28/03/2022

Trams To Newhaven Scheme Enters Final Phase Of Construction

Construction News Image
The City of Edinburgh Council has announced that the majority of track has been laid to take the tram to Newhaven as the scheme enters the final phase of construction works.

More than 3km of track – 70% of the total to be laid – is now in the ground as part of the Trams to Newhaven project, which remains on schedule to begin revenue services in spring 2023, delivered within the £207.3m budget.

The main construction work on three of the eight new tram stops is also complete, while over 3km of drainage (66% of the total) and almost 4km of communications ducting (82% of the total) serving the tram and wider area has been installed. Construction is largely finished on several key sections of the route, other than some localised works, including Constitution Street, between Constitution Place and Queen Charlotte Street, and Ocean Terminal to Rennie's Isle.

Next week, operational tram stops on Princes Street and St Andrew Square will reopen following their temporary closure. These were closed to allow for the removal of the York Place tram stop and installation of new infrastructure there connecting the existing line to the new one.

As we enter the final year of major civil work ahead of testing and commissioning this winter, a review of the specific completion dates for remaining sections has been carried out. This has resulted in some changes affecting certain sections due to various unavoidable factors such as complex utilities diversions, archaeological finds and an industry wide shortage of materials, though this is not expected to affect the final completion date.

-- Advertisement --
NorthernAsbestosServicesLtd

Councillor Lesley Macinnes, Transport and Environment Convener, said: "It's clear that the Trams to Newhaven project is well on its way to completion, as these figures show, and before long we'll be testing trams on the streets of Leith. Next week, we'll also see the return of the existing service to the city centre, which I'm sure will be great news for many.

"Of course, while this project will bring significant benefits to the area, we know that its construction has impacted all those who live and work nearby, and I'd like to thank them for their patience during the last two years.

"As we enter the final year of work to deliver the tram line, we've had to make some changes to the programme due to issues outwith our control. I want to assure communities along the route that we're doing everything we can to mitigate the impacts of this, and that we're still on track to begin providing the service by spring next year."

Councillor Karen Doran, Transport and Environment Vice Convener, said: "This project will be transformative for the north of the city and it's really exciting to see it take shape already.

"Once complete, it will play a key role in the future growth and development of the city. Delivering the tram line to Leith will unlock a large area of the city for housing and economic development, while providing a low-carbon, clean mode of transport to densely populated communities."

The project team is working to mitigate the impact of changes to the programme, ensuring the scheduled spring completion date is met. Based on lessons from the first tram line, and best practice from other major European construction projects, Trams to Newhaven focuses on large work sites, providing the flexibility to continue construction elsewhere on-site if issues are encountered.

In the coming months, localised works will continue on completed sections to resolve defects, carry out landscaping, install equipment to support the new tram line including tram communication systems, complete tram stop fit-outs and install overhead line equipment, street lighting and traffic signalling.

Since 2019 the project has provided significant support to businesses through its £2.4m Support for Business initiative. As part of this more than £100k has been spent on an ‘Open for Business' campaign, 60k deliveries have gone through dedicated logistics hubs and 140 applications have been made to the business continuity fund. In addition, the extremely popular itison scheme has seen over 20k vouchers sold, generating £200k spend in participating businesses.

Latest Construction News

02/05/2024

Malin Group has secured planning permission in principle for its proposed development of the Scottish Marine Technology Park (SMTP). Malin Group's vision for the site is to deliver a state-of-the-art marine excellence hub which will bring together manufacturers with marine and renewables ...
02/05/2024

Fleming Building has officially broken ground on the development of the multi-million pound Bishopton Dargavel Satellite Facility. Working alongside Hub West Scotland and NHS Greater Glasgow & Clyde through a detailed pre-construction period, designs were developed to meet a range of requirements ...
02/05/2024

Aberdeenshire Council has announced the installation of a downstream defender as part of ongoing works to restore and improve the ponds at Denman Park in Westhill. The popular ponds in Denman Park are home to a wide variety of pondlife and wildlife but have been subject to pollution from a range ...
02/05/2024

Contractors RJ McLeod are on schedule to complete the construction of a new Largs seawall in North Ayrshire. The £4.6m project is almost complete with the northern section of the promenade expected to re-open to pedestrians before the summer season gets under way. The project has seen the ...
02/05/2024

Scottish Water has announced the successful completion of a major technological transformation of Glasgow's Victorian era Partick Pumping Station. Built some 120 years ago, the pumping station remains a key part of the city's waste water infrastructure and still serves 170,000 people. It is one of ...
02/05/2024

SSEN Transmission has committed to consider community and landowner proposed alignments as part of its Kintore-Tealing 400kV project. These alignments - which will be assessed in parallel with other alignment options within the refined routes SSEN Transmission recently consulted on - are around ...
02/05/2024

SSEN Distribution has announced that it has chosen Electron's 'ElectronConnect' platform to streamline and expand its procurement of Flexibility Services. The company's DSO Acceleration Action Plan identified the selection of a new Flexibility Market Platform during the Spring of 2024 as a key ...
02/05/2024

West Dunbartonshire Council has declared a housing emergency, highlighting the unprecedented pressures on the ability to meet the needs of those in social housing or seeking a Council property. Councillor Gurpreet Singh Johal, who is the Convener of Housing and Communities, made the declaration ...
02/05/2024

The Highland Council has submitted its response to the Scottish Government's consultation on Masterplan Consent Areas (MCA), developed by members of the Economy and Infrastructure Committee. The Scottish Government is proposing the introduction of discretionary powers to establish Masterplan ...
02/05/2024

As part of its ongoing efforts to improve biodiversity across the region, Perth and Kinross Council has announced an extension of its Grassland Management Trials, following successes at 42 other sites. These areas of longer grass will create space for nature and help attract bees, butterflies and ...
Morris & Spottiswood LtdRBT Underfloor LimitedMaterials Market LtdToner Damp Proofing SuppliesNo HydroBurnside Plant Hire LtdKattrak International Hidromek SalesScotdeck LtdThe Big Block Co LtdSafe Access (Highland) Ltd.
Terms and Conditions
2024/05/03 06:02:29