Construction News

28/03/2022

Trams To Newhaven Scheme Enters Final Phase Of Construction

The City of Edinburgh Council has announced that the majority of track has been laid to take the tram to Newhaven as the scheme enters the final phase of construction works.

More than 3km of track – 70% of the total to be laid – is now in the ground as part of the Trams to Newhaven project, which remains on schedule to begin revenue services in spring 2023, delivered within the £207.3m budget.

The main construction work on three of the eight new tram stops is also complete, while over 3km of drainage (66% of the total) and almost 4km of communications ducting (82% of the total) serving the tram and wider area has been installed. Construction is largely finished on several key sections of the route, other than some localised works, including Constitution Street, between Constitution Place and Queen Charlotte Street, and Ocean Terminal to Rennie's Isle.

Next week, operational tram stops on Princes Street and St Andrew Square will reopen following their temporary closure. These were closed to allow for the removal of the York Place tram stop and installation of new infrastructure there connecting the existing line to the new one.

As we enter the final year of major civil work ahead of testing and commissioning this winter, a review of the specific completion dates for remaining sections has been carried out. This has resulted in some changes affecting certain sections due to various unavoidable factors such as complex utilities diversions, archaeological finds and an industry wide shortage of materials, though this is not expected to affect the final completion date.

-- Advertisement --
NorthernAsbestosServicesLtd

Councillor Lesley Macinnes, Transport and Environment Convener, said: "It's clear that the Trams to Newhaven project is well on its way to completion, as these figures show, and before long we'll be testing trams on the streets of Leith. Next week, we'll also see the return of the existing service to the city centre, which I'm sure will be great news for many.

"Of course, while this project will bring significant benefits to the area, we know that its construction has impacted all those who live and work nearby, and I'd like to thank them for their patience during the last two years.

"As we enter the final year of work to deliver the tram line, we've had to make some changes to the programme due to issues outwith our control. I want to assure communities along the route that we're doing everything we can to mitigate the impacts of this, and that we're still on track to begin providing the service by spring next year."

Councillor Karen Doran, Transport and Environment Vice Convener, said: "This project will be transformative for the north of the city and it's really exciting to see it take shape already.

"Once complete, it will play a key role in the future growth and development of the city. Delivering the tram line to Leith will unlock a large area of the city for housing and economic development, while providing a low-carbon, clean mode of transport to densely populated communities."

The project team is working to mitigate the impact of changes to the programme, ensuring the scheduled spring completion date is met. Based on lessons from the first tram line, and best practice from other major European construction projects, Trams to Newhaven focuses on large work sites, providing the flexibility to continue construction elsewhere on-site if issues are encountered.

In the coming months, localised works will continue on completed sections to resolve defects, carry out landscaping, install equipment to support the new tram line including tram communication systems, complete tram stop fit-outs and install overhead line equipment, street lighting and traffic signalling.

Since 2019 the project has provided significant support to businesses through its £2.4m Support for Business initiative. As part of this more than £100k has been spent on an ‘Open for Business' campaign, 60k deliveries have gone through dedicated logistics hubs and 140 applications have been made to the business continuity fund. In addition, the extremely popular itison scheme has seen over 20k vouchers sold, generating £200k spend in participating businesses.

Latest Construction News

20/10/2026
Scotland's leading public sector framework provider has opened bidding for a £900 million Refurbishment and Modernisation programme aimed at delivering urgent and planned works across housing and public buildings. The Scottish Procurement Alliance's Refurbishment and Modernisation framework (RM4S)
Read More
20/10/2026
A £1 million grant programme has been launched to help owners return vacant listed buildings across Glasgow to productive use. The Heritage Building Viability Grant Scheme, funded by Glasgow City Council and administered by Glasgow City Heritage Trust, is designed to bring floorspace in some of the
Read More
20/10/2026
Road resurfacing on the A702 at West Linton will take place over six nights from Monday 9 to Friday 13 November, and on Monday 16 November 2026, requiring overnight closures. Transport Scotland's operating company, BEAR Scotland, will deliver the scheme. For safety, the A702 will be closed each ni
Read More
20/10/2026
SP Energy Networks chief executive Nicola Connelly has welcomed the launch of a new industry plan setting out how the biggest grid upgrade in living memory will boost employment and economic growth across the UK. The Electricity Networks Sector Growth Plan – led by the Energy Networks Association (
Read More
20/10/2026
An £8 million scheme is under way to enhance accessibility for passengers at Dalwhinnie and improve performance on the Highland Main Line. The project will install a new crossover so trains can switch between tracks, enabling northbound services to use Platform 1 when step-free access is required.
Read More
20/10/2026
The Scottish Government intends to award Wills Bros Civil Engineering Ltd the contract to dual the A9 between Pitlochry and Killiecrankie, Economy, Tourism and Transport Secretary Stephen Flynn has announced. The move represents the final stage of procurement for the fifth A9 Dualling scheme to rea
Read More
20/10/2026
Residents in Clackmannanshire are already benefiting from a new electric nine-seater minibus provided by Robertson Construction Central East, part of the contractor's social value commitments linked to the Wellbeing Village and Lochies School development in Alloa. During construction, the vehicle i
Read More
20/10/2026
A major new study will examine how climate change could trigger cascading disruption across Scotland's critical infrastructure, giving organisations a clearer view of risks to the services people rely on daily. Commissioned by the Climate Ready Infrastructure Scotland Forum (CRIS) — a partnership o
Read More
20/10/2026
Clark Contracts has secured a place on Pagabo's Major Works Framework, enhancing its ability to support public sector bodies in delivering major construction and refurbishment schemes. The framework, expected to be worth up to £5bn over four years, follows the creation of a 10-year strategic delive
Read More
20/10/2026
North Ayrshire Council has carried out its annual winter dry run this month as it gets ready for the colder months. Roads staff took part in the exercise as part of preparations to keep roads, footways and communities safe and accessible during severe weather. It follows a meeting of Cabinet at wh
Read More
SEEIT3DDGC Speed SprayMartin Property Care LimitedIredia ResourcesGalaxy Window BlindsAlternative Tying Systems LtdSips Eco Panel Systems LtdApollo Scaffolding Ties LtdHBB GeoSales LtdFP McCann Ltd