Network Rail Announces West Coast Main Line Modernisation Works

Network Rail has announced a major modernisation scheme for Carstairs junction, as part of a £164m Scottish Government investment in the railway.

The West Coast main line will close for 16 days from Saturday (March 4) as engineers deliver a vital programme of work to upgrade Carstairs Junction.

The closure of the line, between March 4 and March 19, is the first phase of a three-month programme of work which will also see trains diverted and journey-times extended all services between Glasgow/Edinburgh and Carlisle until June.

The work is part of a £164m Scottish Government investment to modernise the key junction for passenger and freight services.

Engineers will simplify and upgrade the track-layout to clear an existing bottleneck on the network, making it more reliable and able to better cope with passenger and freight demands.

-- Advertisement --
NorthernAsbestosServicesLtd

Work on this strategically important route will be complex and Network Rail will complete it in three phases designed to manage the effect on services in the least disruptive way.

During the first phase of the project there will be no direct services to Glasgow Central and Edinburgh on the West Coast main line through Carstairs.

The closure of the junction will affect cross-border operators including Avanti West Coast, Caledonian Sleeper, CrossCountry Trains, London North Eastern Railway and TransPennine Express, who will be operating via diversionary routes or offering alternative journey options during this time.

Liam Sumpter, Route Director, Network Rail Scotland, said: "Carstairs Junction is coming to the end of its life cycle and with the volume of freight and passenger trains passing through each week it's important that we modernise this part of the network.

"By completing this crucial upgrade work we will improve the capabilities and reliability of this strategically important junction, providing better future journeys for passengers and more capacity for freight.

"There's never a good time to close such an important line but this is a huge and extremely complex piece of work that will safeguard the future of the route for years to come.

"We appreciate that this will cause some inconvenience and would like to thank customers for their patience during this time."

Latest Construction News

20/07/2026
SSEN Transmission has begun drilling at Rattray Head, near Peterhead, marking a key construction milestone for the Spittal to Peterhead High Voltage Direct Current (HVDC) scheme. Work that commenced this month involves Horizontal Directional Drilling (HDD) beneath the coastline to forge the critica
Read More
20/07/2026
Family-owned, Glasgow-based housebuilder AS Homes Scotland has submitted a planning application for 59 new affordable homes in Glasgow's East End, in partnership with Home Group, one of the UK's largest providers of high-quality housing and integrated health and social care support. Located on the
Read More
20/07/2026
The Construction Industry Training Board (CITB) and the Federation of Master Builders (FMB) have launched a new RMI (Retrofit) Sector Skills Plan, developed with input from the Sector Advisory Group on which NFRC sits. NFRC has welcomed the plan and its aims. Focusing on domestic retrofit and on he
Read More
20/07/2026
Three Robertson-delivered projects have been recognised by the Royal Institution of Chartered Surveyors (RICS) as exemplars of the built and natural environment across the UK at recent regional ceremonies. In Scotland, the comprehensive refurbishment of BlackRock's Edinburgh office secured the Comm
Read More
20/07/2026
Glasgow city centre will be handed over to families for a celebratory weekend as the refurbishment of George Square reaches its next milestone. The phased reopening is already under way, with the north carriageway returning to use on 26 June following works that began in May last year. Plans are b
Read More
20/07/2026
As Andy Burnham prepares to enter Downing Street, the Federation of Master Builders (FMB) has urged the incoming Prime Minister to prioritise rapid housing delivery and targeted support for small construction firms as the economy stagnates. Making the call, Brian Berry, Chief Executive of the FMB s
Read More
20/07/2026
Scottish Ministers have granted consents and marine licences for the North and South Caledonia offshore wind farms in the Moray Firth. Together, the schemes will cover around 429 km² and host up to 140 wind turbines. According to the projects, they could generate enough electricity annually to supp
Read More
20/07/2026
SSEN Transmission has revised plans for a temporary construction compound near Contin after listening to concerns raised by the local community during consultation and engagement. The facility, which will support delivery of the mainland underground cable section of the Western Isles HVDC Link, wil
Read More
17/07/2026
Construction has begun on a new £3.3 million paint facility at BAE Systems’ Govan shipyard in Glasgow as part of a wider programme to modernise the city's naval shipbuilding infrastructure. The new facility will allow ship blocks to be painted in a dedicated space, freeing up existing areas at the
Read More
17/07/2026
Retrofit and energy-efficiency specialist Procast Group has secured two awards at the Energy Efficiency Awards, with apprentice electrician Cameron Sleith also recognised as Apprentice of the Year. The company was named Regional Insulation & Fabric Installer and Contractor of the Year at the awards
Read More
SEEIT3DAtlas Winch & Hoist Services LtdDublcheck Cleaning GlasgowGreater Good Glass LtdDenfind Stone LimitedForde Training Services LtdThe Water PointKattrak International LtdG M Joinery Scotland LtdLogical Insulation Solutions Limited