23/10/2025

Inch Cape Offshore Wind Farm Installs First 85km Export Cable

The Inch Cape Offshore Wind Farm has achieved a significant infrastructure milestone with the successful installation of the first of its two 85-kilometre offshore export cables off the east coast of Scotland.

The 220 kV, three-phase cable will serve as the crucial link to transmit power from the 1.1 gigawatt (GW) wind farm to the project's new onshore substation, which is currently under construction at Cockenzie, East Lothian.

The cable, which is manufactured by Orient Cable and is among the largest AC export cables globally, was installed in three 28-kilometre sections by Enshore Subsea, utilising the CMOS Installer cable lay vessel. The installation required two offshore joints, completed using the North Sea Giant, and the cable will shortly be buried in the seabed.

-- Advertisement --
NorthernAsbestosServicesLtd

John Hill, Inch Cape Project Director, welcomed the completion of the complex offshore scope. "This is the critical link between the offshore and onshore substations, with great work by the Inch Cape team and our supply partners," he said. "This achievement is testament to the momentum Inch Cape has gathered since early summer, and to the team's focus on the successful delivery of key milestones."

Inch Cape is now well into its offshore construction phase, with both the offshore substation platform and the first export cable installed, and the first of its XXL monopiles delivered to the Port of Leith.

The project is on track for first power in late-2026 and full commercial operations in 2027. Once complete, the wind farm, owned in a 50/50 joint venture by ESB and Red Rock Renewables, will generate almost 5 terawatt hours (TWh) of energy each year, enough to power half of the homes in Scotland.

The second 85km export cable will also be installed by Enshore Subsea in three 28km sections during a later campaign in 2026. Next year will also see the installation of the project's foundation structures and the first of 72 Vestas 15MW turbines.

Latest Construction News

04/09/2026
Morgan Sindall Construction has been appointed by the Scottish Fire and Rescue Service (SFRS) to demolish and rebuild the Liberton station in the capital. Procured via the SCAPE Scotland Construction Framework, the £10m scheme marks a significant investment in SFRS infrastructure and will create a
Read More
03/09/2026
Network Rail says it has hit a key milestone in efforts to strengthen Scotland's railway against severe weather, with £130m invested in resilience over the last two years. The move comes amid tougher operating conditions, including higher temperatures, increasingly unpredictable rainfall and more f
Read More
04/09/2026
ESB has reached Final Investment Decision (FID) and executed the principal construction agreements for the 96MW Chleansaid Wind Farm, near Lairg in the Scottish Highlands. The move signals the start of delivery for one of the utility's most strategic renewable projects and its first ESB-developed on
Read More
04/09/2026
Glasgow City Region has welcomed confirmation of £22.7 million in first-year funding from the UK Government's Local Growth Fund, aimed at accelerating business growth, improving skills and employability, and creating new commercial space across the area. The award represents the opening phase of a
Read More
04/09/2026
A major planned maintenance scheme has begun across East Renfrewshire, with 190 council homes set to receive new kitchens in the first year of works. The initiative is part of East Renfrewshire Council's longer-term investment in its housing stock. Approximately 300 kitchens are due to be replaced
Read More
04/09/2026
A £9.8m Local Growth Fund programme for the Forth Valley has moved into delivery after the UK Government approved the region's Investment Plan, paving the way for projects to boost businesses, skills, housing and infrastructure across Falkirk, Stirling and Clackmannanshire. Following approval of th
Read More
04/09/2026
Approval of a new Local Growth Fund Investment Plan will deliver £11.8 million to Ayrshire between 2026 and 2029, targeting higher household incomes and stronger local economies through infrastructure, business support and skills. The funding reflects the collective ambition of the Ayrshire Regiona
Read More
04/09/2026
SNIPEF's State of Trade Survey for the first quarter of 2026 points to steady activity tempered by growing caution. Work volumes have held up, payment performance is broadly consistent and product availability remains manageable. However, order books are more finely balanced, margins are under press
Read More
04/09/2026
Farrans has been appointed by ESB to deliver the Civil Balance of Plant (CBoP) for the 96MW Chleansaid Wind Farm near Lairg in the Scottish Highlands. The contract signals the start of delivery on one of ESB's most strategically important renewable schemes and marks its first onshore wind project i
Read More
03/09/2026
Sky has secured planning permission for its new Livingston Campus, unlocking a major investment and underscoring the company's long-term commitment to Scotland. The decision marks a key step towards delivering a significant new workplace development in West Lothian. The approved plans will bring Sk
Read More
SEEIT3DIredia ResourcesGalaxy Window BlindsAlternative Tying Systems LtdSips Eco Panel Systems LtdApollo Scaffolding Ties LtdHBB GeoSales LtdFP McCann LtdContainexSEEIT3D