Network Rail Outlines Christmas Engineering Programme

Network Rail will undertake a concentrated programme of Christmas and New Year engineering across Scotland's Railway and key cross‑border sections, with teams working around the clock from 24 December to 2 January to bolster safety, reliability and resilience.

The festive works package centres on signalling, bridge renewals, track upgrades and junction replacement, sequenced to take advantage of extended access windows while traffic is lighter.

Key schemes include:

- Portobello, Edinburgh (24–27 December): signalling upgrades to improve route reliability on the approaches east of the city.

- Bowling, West Dunbartonshire (24 December–2 January): construction and installation of a new railway bridge, delivered via a planned blockade on the local corridor.

- Motherwell–Cumbernauld (25 December–2 January): track renewal to provide a smoother, more reliable railway on this strategic commuter and freight link.

- Hanslope, West Coast Main Line (25 December–5 January): replacement of a worn junction to increase performance and asset life on cross‑border flows.

-- Advertisement --
NorthernAsbestosServicesLtd

- M6 overbridge renewal (31 December–15 January): removal and renewal of a 1960s rail bridge spanning the motorway to future‑proof a key section of the West Coast route.

- Kingmoor, north of Carlisle (1–7 January): installation of new signalling to enhance performance and resilience on the West Coast Main Line.

By scheduling this portfolio during the festive period, Network Rail can combine possessions to minimise repeated disruption and deliver complex, labour‑intensive activities in fewer, longer shifts.

Ross Moran, route director at Network Rail Scotland, said: "Christmas and New Year give us a unique opportunity to deliver major improvements while fewer people are travelling. By using this time wisely, we can carry out essential work that will make Scotland's railway safer and more reliable for years to come.

"I'm incredibly thankful to the teams who will be working through the festive period to make these upgrades happen. Their commitment behind the scenes is what keeps the railway moving. For anyone planning a journey, I'd encourage you to check your plans in advance and allow a little extra time."

Mark Ilderton, ScotRail Service Delivery Director, said:

"Whenever Network Rail carries out essential improvement work, our priority is to ensure customers can continue to travel with confidence.

"While these upgrades mean journeys will be different for some customers over the Christmas period, we'll have reliable alternative transport in place and clear, timely information to help keep people moving.

"We understand that this work will cause inconvenience for some customers, but it is crucial to maintaining and improving the reliability of the railway. We appreciate our customers' patience and understanding and encourage everyone to check their journey before travelling."

Collectively, the programme targets long‑term asset condition, capacity for future growth and operational performance across Scotland's network and its cross‑border arteries.

Latest Construction News

20/10/2026
Scotland's leading public sector framework provider has opened bidding for a £900 million Refurbishment and Modernisation programme aimed at delivering urgent and planned works across housing and public buildings. The Scottish Procurement Alliance's Refurbishment and Modernisation framework (RM4S)
Read More
20/10/2026
A £1 million grant programme has been launched to help owners return vacant listed buildings across Glasgow to productive use. The Heritage Building Viability Grant Scheme, funded by Glasgow City Council and administered by Glasgow City Heritage Trust, is designed to bring floorspace in some of the
Read More
20/10/2026
Road resurfacing on the A702 at West Linton will take place over six nights from Monday 9 to Friday 13 November, and on Monday 16 November 2026, requiring overnight closures. Transport Scotland's operating company, BEAR Scotland, will deliver the scheme. For safety, the A702 will be closed each ni
Read More
20/10/2026
SP Energy Networks chief executive Nicola Connelly has welcomed the launch of a new industry plan setting out how the biggest grid upgrade in living memory will boost employment and economic growth across the UK. The Electricity Networks Sector Growth Plan – led by the Energy Networks Association (
Read More
20/10/2026
An £8 million scheme is under way to enhance accessibility for passengers at Dalwhinnie and improve performance on the Highland Main Line. The project will install a new crossover so trains can switch between tracks, enabling northbound services to use Platform 1 when step-free access is required.
Read More
20/10/2026
The Scottish Government intends to award Wills Bros Civil Engineering Ltd the contract to dual the A9 between Pitlochry and Killiecrankie, Economy, Tourism and Transport Secretary Stephen Flynn has announced. The move represents the final stage of procurement for the fifth A9 Dualling scheme to rea
Read More
20/10/2026
Residents in Clackmannanshire are already benefiting from a new electric nine-seater minibus provided by Robertson Construction Central East, part of the contractor's social value commitments linked to the Wellbeing Village and Lochies School development in Alloa. During construction, the vehicle i
Read More
20/10/2026
A major new study will examine how climate change could trigger cascading disruption across Scotland's critical infrastructure, giving organisations a clearer view of risks to the services people rely on daily. Commissioned by the Climate Ready Infrastructure Scotland Forum (CRIS) — a partnership o
Read More
20/10/2026
Clark Contracts has secured a place on Pagabo's Major Works Framework, enhancing its ability to support public sector bodies in delivering major construction and refurbishment schemes. The framework, expected to be worth up to £5bn over four years, follows the creation of a 10-year strategic delive
Read More
20/10/2026
North Ayrshire Council has carried out its annual winter dry run this month as it gets ready for the colder months. Roads staff took part in the exercise as part of preparations to keep roads, footways and communities safe and accessible during severe weather. It follows a meeting of Cabinet at wh
Read More
SEEIT3DRBT Underfloor LimitedE & P BricklayingSinclair Industries LtdOrd Industrial & Commercial Supplies LtdPlant Machinery TradingLowland ArchitectsComplete Property ServicesLothian Bricklaying ServicesOptimo Waste LTD