Work Continues To Construct New Inverness Airport Station

Construction News Image
Network Rail has announced that work to build the new Inverness Airport station will continue with 54 hours of continuous working from Friday night until Monday morning to carry out work that cannot be undertaken safely while the railway is open.

Since starting work last October the new £14m station at Inverness Airport has seen the construction of new platforms, the creation of the foundations for what will form the footbridge and lifts and the start of work to create the access road and car park at the site adjacent to the airport.

This weekend will see the demolition of the masonry road bridge to the east of the station site, installation of drainage, platform works and welding and stressing of the double-track section which has been created through the station.

-- Advertisement --
NorthernAsbestosServicesLtd

The project, which is scheduled to complete in December, will deliver a two-platform station on the Aberdeen-Inverness line with step-free access, via a footbridge with lifts.

The station will have 64 car parking spaces with 10 electric charging facilities, four disabled spaces and cycle parking. There will be a new access road to the station for motorists and access to both platforms for pedestrians and cyclists.

Inverness Airport station will deliver improved travel links to the growing Inverness Airport Business Park and the new town of Tornagrain.

David Millar, Project Manager for Network Rail said: "The construction of Inverness Airport Station continues to gather momentum and this weekend marks a significant point in the project. The removal of the old masonry arch bridge and connecting the passing loop are both important milestones in the delivery of the new station.

"We apologise for any inconvenience while the line is closed this weekend both to those intending to travel and to anyone who lives close to the site where we will be working continuously from Friday night until Monday morning.

"We appreciate your patience while we deliver this important addition to the area’s transport infrastructure."

Latest Construction News

03/05/2024

The Wheatley Group has been given planning permission from Glasgow City Council to convert the 1930s B-listed Bellgrove Hotel into 14 modern, energy-efficient and affordable flats – eight of which will be wheelchair accessible. Permission has also been granted for a further 56 flats to be built on ...
03/05/2024

Renewable energy leader Drax has announced that it will invest £80 million in a major refurbishment of its iconic 'Hollow Mountain' Cruachan pumped storage hydro power station in Scotland. Global hydropower technology supplier ANDRITZ has been appointed as the main contractor for the Cruachan ...
03/05/2024

Clark Contracts has welcomed the news that the former Dalmarnock Purifier Studios, now branded as EastWorks, has been awarded the Refurbished/Recycled workplace award at the prestigious British Council for Offices (BCO) Awards 2024. The 120-year-old former purifier shed, owned by Clyde Gateway, ...
03/05/2024

Stirling Council has launched a public consultation to shape future developments at the Viewforth and Burghmuir Road areas. The new draft framework and planning brief for Viewforth and Burghmuir covers a key area of the city centre that includes the Viewforth site, existing council buildings, ...
03/05/2024

Morrison Community Care (CCG) Holdco has secured planning permission or its latest project in South Queensferry, marking its third consecutive success. Forming part of a wider 44-hectare masterplan that will include 980 new homes, a primary school and commercial premises on Builyon Road, south of ...
03/05/2024

The Highland Council's Economy and Infrastructure Committee have carried out a review of the last two years of the Community Regeneration Funding Programme, ahead of agreeing changes to how the 2024/25 programme will be delivered. Committee Chair, Cllr Ken Gowans said: "Following a successful two ...
03/05/2024

Perth and Kinross Council and partners are set to progress community-led projects aimed at revitalising homes and improving rural transport links, following a winning bid for Innovate UK Pathfinder Places funding. Funding of £150,000 has been secured following a successful Phase 1 Pathfinder ...
03/05/2024

SGN engineers working on the H100 Fife project have helped support the Methilhill Community Children's Initiative (MCCI) by building an eco-toilet in the charity's learning garden. MCCI provides a safe and engaging space for local children to participate in various outdoor activities, including ...
03/05/2024

SNIPEF, the Scottish and Northern Ireland Plumbing Employers' Federation, has published a draft of its 2024 election manifesto detailing six strategic policy proposals designed to support its members and the broader plumbing and heating profession. Once finalised, the manifesto will be central to ...
03/05/2024

The Scottish Environment Protection Agency (SEPA) have published their 2024-25 Annual Operating Plan, detailing how they will protect and improve Scotland's environment over the next 12 months. The publication follows the launch of a new Corporate Plan at the end of March, which set out the ...
RBT Underfloor LimitedMorris & Spottiswood LtdMaterials Market LtdToner Damp Proofing SuppliesNo HydroBurnside Plant Hire LtdKattrak International Hidromek SalesScotdeck LtdThe Big Block Co LtdSafe Access (Highland) Ltd.
Terms and Conditions
2024/05/07 10:44:23