BEAR Scotland, working on behalf of Transport Scotland, has reported strong progress on the rockslope stabilisation scheme at Ledaig on the A828.
On the northern part of the slope, installation of the rockfall protection mesh is largely finished. Crews are currently installing the remaining rock anchors, and minor stitching works are still required. Once this stage is complete, the temporary barrier systems used during construction will be removed.
Subject to favourable weather and continued on-site progress, this phase is expected to conclude by the end of August 2026.
After the current activities are completed, work will pause while BEAR Scotland’s geotechnical specialists finalise the design for the next and final phase. To safeguard road users and the workforce, 24-hour temporary traffic lights will remain in operation during this period.
Further details on the final phase will be shared in the coming weeks once proposals are confirmed.
Michael Baxter, BEAR Scotland's North West Improvements Scheme Manager said: "BEAR Scotland and Transport Scotland remain committed to delivering these essential works to improve the long-term resilience and safety of the A828 corridor.
"We are pleased with the progress being made on the A828 Ledaig rockslope stabilisation project, with substantial work now completed on the northern section of the slope.
"We would like to thank road users, local communities and stakeholders for their continued patience and cooperation while these essential safety improvements are carried out. We look forward to providing further details on the final phase of the project in due course."