Subscribe to our Construction Newsfeed
Scotland Construction Directory
Search our 13,917 companies....

Construction News

20/04/2022

Shetland Subsea HVDC Link Project Progresses

SSEN Transmission has welcomed the progress being made on the Shetland subsea High Voltage Direct Current (HVDC) link project, with numerous project milestones reached in recent months.

The £660 million project by SSEN Transmission will involve constructing a 260km subsea cable from Shetland to Noss Head in Caithness, connecting Shetland to the main GB energy system for the first time, supporting Shetland's future security of supply as well as enabling the connection of renewable energy generation.

The first phase of boulder relocating work along the proposed subsea cable route has been completed by Principal Contractor NKT, lead Contractor for all cabling works, which involved clearing a 100m-wide corridor along the proposed consented cable route to move any obstacles from its path. Subsea equipment deployed from specialist vessel the Seawell was brought in to help safely manoeuvre boulders away from the Shetland HVDC cable route along its 260km route.

Prior to the boulder clearance work taking place, a UXO survey was carried out in a bid to identify if any unexploded ordnance (UXOs) were in the cable route of the subsea HVDC cable being installed between Shetland and the mainland at Noss Head, Caithness. While multiple marine seabed surveys have been completed as part of the project, the additional specialist UXO survey was carried out as standard practice and identified no UXOs within the cable corridor, meaning work could continue as planned. While no UXOs were identified, the survey located various items such as scrap metal and other debris along the cable route, which were recovered by the vessel. These objects have now been safely disposed of, helping to clean-up the seabed and reduce unnecessary marine debris and any associated risk they may cause.

-- Advertisement --
NorthernAsbestosServicesLtd

Back on land, the team completed horizontal directional drilling (HDD) work to the south of Noss Head lighthouse where the subsea cables will make landfall, marking a major milestone for the project. HDD is a drilling method used to install ducts beneath the ground through which cables can be pulled, providing minimum disturbance to the surrounding area.

The HDD works took around three months to complete with teams working continuously to carefully execute the drilling scope and then install the new ducts, preparing for when the cable will be pulled through from the seabed through to the transition joint bay where it will tie-in to the land cables which will be connected to the switching station. The operation required multiple activities including diving operations and marine surveys in order to support the land-based HDD effort.

Teams are now preparing to begin work on the first subsea installations this summer, which will involve specialist vessel NKT Victoria installing the first cable length.

Reflecting on the project achievements so far, SSEN Transmission Lead Project Manager Chris Finnigan said: "We've made some really excellent progress in recent months with regards to the Shetland HVDC link which allows us to move forwards on connecting Shetland to the mainland and opening up a clean-energy corridor for transporting electricity to and from the islands.

"Completing the HDD work was a crucial milestone, and the team has worked tirelessly to overcome major challenges including working through the complex geological make-up of the ground conditions at the Noss Head cliffs, as well as safely mobilising and demobilising the drilling spread and the vessels required for the supporting marine operations. It's a huge achievement and one that those involved with the works should be proud of.

"The first stage of subsea boulder clearance marks another integral step ahead of the HVDC cable being installed, and the team from NKT and their subcontractor Helix, including all those onboard the Seawell vessel, did a fantastic job in creating a safe subsea corridor for the future cable.

"As is standard practice we carried out specific surveys in order to check for UXOs along the cable route, and we're pleased that no UXO targets were identified within the cable installation route. The survey did however identify some scrap metal debris on the seabed, and although this would not have impacted our project we worked with our contractor NKT to remove these items and have them disposed of properly onshore. As a responsible developer we aim, where possible, to leave a positive impact on the environment in which we operate and small actions like this are something we aim to achieve whenever we can.

"In general the project continues to make great strides forward and teams are now gearing up ahead of our first subsea installation campaign which is scheduled to begin this summer.

"We thank the local community and stakeholders for their cooperation and understanding while we continue with this crucial project, and as ever we'll work to keep informed as we move through the pre-construction phases of the Shetland HDVC link project."

The Shetland HVDC subsea link project is on track to be completed by 2024.

Latest Construction News

04/09/2026
Morgan Sindall Construction has been appointed by the Scottish Fire and Rescue Service (SFRS) to demolish and rebuild the Liberton station in the capital. Procured via the SCAPE Scotland Construction Framework, the £10m scheme marks a significant investment in SFRS infrastructure and will create a
Read More
03/09/2026
Network Rail says it has hit a key milestone in efforts to strengthen Scotland's railway against severe weather, with £130m invested in resilience over the last two years. The move comes amid tougher operating conditions, including higher temperatures, increasingly unpredictable rainfall and more f
Read More
04/09/2026
ESB has reached Final Investment Decision (FID) and executed the principal construction agreements for the 96MW Chleansaid Wind Farm, near Lairg in the Scottish Highlands. The move signals the start of delivery for one of the utility's most strategic renewable projects and its first ESB-developed on
Read More
04/09/2026
Glasgow City Region has welcomed confirmation of £22.7 million in first-year funding from the UK Government's Local Growth Fund, aimed at accelerating business growth, improving skills and employability, and creating new commercial space across the area. The award represents the opening phase of a
Read More
04/09/2026
A major planned maintenance scheme has begun across East Renfrewshire, with 190 council homes set to receive new kitchens in the first year of works. The initiative is part of East Renfrewshire Council's longer-term investment in its housing stock. Approximately 300 kitchens are due to be replaced
Read More
04/09/2026
A £9.8m Local Growth Fund programme for the Forth Valley has moved into delivery after the UK Government approved the region's Investment Plan, paving the way for projects to boost businesses, skills, housing and infrastructure across Falkirk, Stirling and Clackmannanshire. Following approval of th
Read More
04/09/2026
Approval of a new Local Growth Fund Investment Plan will deliver £11.8 million to Ayrshire between 2026 and 2029, targeting higher household incomes and stronger local economies through infrastructure, business support and skills. The funding reflects the collective ambition of the Ayrshire Regiona
Read More
04/09/2026
SNIPEF's State of Trade Survey for the first quarter of 2026 points to steady activity tempered by growing caution. Work volumes have held up, payment performance is broadly consistent and product availability remains manageable. However, order books are more finely balanced, margins are under press
Read More
04/09/2026
Farrans has been appointed by ESB to deliver the Civil Balance of Plant (CBoP) for the 96MW Chleansaid Wind Farm near Lairg in the Scottish Highlands. The contract signals the start of delivery on one of ESB's most strategically important renewable schemes and marks its first onshore wind project i
Read More
03/09/2026
Sky has secured planning permission for its new Livingston Campus, unlocking a major investment and underscoring the company's long-term commitment to Scotland. The decision marks a key step towards delivering a significant new workplace development in West Lothian. The approved plans will bring Sk
Read More
SEEIT3DInverness Core Drilling LtdStuart King Architecture & Design LtdNew Home Quality ControlRural House LtdJames Macqueen Building Contractors LtdHodge Plant LimitedNick Ives JoineryListers Concrete PumpingADAM Roofing Services Glasgow