Network Rail is preparing for the installation of a new active travel bridge to connect Methilhill and Cameron Bridge.
Over the next two weeks, Network Rail will crane the 129-metre structure into position, connecting the various active travel paths under construction as part of the Levenmouth Rail Link project.
That work is taking place from 2 to 16 September, with nine pre-fabricated sections, including bridge piers, staircase sections and four spans of bridge-deck being installed.
The installation had originally been planned ahead of the opening of the rail link but was delayed due to the company building the bridge going into administration this year.
Complex discussions with the administrator to release the part-built structure, as well as the need to source a new supplier, compounded that delay.
Now, with plans in place to complete the work, no parking and no waiting zones have been introduced on Poplar Road and Kirkland Walk until 16 September so that work vehicles can access the site.
Tommy McPake, senior programme manager, Network Rail said: "The team has worked hard to build the alternative walking route and then to deliver on the revised timeline to get the structure complete and site prepared for the bridge installation.
"While it was disappointing not to have the bridge in place ahead of the opening, it was due to circumstances beyond our control that could not have been foreseen.
"We hope the new bridge allows the community in Methilhill the opportunity to fully join in the excitement the return of the passenger service to Levenmouth has created. We're now very close to completing the connection to their local station which will enable them to easily access all of the opportunities the railway delivers.
"It is always exciting to see the crane lift the bridge into position to create what will be a very impressive looking structure that will support active travel in the area.
"We are grateful to the surrounding communities for their cooperation as we bring the bridge sections to site and look forward to completing the work in the coming weeks."
The bridge will be craned into position using a 750-tonne crane.
At its highest the bridge will sit approximately 8m above the river and will drop in height as it crosses the railway to connect into Cameron Bridge station.
Time and date
CONSTRUCTION DIRECTORY
Construction News
04/09/2024
Network Rail Unveils Levenmouth Rail Link Bridge Installation
Latest Construction News
06/09/2024
Balfour Beatty has scooped a £27 million contract to deliver the Comrie flood protection scheme in Scotland, on behalf of Perth and Kinross Council. Awarded through the SCAPE Civil Engineering Framework, a rapid access framework designed to drive collaboration, efficiency, time and cost savings, ...
06/09/2024
Construction work has been completed on nine new homes in Chryston, North Lanarkshire. The homes, for Caledonia Housing Association, are located at Berryknowe Avenue. Built by Morris & Spottiswood, the £2.1 million development, which was supported by £1.3 million of Scottish Government funding, ...
06/09/2024
The Govan - Partick Bridge has formally opened. The £29.5 million Glasgow City Region City Deal project - funded by the Scottish and UK Governments - re-establishes the historic connection between Govan and Partick, with the bridge crossing between Water Row on the south side and Pointhouse Quay ...
06/09/2024
Perth and Kinross Council is piloting a cutting-edge machine to improve the speed and efficiency of pothole repairs. The JCB Pothole Pro is being trialed on roads throughout the region, operated by a skilled Tayside Contracts roadworker with the support of a five-person team. The machine, which ...
06/09/2024
The Kingdom Group has appointed Dan Blake as its Group Director of Communities. The new role was created following a structural evaluation of the Kingdom Group, ensuring the organisation is well-positioned to meet the needs of its customers now and in the future, delivering an exceptional customer ...
06/09/2024
DM Hall is marketing a fully secured industrial yard with four buildings at 1 Deerdykes Place, Cumbernauld G68 9HE at offers over £2.1 million. The property lies to the north west of Deerdykes Place, overlooking Westfield Road, one of the area’s main link roads which in turn affords easy access to ...
05/09/2024
Scottish Water has successfully completed the installation of a £852,000 solar scheme at a site in Perth. The scheme has seen 1,236 ground mounted PV (photovoltaic) panels installed on the site at Gowan's Terrace which hosts a Scottish Water office and water treatment works. It is set to generate ...
05/09/2024
A new £400,000 fund has been approved by Glasgow City Council to help improve the look and feel of the city centre and find new uses for vacant property. The City Centre Improvement Grant Fund will provide awards of up to £20,000 to businesses and organisations who meet the criteria. Split into ...
05/09/2024
MacInnes Bros Ltd has been awarded the construction contract for Phase 2 of the Cnoc Soilleir development, following the confirmation of the final £2.1 million grant award from Highlands and Islands Enterprise (HIE). This follows grants of £5 million by Scottish Government, as well as an earlier ...
05/09/2024
The Scottish Government has published new legislation for the creation of a carbon budget approach to setting climate targets. The Climate Change (Emissions Reduction Targets) (Scotland) Bill seeks to amend the Climate Change (Scotland) Act 2009, in response to the Climate Change Committee's (CCC) ...