Construction News

28/03/2022

Trams To Newhaven Scheme Enters Final Phase Of Construction

The City of Edinburgh Council has announced that the majority of track has been laid to take the tram to Newhaven as the scheme enters the final phase of construction works.

More than 3km of track – 70% of the total to be laid – is now in the ground as part of the Trams to Newhaven project, which remains on schedule to begin revenue services in spring 2023, delivered within the £207.3m budget.

The main construction work on three of the eight new tram stops is also complete, while over 3km of drainage (66% of the total) and almost 4km of communications ducting (82% of the total) serving the tram and wider area has been installed. Construction is largely finished on several key sections of the route, other than some localised works, including Constitution Street, between Constitution Place and Queen Charlotte Street, and Ocean Terminal to Rennie's Isle.

Next week, operational tram stops on Princes Street and St Andrew Square will reopen following their temporary closure. These were closed to allow for the removal of the York Place tram stop and installation of new infrastructure there connecting the existing line to the new one.

As we enter the final year of major civil work ahead of testing and commissioning this winter, a review of the specific completion dates for remaining sections has been carried out. This has resulted in some changes affecting certain sections due to various unavoidable factors such as complex utilities diversions, archaeological finds and an industry wide shortage of materials, though this is not expected to affect the final completion date.

-- Advertisement --
NorthernAsbestosServicesLtd

Councillor Lesley Macinnes, Transport and Environment Convener, said: "It's clear that the Trams to Newhaven project is well on its way to completion, as these figures show, and before long we'll be testing trams on the streets of Leith. Next week, we'll also see the return of the existing service to the city centre, which I'm sure will be great news for many.

"Of course, while this project will bring significant benefits to the area, we know that its construction has impacted all those who live and work nearby, and I'd like to thank them for their patience during the last two years.

"As we enter the final year of work to deliver the tram line, we've had to make some changes to the programme due to issues outwith our control. I want to assure communities along the route that we're doing everything we can to mitigate the impacts of this, and that we're still on track to begin providing the service by spring next year."

Councillor Karen Doran, Transport and Environment Vice Convener, said: "This project will be transformative for the north of the city and it's really exciting to see it take shape already.

"Once complete, it will play a key role in the future growth and development of the city. Delivering the tram line to Leith will unlock a large area of the city for housing and economic development, while providing a low-carbon, clean mode of transport to densely populated communities."

The project team is working to mitigate the impact of changes to the programme, ensuring the scheduled spring completion date is met. Based on lessons from the first tram line, and best practice from other major European construction projects, Trams to Newhaven focuses on large work sites, providing the flexibility to continue construction elsewhere on-site if issues are encountered.

In the coming months, localised works will continue on completed sections to resolve defects, carry out landscaping, install equipment to support the new tram line including tram communication systems, complete tram stop fit-outs and install overhead line equipment, street lighting and traffic signalling.

Since 2019 the project has provided significant support to businesses through its £2.4m Support for Business initiative. As part of this more than £100k has been spent on an ‘Open for Business' campaign, 60k deliveries have gone through dedicated logistics hubs and 140 applications have been made to the business continuity fund. In addition, the extremely popular itison scheme has seen over 20k vouchers sold, generating £200k spend in participating businesses.

Latest Construction News

04/09/2026
Morgan Sindall Construction has been appointed by the Scottish Fire and Rescue Service (SFRS) to demolish and rebuild the Liberton station in the capital. Procured via the SCAPE Scotland Construction Framework, the £10m scheme marks a significant investment in SFRS infrastructure and will create a
Read More
03/09/2026
Network Rail says it has hit a key milestone in efforts to strengthen Scotland's railway against severe weather, with £130m invested in resilience over the last two years. The move comes amid tougher operating conditions, including higher temperatures, increasingly unpredictable rainfall and more f
Read More
04/09/2026
ESB has reached Final Investment Decision (FID) and executed the principal construction agreements for the 96MW Chleansaid Wind Farm, near Lairg in the Scottish Highlands. The move signals the start of delivery for one of the utility's most strategic renewable projects and its first ESB-developed on
Read More
04/09/2026
Glasgow City Region has welcomed confirmation of £22.7 million in first-year funding from the UK Government's Local Growth Fund, aimed at accelerating business growth, improving skills and employability, and creating new commercial space across the area. The award represents the opening phase of a
Read More
04/09/2026
A major planned maintenance scheme has begun across East Renfrewshire, with 190 council homes set to receive new kitchens in the first year of works. The initiative is part of East Renfrewshire Council's longer-term investment in its housing stock. Approximately 300 kitchens are due to be replaced
Read More
04/09/2026
A £9.8m Local Growth Fund programme for the Forth Valley has moved into delivery after the UK Government approved the region's Investment Plan, paving the way for projects to boost businesses, skills, housing and infrastructure across Falkirk, Stirling and Clackmannanshire. Following approval of th
Read More
04/09/2026
Approval of a new Local Growth Fund Investment Plan will deliver £11.8 million to Ayrshire between 2026 and 2029, targeting higher household incomes and stronger local economies through infrastructure, business support and skills. The funding reflects the collective ambition of the Ayrshire Regiona
Read More
04/09/2026
SNIPEF's State of Trade Survey for the first quarter of 2026 points to steady activity tempered by growing caution. Work volumes have held up, payment performance is broadly consistent and product availability remains manageable. However, order books are more finely balanced, margins are under press
Read More
04/09/2026
Farrans has been appointed by ESB to deliver the Civil Balance of Plant (CBoP) for the 96MW Chleansaid Wind Farm near Lairg in the Scottish Highlands. The contract signals the start of delivery on one of ESB's most strategically important renewable schemes and marks its first onshore wind project i
Read More
03/09/2026
Sky has secured planning permission for its new Livingston Campus, unlocking a major investment and underscoring the company's long-term commitment to Scotland. The decision marks a key step towards delivering a significant new workplace development in West Lothian. The approved plans will bring Sk
Read More
SEEIT3DWasteMan LTDRRS GroundworksGlazing and Repairs Window and Door SpecialistsBaseline Contracts LTDTHE HOME ARCHITECTWT ConsultancyDonnelly Safety ServicesCTW Safety LTDBusiness Solutions (SW) LTD