18/02/2026

Repairs Scheduled for Burnside Station Footbridge

Network Rail has confirmed that essential repair work will begin next month on the footbridge at Burnside station, marking a major step toward restoring full connectivity for the local community.

The £200,000 project, which is being jointly funded by Network Rail and South Lanarkshire Council, will focus on the staircase on the west side of the station. This specific access point has been closed to the public since March 2025 due to safety concerns.

Engineers are scheduled to arrive on-site on 4 March to begin a four-week programme of works. The refurbishment will involve the replacement of worn stair treads, comprehensive repainting of the steelwork, and structural repairs to the landing area.

-- Advertisement --
NorthernAsbestosServicesLtd

While the staircase linking the footbridge to the platform will remain a restricted construction site for the duration of the project, all other areas of the footbridge crossing will remain open and accessible. The main station entrance will also continue to operate as normal.

Richard Kinsella, regional asset manager at Network Rail, said: "These repairs will provide a safer, more dependable route for everyone using the station. We're working closely with South Lanarkshire Council to complete the work as efficiently as possible."

The closure of the stairs has been a significant point of frustration for commuters over the past year. Councillor Joe Fagan, leader of South Lanarkshire Council, welcomed the start of the repairs, stating: "We know that this staircase being closed to the public has been incredibly disruptive to many local people, but obviously the safety of its users is paramount. I am therefore delighted that, through our partnership working with Network Rail, work will be starting so soon and that everyone who uses the station will have the footbridge open and available to them in a matter of weeks."

The project is expected to be completed by 29 March.

Latest Construction News

20/07/2026
SSEN Transmission has begun drilling at Rattray Head, near Peterhead, marking a key construction milestone for the Spittal to Peterhead High Voltage Direct Current (HVDC) scheme. Work that commenced this month involves Horizontal Directional Drilling (HDD) beneath the coastline to forge the critica
Read More
20/07/2026
Family-owned, Glasgow-based housebuilder AS Homes Scotland has submitted a planning application for 59 new affordable homes in Glasgow's East End, in partnership with Home Group, one of the UK's largest providers of high-quality housing and integrated health and social care support. Located on the
Read More
20/07/2026
The Construction Industry Training Board (CITB) and the Federation of Master Builders (FMB) have launched a new RMI (Retrofit) Sector Skills Plan, developed with input from the Sector Advisory Group on which NFRC sits. NFRC has welcomed the plan and its aims. Focusing on domestic retrofit and on he
Read More
20/07/2026
Three Robertson-delivered projects have been recognised by the Royal Institution of Chartered Surveyors (RICS) as exemplars of the built and natural environment across the UK at recent regional ceremonies. In Scotland, the comprehensive refurbishment of BlackRock's Edinburgh office secured the Comm
Read More
20/07/2026
Glasgow city centre will be handed over to families for a celebratory weekend as the refurbishment of George Square reaches its next milestone. The phased reopening is already under way, with the north carriageway returning to use on 26 June following works that began in May last year. Plans are b
Read More
20/07/2026
As Andy Burnham prepares to enter Downing Street, the Federation of Master Builders (FMB) has urged the incoming Prime Minister to prioritise rapid housing delivery and targeted support for small construction firms as the economy stagnates. Making the call, Brian Berry, Chief Executive of the FMB s
Read More
20/07/2026
Scottish Ministers have granted consents and marine licences for the North and South Caledonia offshore wind farms in the Moray Firth. Together, the schemes will cover around 429 km² and host up to 140 wind turbines. According to the projects, they could generate enough electricity annually to supp
Read More
20/07/2026
SSEN Transmission has revised plans for a temporary construction compound near Contin after listening to concerns raised by the local community during consultation and engagement. The facility, which will support delivery of the mainland underground cable section of the Western Isles HVDC Link, wil
Read More
17/07/2026
Construction has begun on a new £3.3 million paint facility at BAE Systems’ Govan shipyard in Glasgow as part of a wider programme to modernise the city's naval shipbuilding infrastructure. The new facility will allow ship blocks to be painted in a dedicated space, freeing up existing areas at the
Read More
17/07/2026
Retrofit and energy-efficiency specialist Procast Group has secured two awards at the Energy Efficiency Awards, with apprentice electrician Cameron Sleith also recognised as Apprentice of the Year. The company was named Regional Insulation & Fabric Installer and Contractor of the Year at the awards
Read More
SEEIT3DJames Smith Fencing LtdCelsius Plumbing and Heating (Edinburgh) LtdPrestige Concrete Sectional GaragesNorthern ContainersHorizon Reinforcing & Crane Hire Co LtdJ Building Contractors LtdLSMannCreagh Concrete Products LtdThe Sandstone Specialists