.
According to the report, the existing bridge with its current restrictions is not a viable long-term main crossing for the A755. It recommends progressing a replacement that would restore unrestricted access and include facilities for walking and cycling.
An immediately upstream alignment has been identified as the recommended option at this stage, with the exact location and design to be developed during the next phase.
Two public engagement events took place in June 2026 and more than 300 people responded to a community survey. Feedback stressed the need for a safe, accessible bridge, unrestricted access, long-term reliability and minimising disruption during construction. Sixty per cent of respondents preferred the upstream location.
The current cost plan indicates the overall project is most likely to cost £43.7 million. This is not a final construction figure nor the sum being sought on 24 September. The next phase would provide firmer estimates before councillors decide whether to proceed to construction.
The £6.19 million would be drawn from an existing £36.8 million allowance in the council's Capital Investment Strategy for unavoidable requirements. Funding for construction would be considered once the final design, costs and business case are presented to councillors.
The programme suggests the detailed design and final business case could be completed by January 2028. Subject to further decisions, funding and approvals, construction could begin in January 2028 and the new bridge could open in April 2030, though dates may change as the project develops.
Convener of Dumfries and Galloway Council, Councillor Tracey Little, said: "Kirkcudbright Bridge is an important connection for local communities, businesses and visitors. Councillors recognise the need to find a safe and sustainable long-term solution.
"This report represents a significant next step. If approved, the funding would allow the detailed design, investigations and other work needed to produce a clearer and more reliable proposal before councillors make any decision on construction.
"It has been encouraging to see the level of engagement from local residents, businesses and other stakeholders. More than 300 people responded to the survey, and their feedback will continue to inform the project as the plans develop.
"We will continue to keep the community informed and provide opportunities for people to be involved as this important work progresses."
The report will be considered by Full Council on Thursday 24 September. Meeting papers are available on the council's website: dumfriesgalloway.moderngov.co.uk/ieListDocuments.aspx?CId=137&MId=6526