SSEN Transmission has welcomed the progress being made on the Shetland subsea High Voltage Direct Current (HVDC) link project, with numerous project milestones reached in recent months.
The £660 million project by SSEN Transmission will involve constructing a 260km subsea cable from Shetland to Noss Head in Caithness, connecting Shetland to the main GB energy system for the first time, supporting Shetland's future security of supply as well as enabling the connection of renewable energy generation.
The first phase of boulder relocating work along the proposed subsea cable route has been completed by Principal Contractor NKT, lead Contractor for all cabling works, which involved clearing a 100m-wide corridor along the proposed consented cable route to move any obstacles from its path. Subsea equipment deployed from specialist vessel the Seawell was brought in to help safely manoeuvre boulders away from the Shetland HVDC cable route along its 260km route.
Prior to the boulder clearance work taking place, a UXO survey was carried out in a bid to identify if any unexploded ordnance (UXOs) were in the cable route of the subsea HVDC cable being installed between Shetland and the mainland at Noss Head, Caithness. While multiple marine seabed surveys have been completed as part of the project, the additional specialist UXO survey was carried out as standard practice and identified no UXOs within the cable corridor, meaning work could continue as planned. While no UXOs were identified, the survey located various items such as scrap metal and other debris along the cable route, which were recovered by the vessel. These objects have now been safely disposed of, helping to clean-up the seabed and reduce unnecessary marine debris and any associated risk they may cause.
Back on land, the team completed horizontal directional drilling (HDD) work to the south of Noss Head lighthouse where the subsea cables will make landfall, marking a major milestone for the project. HDD is a drilling method used to install ducts beneath the ground through which cables can be pulled, providing minimum disturbance to the surrounding area.
The HDD works took around three months to complete with teams working continuously to carefully execute the drilling scope and then install the new ducts, preparing for when the cable will be pulled through from the seabed through to the transition joint bay where it will tie-in to the land cables which will be connected to the switching station. The operation required multiple activities including diving operations and marine surveys in order to support the land-based HDD effort.
Teams are now preparing to begin work on the first subsea installations this summer, which will involve specialist vessel NKT Victoria installing the first cable length.
Reflecting on the project achievements so far, SSEN Transmission Lead Project Manager Chris Finnigan said: "We've made some really excellent progress in recent months with regards to the Shetland HVDC link which allows us to move forwards on connecting Shetland to the mainland and opening up a clean-energy corridor for transporting electricity to and from the islands.
"Completing the HDD work was a crucial milestone, and the team has worked tirelessly to overcome major challenges including working through the complex geological make-up of the ground conditions at the Noss Head cliffs, as well as safely mobilising and demobilising the drilling spread and the vessels required for the supporting marine operations. It's a huge achievement and one that those involved with the works should be proud of.
"The first stage of subsea boulder clearance marks another integral step ahead of the HVDC cable being installed, and the team from NKT and their subcontractor Helix, including all those onboard the Seawell vessel, did a fantastic job in creating a safe subsea corridor for the future cable.
"As is standard practice we carried out specific surveys in order to check for UXOs along the cable route, and we're pleased that no UXO targets were identified within the cable installation route. The survey did however identify some scrap metal debris on the seabed, and although this would not have impacted our project we worked with our contractor NKT to remove these items and have them disposed of properly onshore. As a responsible developer we aim, where possible, to leave a positive impact on the environment in which we operate and small actions like this are something we aim to achieve whenever we can.
"In general the project continues to make great strides forward and teams are now gearing up ahead of our first subsea installation campaign which is scheduled to begin this summer.
"We thank the local community and stakeholders for their cooperation and understanding while we continue with this crucial project, and as ever we'll work to keep informed as we move through the pre-construction phases of the Shetland HDVC link project."
The Shetland HVDC subsea link project is on track to be completed by 2024.
Construction News
20/04/2022
Shetland Subsea HVDC Link Project Progresses


30/04/2025
Plans for a £43 million education campus on the Isle of Mull have moved forward, Argyll and Bute Council has confirmed.
Following a decision earlier this month on the preferred location, the council will now progress with developing a detailed brief and concept design to inform the overall busines

30/04/2025
Global engineering and development consultancy Mott MacDonald has been appointed by Strathclyde Partnership for Transport (SPT), in collaboration with Glasgow City Council on behalf of the Glasgow City Region, to progress two key elements of the Case for Investment for the ambitious Clyde Metro proj

30/04/2025
Members of the Caithness Committee have unanimously agreed to adopt the Caithness Area Place Plan (APP).
The committee also committed to fully supporting and promoting the plan, ensuring it is considered within other relevant plans, strategies, developments, and funding opportunities impacting the

30/04/2025
Plans for a new business park at Oban Airport have advanced significantly with the announcement that Argyll and Bute Council has appointed hub North Scotland to oversee the project and Robertson Construction as the main contractor.
The Oban Airport project is a key component of the council's Tax In

30/04/2025
Contractors engaged in public sector projects across the UK will soon be subject to random and targeted spot checks on their payment practices.
This move by the UK government is designed to tackle the persistent issue of late payments throughout the construction supply chain.
According to advice

30/04/2025
Ten new affordable flats for social rent have been completed by The Highland Council in Carrbridge, addressing a significant demand for smaller properties in the area.
The development, named Struan Court after the former Struan Hotel which previously occupied the site, offers eight one-bedroom and

30/04/2025
The City of Edinburgh Council has held collaborative summit with key partner organisations to explore avenues for expanding the availability of accessible housing across the capital.
The Accessible Housing Summit, hosted by the council, brought together representatives from the third sector, housin

30/04/2025
A significant step forward has been taken in the development of a new £16 million flood prevention scheme designed to safeguard Bridge of Allan. Stirling Council has approved the procurement of a contract to design and construct the essential flood defences.
The planned infrastructure will offer pr

30/04/2025
A significant 64% of companies within Scotland's renewable energy supply chain are actively investing in skills, capabilities, and facilities to capitalise on the nation's burgeoning clean energy market over the next three to five years, a survey by Scottish Renewables has revealed.
The findings we

30/04/2025
A collaborative effort between McTaggart Construction and West Dunbartonshire Council is set to bring new affordable housing and a range of community benefits to the Willox Park area. The partnership will deliver a 17-unit, client design led, affordable housing development, procured through Scotland