Network Rail Completes £32m Rutherglen Improvement Project

Network Rail has announced that the route between Rutherglen and Exhibition Centre has re-opened following a £32m improvement project.

Having successfully completed work to the Argyle line, which will reopen as planned today, Monday May 9, following an eight-week programme of extensive engineering works.

The line closed on March 13 to allow engineers to deliver a £32m investment in repairing and renewing tunnels, bridges and tracks between Rutherglen and Exhibition Centre

It was the most significant piece of engineering on the line in a generation and was all designed to improve punctuality and reliability for passengers for years to come.

Engineers removed 500 tonnes of concrete encasement from the tunnels, with 700 structural beams repainted and more than 1,000 square metres of waterproofing applied.

All ScotRail services affected by the work resumed in time for the start of Monday morning service.

Jenny Gilruth, Transport Minister, said: "Passengers will undoubtedly welcome the news that this particular programme of work and its associated closures have come to an end. I’d like to thank them for their patience throughout, particularly users of Anderston station. I would also like to thank all of the staff at Network Rail and ScotRail who have facilitated these improvements, delivering them on time and within budget.

"The Scottish Government has provided £32m of funding for this work and will continue to significantly invest in rail infrastructure and services in Scotland which helps us to attract passengers back to rail. It is vital that we deliver reliable infrastructure and do so in a manner that minimises the impact of disruption to passengers and freight.

-- Advertisement --
NorthernAsbestosServicesLtd

"Any project of this scale brings with it a number of challenges but at the same time also delivers significant improvements to Scotland’s Railway for passengers, including a reduction in the need for future disruption arising from any future works.

Jeremy Spence, programme manager, Network Rail, said: "I am pleased that this major programme of work to the Argyle line has been completed both on time and within budget.

"The complexity of a project that covers multiple work sites, involves a range of disciplines, not to mention the mobilisation of plant and equipment, is not without significant challenges. It’s a credit to the Network Rail project team, our contractors and supply chain partners that every element was delivered safely and on time.

"The outcome is a comprehensive programme of improvements and enhancements that futureproof Scotland’s Railway for passengers, as work on this scale will not be required for many years to come.

"Closing part of our infrastructure is something done rarely, as we fully appreciate the impact of this on our customers. Our decision was weighed against whether it was best to complete the work over an intense period of time by closing the line completely or prolong it over many months by only being able to undertake work at weekends.

"I would like to thank all the passengers whose travel plans have been affected for their patience and understanding over the past eight weeks."

David Simpson, ScotRail Service Delivery Director, said: "This was an ambitious programme of work and it’s great to see that it’s been completed on time, within budget, and with alternative transport arrangements working well for customers.

"The work has helped future proof the line and customers can look forward to a better journey experience.

"We’d ask them for a little bit more patience as we carry out further essential work at Anderston station over the next four weeks.

"We’ll be upgrading the entrance, booking office, concourse and platforms and installing a lift for better customer access.

"This is all part of our strategy to make ScotRail fit for the future with investment in infrastructure, more reliable timetables, and great offers like the half-price ticket sale which begins on 9 May."

The Argyle line project includes improvements to Anderston station, with the closure of the station extended by four weeks until June 6. This is to allow engineers to complete critical work on the entrance, booking office, concourse and platforms.

By extending the closure, the most critical work will be finished earlier and reduces the overall time taken to renovate the station by 12 weeks, completing in the autumn instead of by December 2022.

Once complete, the station will feature a lift for better customer access, a remodelled booking office and modern finishes on the stairs, floors and ceilings. This also includes improving the outside area to the station, with a new-look glazed entrance and enhanced external lighting.

Latest Construction News

20/10/2026
Scotland's leading public sector framework provider has opened bidding for a £900 million Refurbishment and Modernisation programme aimed at delivering urgent and planned works across housing and public buildings. The Scottish Procurement Alliance's Refurbishment and Modernisation framework (RM4S)
Read More
20/10/2026
A £1 million grant programme has been launched to help owners return vacant listed buildings across Glasgow to productive use. The Heritage Building Viability Grant Scheme, funded by Glasgow City Council and administered by Glasgow City Heritage Trust, is designed to bring floorspace in some of the
Read More
20/10/2026
Road resurfacing on the A702 at West Linton will take place over six nights from Monday 9 to Friday 13 November, and on Monday 16 November 2026, requiring overnight closures. Transport Scotland's operating company, BEAR Scotland, will deliver the scheme. For safety, the A702 will be closed each ni
Read More
20/10/2026
SP Energy Networks chief executive Nicola Connelly has welcomed the launch of a new industry plan setting out how the biggest grid upgrade in living memory will boost employment and economic growth across the UK. The Electricity Networks Sector Growth Plan – led by the Energy Networks Association (
Read More
20/10/2026
An £8 million scheme is under way to enhance accessibility for passengers at Dalwhinnie and improve performance on the Highland Main Line. The project will install a new crossover so trains can switch between tracks, enabling northbound services to use Platform 1 when step-free access is required.
Read More
20/10/2026
The Scottish Government intends to award Wills Bros Civil Engineering Ltd the contract to dual the A9 between Pitlochry and Killiecrankie, Economy, Tourism and Transport Secretary Stephen Flynn has announced. The move represents the final stage of procurement for the fifth A9 Dualling scheme to rea
Read More
20/10/2026
Residents in Clackmannanshire are already benefiting from a new electric nine-seater minibus provided by Robertson Construction Central East, part of the contractor's social value commitments linked to the Wellbeing Village and Lochies School development in Alloa. During construction, the vehicle i
Read More
20/10/2026
A major new study will examine how climate change could trigger cascading disruption across Scotland's critical infrastructure, giving organisations a clearer view of risks to the services people rely on daily. Commissioned by the Climate Ready Infrastructure Scotland Forum (CRIS) — a partnership o
Read More
20/10/2026
Clark Contracts has secured a place on Pagabo's Major Works Framework, enhancing its ability to support public sector bodies in delivering major construction and refurbishment schemes. The framework, expected to be worth up to £5bn over four years, follows the creation of a 10-year strategic delive
Read More
20/10/2026
North Ayrshire Council has carried out its annual winter dry run this month as it gets ready for the colder months. Roads staff took part in the exercise as part of preparations to keep roads, footways and communities safe and accessible during severe weather. It follows a meeting of Cabinet at wh
Read More
SEEIT3DDunedin Stone LtdMaterials Market UK Trading LtdForde Training Services LtdGreater Good Glass LtdCountryside KitchensDenfind Stone LimitedKattrak International LtdVisual Precision LtdBlaven Interiors