Network Rail Progress £2.9m Neilston Bridge Replacement Project

Network Rail has welcomed a "big step forward" for a £2.9m project to replace a bridge on a key walking route over the Neilston railway line.

A replacement bridge deck has been lifted into position, after Network Rail engineers worked around the clock on Sunday 20 and Monday 21 August.

On-site teams used a Kirow 1200, the largest rail-mounted crane in the UK, to lift the pre-cast concrete components into place.

The overhead line equipment that powers electric trains was disconnected from the old bridge deck while new concrete beams were installed. It was then connected to the new bridge to allow trains to run from Tuesday morning.

-- Advertisement --
NorthernAsbestosServicesLtd

Susan Menmuir, scheme project manager for Network Rail, said: "The existing concrete bridge deck was gradually deteriorating and nearing the end of its lifespan.

"Our work will extend the lifespan of the bridge, helping to keep the railway safe and reliable for years to come.

"I'd like to thank passengers and the community for their patience. I understand there's never a good time to carry out work that disrupts passenger trains. By working on Sunday and Monday, however, we were able to minimise disruption on Saturday, which is now the busiest day for rail travel in Scotland."

Demolition of the former bridge deck, as well as the removal of a disused bridge near Neilston station, took place a week earlier on 13-15 August.

The diverted footpath to Balgray reservoir will remain in place until November this year whilst further work is carried out to refurbish the structure.

Latest Construction News

20/10/2026
Scotland's leading public sector framework provider has opened bidding for a £900 million Refurbishment and Modernisation programme aimed at delivering urgent and planned works across housing and public buildings. The Scottish Procurement Alliance's Refurbishment and Modernisation framework (RM4S)
Read More
20/10/2026
A £1 million grant programme has been launched to help owners return vacant listed buildings across Glasgow to productive use. The Heritage Building Viability Grant Scheme, funded by Glasgow City Council and administered by Glasgow City Heritage Trust, is designed to bring floorspace in some of the
Read More
20/10/2026
Road resurfacing on the A702 at West Linton will take place over six nights from Monday 9 to Friday 13 November, and on Monday 16 November 2026, requiring overnight closures. Transport Scotland's operating company, BEAR Scotland, will deliver the scheme. For safety, the A702 will be closed each ni
Read More
20/10/2026
SP Energy Networks chief executive Nicola Connelly has welcomed the launch of a new industry plan setting out how the biggest grid upgrade in living memory will boost employment and economic growth across the UK. The Electricity Networks Sector Growth Plan – led by the Energy Networks Association (
Read More
20/10/2026
An £8 million scheme is under way to enhance accessibility for passengers at Dalwhinnie and improve performance on the Highland Main Line. The project will install a new crossover so trains can switch between tracks, enabling northbound services to use Platform 1 when step-free access is required.
Read More
20/10/2026
The Scottish Government intends to award Wills Bros Civil Engineering Ltd the contract to dual the A9 between Pitlochry and Killiecrankie, Economy, Tourism and Transport Secretary Stephen Flynn has announced. The move represents the final stage of procurement for the fifth A9 Dualling scheme to rea
Read More
20/10/2026
Residents in Clackmannanshire are already benefiting from a new electric nine-seater minibus provided by Robertson Construction Central East, part of the contractor's social value commitments linked to the Wellbeing Village and Lochies School development in Alloa. During construction, the vehicle i
Read More
20/10/2026
A major new study will examine how climate change could trigger cascading disruption across Scotland's critical infrastructure, giving organisations a clearer view of risks to the services people rely on daily. Commissioned by the Climate Ready Infrastructure Scotland Forum (CRIS) — a partnership o
Read More
20/10/2026
Clark Contracts has secured a place on Pagabo's Major Works Framework, enhancing its ability to support public sector bodies in delivering major construction and refurbishment schemes. The framework, expected to be worth up to £5bn over four years, follows the creation of a 10-year strategic delive
Read More
20/10/2026
North Ayrshire Council has carried out its annual winter dry run this month as it gets ready for the colder months. Roads staff took part in the exercise as part of preparations to keep roads, footways and communities safe and accessible during severe weather. It follows a meeting of Cabinet at wh
Read More
SEEIT3DRBT Underfloor LimitedE & P BricklayingSinclair Industries LtdOrd Industrial & Commercial Supplies LtdPlant Machinery TradingLowland ArchitectsComplete Property ServicesLothian Bricklaying ServicesOptimo Waste LTD