Network Rail has announced the successful completion of a £1.9 million, six-day programme of upgrade of the Stranraer line.
The project involved replacing more than 1km of track at Laggansarroch viaduct, near Girvan, including the use of 200 recycled plastic (composite) sleepers over the structure itself. It's part of efforts to help Network Rail in its aim to achieve a net zero carbon target by 2035.
As well as the composite sleepers, engineers used 1800 steel sleepers, 1500 tonnes of ballast (stone which supports the track) and 2km of new rails during the work.
At Kilkeran, 650m of new track drainage was also installed during the project.
With the line closed due to the ongoing demolition of the former Station Hotel at Ayr, a 65-tonne tamper - a machine used to maintain tracks - was brought in by road and lifted onto the railway at Stranraer using a 500-tonne crane.
That crane was also used to lift two of ScotRail's trains onto lorries, allowing them to return to their depot in Glasgow for vital maintenance.
Gerry McQuade, capital delivery director at Network Rail Scotland said: "The work we've carried out on the Stranraer line will help to keep trains moving during periods of extreme rainfall and bring smoother journeys for passengers. A huge thanks to everyone for coming up with an innovative solution to carry out the work, and for working around the clock for six days to complete the job."
Craig Barclay, operations director at Rail Systems Alliance Scotland said: "I'm pleased our alliance between Network Rail, Babcock International and Arcadis was able to devise a new plan to complete this vital work, given the ongoing closure of the railway at Ayr, and also assist ScotRail in returning their two Class 156 trains to Corkerhill depot for vital maintenance."
Construction News
13/03/2024
£1.9m Programme Of Stranraer Line Improvement Works Complete


11/07/2025
Scottish Canals has announced that it is now halfway through its significant engineering programme on the Falkirk Flight of the Forth & Clyde Canal, an ambitious project spanning from locks 3 to 16.
This undertaking represents the biggest single investment in Scotland's canals since the Millennium

11/07/2025
The Construction Industry Training Board (CITB) has announced the elite line-up of finalists for SkillBuild 2025, bringing the nation's most promising construction trainees and apprentices one step closer to being crowned the best in their trade. Recognised as the largest and longest-running industr

11/07/2025
The Eastern Green Link 2 (EGL2) project has confirmed a temporary adjustment to working hours at its converter station site near Boddam, Peterhead.
This strategic decision is designed to facilitate crucial construction activities and ensure the timely delivery of this nationally significant energy

11/07/2025
Aberdeen-based manufacturer Nexos has announced a significant boost to its operations, with its heating, ventilation, and air conditioning (HVAC) team securing £8 million in new contracts since January this year.
This latest achievement follows a period of substantial growth for the firm, which re

11/07/2025
Glasgow-based construction firm CCG (Scotland) Ltd is celebrating a significant achievement as three of its landmark residential developments have been shortlisted as finalists for the prestigious RICS UK Awards 2025.
This year marks the first time the awards have operated on a fully national form

11/07/2025
The Scottish Government has today launched a significant new initiative, the £2 million Heavy Goods Vehicle (HGV) Market Readiness Fund for 2025-26, signalling a clear commitment to accelerating the decarbonisation of Scotland's road freight sector. The fund is specifically designed to encourage col

10/07/2025
RJ McLeod has officially begun construction works at the site of £155million Mill Rig Wind Farm in South Lanarkshire, a major milestone for onshore wind set to power approximately 45,000 homes annually.
Developed by UK renewables specialist OnPath Energy, the 33.4 MW onshore wind project is expecte

10/07/2025
Work has now officially commenced on the highly anticipated £6.7 million community facility in Milton, Glasgow, which will become the new, modern home for Scaraway Nursery and the vital local charity, North United Communities (NUC).
This state-of-the-art development is slated for completion by sum

10/07/2025
Construction of Bishopbriggs' new £31.5 million Balmuildy Primary School has taken a significant step forward as essential enabling works commence this summer, strategically timed during the school holidays to minimise disruption.
These preparatory activities will pave the way for the main build t

10/07/2025
Cumbernauld's urban landscape is poised for a significant transformation following the green light and nearly £3 million in funding for a new five-year wildlife restoration project.
Titled 'Nurturing Natural Connections', the initiative promises extensive tree planting and wildflower sowing, aimin