Dundee Council To Consider Complex Chain Of Olympia Centre Works

Construction News Image
Olympia Centre swimming pools could be closed until late next year amidst a combination of survey works, planned refurbishment and repairs, Dundee City Council have said.

A report to the council's city development committee details a complex chain of events that could lead to up to £4.5 million being spent on the centre.

Mark Flynn convener of the city development committee said: "The Olympia has been open for more than eight years and while that may not seem long, this is a facility that has long operational hours and high usage in a challenging environment due to the heat, moisture and chemicals to maintain water quality in the pools.

"It will always need periodic replacement of various parts and regular planned maintenance including all Health and Safety inspections and testing.

"Taken together these circumstances have created a situation where more surveys need to be carried out, as well as refurbishment work that was planned anyway and repairs to parts of the building that were found to be needed as part of the previous inspection process."
-- Advertisement --
NorthernAsbestosServicesLtd



According to the report, which will be considered by the city development committee on Monday December 6, an issue was identified in September with the fixings for light fittings and as a precautionary measure the decision was taken to close all pool facilities. Work to rectify that issue started in October.

While the facility was closed the opportunity was taken to carry out further inspection work in other areas of Olympia which identified issues in two curtain wall bolt fixings. As a result, other similar fixings will be inspected and replaced as necessary to ensure the required standard of performance.

Additional survey works by council officers, specialist services and pool consultants have been instigated to assess the overall facility. When these are completed and reviewed, any further works required will be incorporated into the planned refurbishment programme.

The renovation works already being developed and scheduled for 2022 will tackle surface and superficial corrosion, general refurbishment and upgrading and rectification of water egress within ancillary plant areas.

If the committee agrees to the ongoing closure of the Olympia pools while all of the works are carried out, the programme will also bring forward some other planned cyclical maintenance and replacement works. This will result in a projected start on site in the first quarter of 2022.

Although the building works are not structural, the need to remove, refurbish and reinstall key public facing equipment including the flume structure will require a significant closure. Dundee City Council and the building's operators Leisure and Culture Dundee will be working with the contractor to minimise the closure period. While the details are still being worked on, it is anticipated that the work could take 45 weeks.

The final contract programme and cost will be discussed as part of the tender acceptance process, with Leisure and Culture Dundee consulted throughout.

If the process is agreed a tender report and further updates will be brought to the city development in due course.

Latest Construction News

17/06/2025
Sypro has announced a major milestone in its long-standing partnership with SSEN Transmission, having now managed over £5 billion in contracts supporting the UK’s critical energy infrastructure across more than 250 projects in the north of Scotland. For more than a decade, Sypro's digital contract
17/06/2025
Stirling Council has approved the sale of the former Beech Gardens Care Home in Torbrex. At a recent council meeting, Urban Nest Scotland Ltd was confirmed as the preferred bidder. The company plans to redevelop the vacant site for private residential use, with proposals that aim to complement the
17/06/2025
Two sod-cutting ceremonies have marked the official start of new housing developments in the west of Dumfries and Galloway, as Wheatley Homes and McTaggart Construction begin delivering vital social housing in Stranraer and Leswalt. The ceremonies celebrated the beginning of construction on two sit
17/06/2025
Fife Council is inviting residents to take part in a public consultation on short-term lets, seeking views on the potential introduction of Short-Term Let Control Areas across the region. The consultation, now open, aims to gather public opinion on whether areas should be designated where planning
17/06/2025
Highland charity DAY1 is exploring opportunities for an ambitious new centre of learning, capitalising on the opportunities in construction and green energy revolution, expanding its services to support more disengaged youths across the Highlands Since 2005, the Inverness-based charity has been pro
17/06/2025
AS Homes (Scotland) has secured planning permission from East Renfrewshire Council for a new social housing development in partnership with Barrhead Housing. The project will see 12 new flats built for social rent on Cross Arthurlie Street, a brownfield site near Barrhead Park and the town's train
17/06/2025
Whiteinch & Scotstoun Housing Association (WSHA) has officially launched its new business plan for 2025–2030, outlining a bold and community-focused vision to strengthen its role as both a leading housing provider and a key anchor organisation within the local area. The five-year strategy sets out
17/06/2025
Balfour Beatty has announced the appointment of Nick Rowan as Managing Director of its UK Construction Services Regional Scotland business, effective from 4 August 2025. Rowan, who began his career with Balfour Beatty 30 years ago as a Graduate Surveyor, steps into the top regional role following a
16/06/2025
Work has commenced on a major project to transform the Watersports Centre at Strathclyde Country Park into a multi-purpose community facility, with an ambitious target to reduce the building's carbon footprint by at least 80%. The initial stage, focusing on improving the building's entrance and ac
16/06/2025
Work is expected to commence this summer on the site for the new Mayfield Community Learning Campus, following Midlothian Council's appointment of Kier as the main contractor. The £41.8 million project is expected to complete its construction phase by spring 2027, with the overall campus fully ope
Morris & Spottiswood LtdAlternative Tying Systems LtdACCON UK LtdPower DoorsBurnside Plant Hire LtdWindow StoreMorris & Spottiswood LtdCharlie Cowie LTDJRF Chimney Specialists and Heating DistributorsKattrak International Ltd