SSE Renewables has announced the successful completion of the installation and energisation of the first of two new hydro power turbines at Perthshire's iconic Tummel Bridge Power Station.
This marks a major milestone in SSE Renewables' £50 million investment to repower the hydro station which, once complete, will increase the station's potential output from 34 to 40 megawatts (MW) during optimum conditions.
The project involves the replacement of the station's two original 'Camel Back' twin-runner, horizontal Francis hydro turbines, which were installed in 1933, with new modern runner technology that will extend the power station's working life by at least 40 years.
The new modern units will significantly improve efficiency and enable a higher generation output by extracting the maximum energy from the available water.
The project team will continue to focus on the second turbine, which is installed and now undergoing dry commissioning tests. The turbine is expected to be energised and operational by mid-summer 2024.
Neil Lannen, Director of Hydro Asset Management at SSE Renewables, said: "This is one of the largest investments we've made to our existing hydro fleet in recent times. This project demonstrates our ongoing commitment to invest in hydro power, so we're proud to reach such a significant milestone in the Tummel Bridge Power Station replant.
"Hydro power has a vital role to play in our path to achieving net zero carbon emissions in the UK by 2050 and this investment will ensure Tummel Bridge continues to play a crucial role in Scotland's energy mix for generations to come. The project is a perfect example of extending the working life of a station which has successfully generated clean, green energy for around 90 years.
"Getting to this point in the project wouldn't have been possible without the commitment of our contract partners. We would also like to thank the local community for their continued cooperation as our attention now turns to the installation and commissioning of the second turbine unit, which is expected to be completed this summer."
The delivery of the repowering programme has also supported Scotland's regional supply chain, helping sustain and create local jobs in the Highlands throughout the duration of the works.
Inverness-headquartered Global Infrastructure has operated as Principal Contractor for the duration of the project, establishing and controlling a complex site, coordinating and managing the safety and work packages of all contracting staff and visitors and delivered enabling works including site establishment, superstructure bracing work, and general site readiness. Global also successfully managed the complex dismantling of the original 90-year-old equipment, complete civil works to remove original foundations within the powerhouse down to bedrock and reinstate a new foundation for the plant.
Stantec, with bases in Edinburgh and Glasgow, has led on Civil Design as well as supporting the engineering team; and Voith, a leading manufacturer of hydropower turbines and generators, has led on the Mechanical and Electrical (M&E) elements of the project.
David Macdonald, Managing Director, for Global Infrastructure, said: "Tummel bridge is a vital part of SSE moving towards zero carbon, we are delighted to have played a leading role in delivering this project for this client.
"This project was a complex design with a lot of interface management between different supply chain, we hope this is the first of many projects we will delivering with SSE over the next 5 years."
Craig Scott, Stantec's Director of Hydropower and Dams, said: "The Tummel Bridge upgrade is a truly unique hydro scheme. I'm proud Stantec's energy teams were able to play an important role in the design, working closely and collaboratively with SSE Renewables and the contractors.
"Successfully rehabilitating such an iconic, listed power station demonstrates a viable future for extending hydro infrastructure life, and is a shining example of how Scotland's hydropower design industry is at the forefront of the low-carbon agenda. The complex works carried out at Tummel can help spur the whole industry on to deliver proposed new-build hydro facilities, and nurture future infrastructure design talent."
Construction News
20/05/2024
Major Milestone In Redevelopment Of Tummel Bridge Power Station


30/04/2025
Plans for a £43 million education campus on the Isle of Mull have moved forward, Argyll and Bute Council has confirmed.
Following a decision earlier this month on the preferred location, the council will now progress with developing a detailed brief and concept design to inform the overall busines

30/04/2025
Global engineering and development consultancy Mott MacDonald has been appointed by Strathclyde Partnership for Transport (SPT), in collaboration with Glasgow City Council on behalf of the Glasgow City Region, to progress two key elements of the Case for Investment for the ambitious Clyde Metro proj

30/04/2025
Members of the Caithness Committee have unanimously agreed to adopt the Caithness Area Place Plan (APP).
The committee also committed to fully supporting and promoting the plan, ensuring it is considered within other relevant plans, strategies, developments, and funding opportunities impacting the

30/04/2025
Plans for a new business park at Oban Airport have advanced significantly with the announcement that Argyll and Bute Council has appointed hub North Scotland to oversee the project and Robertson Construction as the main contractor.
The Oban Airport project is a key component of the council's Tax In

30/04/2025
Contractors engaged in public sector projects across the UK will soon be subject to random and targeted spot checks on their payment practices.
This move by the UK government is designed to tackle the persistent issue of late payments throughout the construction supply chain.
According to advice

30/04/2025
Ten new affordable flats for social rent have been completed by The Highland Council in Carrbridge, addressing a significant demand for smaller properties in the area.
The development, named Struan Court after the former Struan Hotel which previously occupied the site, offers eight one-bedroom and

30/04/2025
The City of Edinburgh Council has held collaborative summit with key partner organisations to explore avenues for expanding the availability of accessible housing across the capital.
The Accessible Housing Summit, hosted by the council, brought together representatives from the third sector, housin

30/04/2025
A significant step forward has been taken in the development of a new £16 million flood prevention scheme designed to safeguard Bridge of Allan. Stirling Council has approved the procurement of a contract to design and construct the essential flood defences.
The planned infrastructure will offer pr

30/04/2025
A significant 64% of companies within Scotland's renewable energy supply chain are actively investing in skills, capabilities, and facilities to capitalise on the nation's burgeoning clean energy market over the next three to five years, a survey by Scottish Renewables has revealed.
The findings we

30/04/2025
A collaborative effort between McTaggart Construction and West Dunbartonshire Council is set to bring new affordable housing and a range of community benefits to the Willox Park area. The partnership will deliver a 17-unit, client design led, affordable housing development, procured through Scotland