14/08/2026

Main Construction To Begin On SSEN Transmission's Dunoon Overhead Line Rebuild

Construction News Image

SSEN Transmission's programme to strengthen the high-voltage network around Dunoon is moving into its principal build phase later this month, marking a major step in efforts to improve resilience and replace ageing assets.

The Dunoon Overhead Line Rebuild Project will replace the existing double-circuit 132kV overhead line that connects Dunoon to the national grid. The upgrade will modernise infrastructure dating back to the 1970s and help future-proof the transmission network across Argyll and Bute, supporting long-term reliability and security of supply.

The project received its Section 37 consent from Scottish Ministers in October 2025, with teams now mobilising to commence main construction within weeks.

Ahead of this next phase, a package of local road upgrades has been completed, including road widening and new passing places—primarily in the Ardentinny area—to support the safe movement of construction traffic throughout the works.

In the coming weeks, contractors will begin building a network of access tracks to reach tower locations along the route. Forestry operations will also start shortly to clear land for the future access tracks and the overhead line corridor, with this activity expected to continue for around 18 months.

-- Advertisement --
NorthernAsbestosServicesLtd

Construction compounds will be established at both ends of the route, at Sandbank Industrial Estate and Gairletter, to serve as operational hubs for project teams and contractors during delivery.

Paul Ferguson, Project Manager for SSEN Transmission's Dunoon Overhead Line Rebuild Project, said: "This is an important milestone for the project as we move from the preparation phase into the start of main construction activities. Over recent months, we've worked closely with local stakeholders and communities as we completed the necessary road improvements ahead of construction. I'd like to thank residents and road users for their patience and understanding while this work has been carried out. As activity increases on site in the coming weeks, we remain committed to keeping local communities informed and minimising disruption wherever possible, while delivering the infrastructure needed to support a resilient electricity network for the future."

Approximately 18km of replacement double-circuit overhead line will be installed between Dunoon Substation and a point west of where the line crosses Loch Long. The scheme includes 77 new steel towers, ranging from 23m to 39m in height, with average spans of about 230m.

To the east of Loch Long, the network is operated by SP Energy Networks, where the rebuilt Dunoon line will connect. Once the new line is energised, the existing 132kV line will be dismantled and removed.

This project forms part of SSEN Transmission's wider investment across the north of Scotland to bolster network resilience and support the transition to a cleaner energy system. Further details are available at: www.ssen-transmission.co.uk/projects/project-map/dunoon-overhead-line-rebuild-project/

Latest Construction News

20/10/2026
Scotland's leading public sector framework provider has opened bidding for a £900 million Refurbishment and Modernisation programme aimed at delivering urgent and planned works across housing and public buildings. The Scottish Procurement Alliance's Refurbishment and Modernisation framework (RM4S)
Read More
20/10/2026
A £1 million grant programme has been launched to help owners return vacant listed buildings across Glasgow to productive use. The Heritage Building Viability Grant Scheme, funded by Glasgow City Council and administered by Glasgow City Heritage Trust, is designed to bring floorspace in some of the
Read More
20/10/2026
Road resurfacing on the A702 at West Linton will take place over six nights from Monday 9 to Friday 13 November, and on Monday 16 November 2026, requiring overnight closures. Transport Scotland's operating company, BEAR Scotland, will deliver the scheme. For safety, the A702 will be closed each ni
Read More
20/10/2026
SP Energy Networks chief executive Nicola Connelly has welcomed the launch of a new industry plan setting out how the biggest grid upgrade in living memory will boost employment and economic growth across the UK. The Electricity Networks Sector Growth Plan – led by the Energy Networks Association (
Read More
20/10/2026
An £8 million scheme is under way to enhance accessibility for passengers at Dalwhinnie and improve performance on the Highland Main Line. The project will install a new crossover so trains can switch between tracks, enabling northbound services to use Platform 1 when step-free access is required.
Read More
20/10/2026
The Scottish Government intends to award Wills Bros Civil Engineering Ltd the contract to dual the A9 between Pitlochry and Killiecrankie, Economy, Tourism and Transport Secretary Stephen Flynn has announced. The move represents the final stage of procurement for the fifth A9 Dualling scheme to rea
Read More
20/10/2026
Residents in Clackmannanshire are already benefiting from a new electric nine-seater minibus provided by Robertson Construction Central East, part of the contractor's social value commitments linked to the Wellbeing Village and Lochies School development in Alloa. During construction, the vehicle i
Read More
20/10/2026
A major new study will examine how climate change could trigger cascading disruption across Scotland's critical infrastructure, giving organisations a clearer view of risks to the services people rely on daily. Commissioned by the Climate Ready Infrastructure Scotland Forum (CRIS) — a partnership o
Read More
20/10/2026
Clark Contracts has secured a place on Pagabo's Major Works Framework, enhancing its ability to support public sector bodies in delivering major construction and refurbishment schemes. The framework, expected to be worth up to £5bn over four years, follows the creation of a 10-year strategic delive
Read More
20/10/2026
North Ayrshire Council has carried out its annual winter dry run this month as it gets ready for the colder months. Roads staff took part in the exercise as part of preparations to keep roads, footways and communities safe and accessible during severe weather. It follows a meeting of Cabinet at wh
Read More
SEEIT3DFP McCann LtdContainexSEEIT3DHutton Stone Co LtdPinecrest Floors LTDACCON UK LtdContainer Hire Services LtdA.G.S Steel Erectors LtdExcavator Parts Direct