M8 Hillington Interchange Bridge Refurbishment Enters Phase Four

Amey, working for Transport Scotland, is progressing a major programme of bridge refurbishment on the M8 at Junction 26 (Hillington Interchange).

The £9 million scheme, running across five phases from September 2025 to spring 2026, delivers extensive repairs and upgrades to four key bridge structures, including vehicle parapets, structural waterproofing, safety barriers and carriageway surfacing.

Phase Four will operate from Friday 13 February until Sunday 8 March 2026 under a 2+2 contraflow. Overnight (8pm to 6am) closures of the M8 Junction 26 eastbound on-slip will continue throughout this phase, alongside overnight closures of the M8 Junction 26 westbound off-slip and the Junction 25A westbound off-slip.

Diversions will be as follows:

- North of Hillington Interchange (Renfrew/Braehead): traffic seeking the Junction 26 on-slip should circulate Hillington Interchange, then use Renfrew Road, Shieldhall Road and Helen Street to join the M8 eastbound at Junction 24 (Helen Street Interchange).

- South of Hillington Interchange (Hillington Industrial Estate): traffic should follow Hillington Road to Paisley Road West, then Helen Street, and join the M8 eastbound via the Junction 24 on-slip.

-- Advertisement --
NorthernAsbestosServicesLtd

For eight nights (25 February to 5 March), Junctions 25A and 26 will close at the same time, together with a closure of the westbound carriageway. During this period, the secondary westbound carriageway will also be closed with the following diversion:

- M8 secondary carriageway traffic: leave the M8 westbound at Junction 23, follow Paisley Road West to Hillington Interchange, where the diversion ends and vehicles rejoin the M8.

The contraflow lane will remain open for all westbound traffic. The Junction 24 and Junction 25 westbound off-slips will stay open; however, both on-slips will close, as will the Junction 25A and Junction 26 westbound off-slips. When the Junction 24 and Junction 25 on-slips are closed, vehicles should use the same Paisley Road West diversion to access the M8 westbound. During closures of the Junction 25A and Junction 26 westbound off-slips, traffic will be diverted as follows:

- M8 Junction 26 westbound off-slip: continue to the M8 westbound Junction 27 off-slip, take the fourth exit at the roundabout and follow Renfrew Road northbound to the next roundabout to join the M8 eastbound, then exit to rejoin the M8 westbound.

- M8 Junction 25A westbound off-slip: continue on the M8 westbound and exit via the Junction 26 off-slip to Hillington Interchange. Turn right onto Hillington Road, then take King's Inch Road and turn right onto Old Govan Road to the end of the diversion. If Junction 26 is closed at the same time, follow the diversion above for the Junction 26 westbound off-slip closure.

A 40mph temporary speed limit, enforced by average speed cameras, will be in place throughout to protect both the workforce and road users, with construction operating 24/7. Further overnight closures will be required for traffic management set-up and changes, with advance notifications provided on swtrunkroads.scot. Recovery vehicles will be on standby.

The scheme has been developed in consultation with Transport Scotland, Traffic Scotland, the emergency services, Renfrewshire Council, Glasgow City Council, West Dunbartonshire Council and Braehead Shopping Centre.

All works are weather dependent and may be postponed or rescheduled in unfavourable conditions.

Latest Construction News

22/07/2026
The £26m Grade A office at Dundee Waterfront, delivered by Robertson for Dundee City Council as part of the city's £1.6bn regeneration programme, has reached full occupation after global software firm N-able joined existing tenant Thorntons. Built by Robertson Construction Tayside, the six-storey J
Read More
22/07/2026
Ground has broken on a permanent spectator stand and team dugouts at the Meadowbank grass pitch at Kirkwall Grammar School (KGS). The project is fully funded by the Scottish Football Association and was proposed by the newly formed Orkney Football Hub, which brings together representatives from Ork
Read More
22/07/2026
Transport Scotland's operating company, BEAR Scotland, will renew approximately 900 metres of road surface to deliver smoother and safer journeys for drivers. A signed diversion will be in place, directing traffic to remain on the M9 northbound to turn at Junction 9, then return southbound to exit
Read More
22/07/2026
CCG (Scotland) has started the second phase of the Athletes' Village development in Glasgow's East End, beginning construction of 58 affordable homes for mid-market rent aimed at households on low to middle incomes. The scheme is funded by socially conscious investor Thriving Investments and marks
Read More
22/07/2026
The Scottish Government is increasing support for small and medium-sized haulage firms by allocating an additional £1 million to its SME Fleet Analysis Support fund, following strong interest from operators across the country. This next phase will enable more businesses to access tailored assessmen
Read More
22/07/2026
Galliford Try has been selected for the new Crescent Purchasing Consortium (CPC) Construction and Capital Works framework. The company’s appointment spans all five regional lots across England, Wales and Scotland. The framework, which will run for a maximum of eight years, will be used to procure a
Read More
22/07/2026
SP Energy Networks is rolling out advanced technology to ensure Glasgow's electricity system is ready to support athletes, officials and visitors during Glasgow 2026. As part of a major resilience programme, the network operator has been testing Power Survey's state-of-the-art Mobile Asset Assessme
Read More
22/07/2026
Major strides have been made in recent months on the Corran Ferry Infrastructure Improvement Scheme (CFIIS), with activity advancing at both Nether Lochaber and Ardgour. Supported by £30 million via the Inverness and Highland City-Region Deal—comprising £20 million from the UK Government and £10 mi
Read More
21/07/2026
Kier has been appointed to the new YORhub YORbuild Major Works 2 framework, worth £1.5bn, enhancing its capacity to deliver major public sector projects across Yorkshire and the Humber, the North East and neighbouring areas. The framework provides access to substantial building schemes for eligible
Read More
21/07/2026
Residents, community organisations and other stakeholders are being urged to share their views in the latest phase of Stirling's new Local Development Plan (LDP) consultation before the deadline. This round focuses on the overall spatial strategy for the area and the specific site options being cons
Read More
SEEIT3DFyfe BrickworkInverness Core Drilling LtdStuart King Architecture & Design LtdNew Home Quality ControlRural House LtdJames Macqueen Building Contractors LtdHodge Plant LimitedNick Ives JoineryListers Concrete Pumping