08/09/2021

First Concrete Poured At Viking Energy Wind Farm

SSE Renewables have announced the pouring of concrete on the first wind turbine base at the Viking Energy Wind Farm.

Eight ready-mix lorries carried the concrete to the turbine site from two batching plants set up nearby, each of which can mix 50 cubic metres an hour.

Once complete, Viking will be able to meet the needs of 475,000 homes and save half a million tonnes of carbon dioxide every year. It will provide around 440 megawatts of power.

Derek Hastings, Head Of Onshore Wind Farm Development, said: "It is really fantastic to get to this point in the project. This moment is one that the project team and all of our contractors can be proud of.

-- Advertisement --
NorthernAsbestosServicesLtd

"While there is still a way to go until the completion of the Viking Wind Farm, we have come so far in a relatively short time – one which included the challenges of the pandemic and unusually prolonged winter weather in Shetland.

"We're another step closer to realising SSE Renewables' own wind energy targets and the net zero ambitions of both Scotland and the UK."

Aaron Priest, Stakeholder Manager For The Viking Project, added: "This is literally a concrete landmark for the Viking project. The logistics ran like clockwork and the teams from RJ McLeod and its sub-contractors have done a tremendous job. Now they just have to repeat their skill and precision another 102 times!"

Shetland contractors and suppliers are playing a key part in wind farm construction. The concreting operation involved two ready-mix lorries from Garriock Bros and high-grade aggregates from the company's quarry at Vatster.

Once the concrete has cured, the base is backfilled with materials excavated from the site, leaving only the centre ring showing, ready for the turbine tower to be bolted on. The Vestas turbines will arrive on site for erection in early 2023.

Viking Energy Wind Farm is on course to go into renewable energy production in late 2024. It is expected to be the most productive onshore wind farm in the UK.

Latest Construction News

04/09/2026
Morgan Sindall Construction has been appointed by the Scottish Fire and Rescue Service (SFRS) to demolish and rebuild the Liberton station in the capital. Procured via the SCAPE Scotland Construction Framework, the £10m scheme marks a significant investment in SFRS infrastructure and will create a
Read More
03/09/2026
Network Rail says it has hit a key milestone in efforts to strengthen Scotland's railway against severe weather, with £130m invested in resilience over the last two years. The move comes amid tougher operating conditions, including higher temperatures, increasingly unpredictable rainfall and more f
Read More
04/09/2026
ESB has reached Final Investment Decision (FID) and executed the principal construction agreements for the 96MW Chleansaid Wind Farm, near Lairg in the Scottish Highlands. The move signals the start of delivery for one of the utility's most strategic renewable projects and its first ESB-developed on
Read More
04/09/2026
Glasgow City Region has welcomed confirmation of £22.7 million in first-year funding from the UK Government's Local Growth Fund, aimed at accelerating business growth, improving skills and employability, and creating new commercial space across the area. The award represents the opening phase of a
Read More
04/09/2026
A major planned maintenance scheme has begun across East Renfrewshire, with 190 council homes set to receive new kitchens in the first year of works. The initiative is part of East Renfrewshire Council's longer-term investment in its housing stock. Approximately 300 kitchens are due to be replaced
Read More
04/09/2026
A £9.8m Local Growth Fund programme for the Forth Valley has moved into delivery after the UK Government approved the region's Investment Plan, paving the way for projects to boost businesses, skills, housing and infrastructure across Falkirk, Stirling and Clackmannanshire. Following approval of th
Read More
04/09/2026
Approval of a new Local Growth Fund Investment Plan will deliver £11.8 million to Ayrshire between 2026 and 2029, targeting higher household incomes and stronger local economies through infrastructure, business support and skills. The funding reflects the collective ambition of the Ayrshire Regiona
Read More
04/09/2026
SNIPEF's State of Trade Survey for the first quarter of 2026 points to steady activity tempered by growing caution. Work volumes have held up, payment performance is broadly consistent and product availability remains manageable. However, order books are more finely balanced, margins are under press
Read More
04/09/2026
Farrans has been appointed by ESB to deliver the Civil Balance of Plant (CBoP) for the 96MW Chleansaid Wind Farm near Lairg in the Scottish Highlands. The contract signals the start of delivery on one of ESB's most strategically important renewable schemes and marks its first onshore wind project i
Read More
03/09/2026
Sky has secured planning permission for its new Livingston Campus, unlocking a major investment and underscoring the company's long-term commitment to Scotland. The decision marks a key step towards delivering a significant new workplace development in West Lothian. The approved plans will bring Sk
Read More
SEEIT3DInsulation Installers ScotlandElectrac NISOLV GROUPDryburgh Associates LimitedFyfe BrickworkMaterials Market UK Trading LtdInverness Core Drilling LtdStuart King Architecture & Design LtdNew Home Quality Control