SSEN Propose Skye Electricity Transmission Line Replacement

An Initial Needs Case (INC) has been submitted on a proposal to replace the existing Fort Augustus to Skye electricity transmission line by SSEN Transmission to Ofgem.

The INC, which is part of Ofgem's new Large Onshore Transmission Investment (LOTI) Uncertainty Mechanism for the RIIO-T2 price control period, is the first stage of the regulatory funding approvals process.

At an estimated cost of around £400m, the Skye reinforcement project would be one of the most significant energy investments in the West Highlands since power was first brought to the area in the 1950's.

The existing Fort-Augustus to Skye line, which was constructed in three distinct sections between 1956 and 1989, consists of a combination of steel lattice towers from Fort Augustus to Broadford, then overhead wooden poles from Broadford to Edinbane. The line is fast reaching the end of its operational life and is in urgent need of intervention. Its planned replacement is therefore essential to maintain network reliability and security of supply to homes and businesses along its route, as well as to the Western Isles which is primarily supplied by two electricity distribution subsea cables from Ardmore point.

To enable the connection of new renewable electricity looking to connect to the transmission network along its route, SSEN Transmission is also proposing to increase the capacity of the replacement line, supporting the UK and Scottish Governments transition to net zero emissions. The existing line has already exceeded its capacity limit, preventing the connection of new renewable electricity in the area.

-- Advertisement --
NorthernAsbestosServicesLtd

Rob McDonald, Managing Director of SSEN Transmission, said: "Submission of our Initial Needs Case marks a major milestone in unlocking the significant investment required for the Skye reinforcement project. The project is essential to maintain and improve network reliability and security of supply, whilst also supporting local and national efforts to tackle the climate emergency and deliver a pathway to net zero emissions.

"We now look forward to working constructively with Ofgem and our stakeholders to make the investment required in a timely manner, delivering on Ofgem's commitment to an agile and flexible regulatory framework and in doing so, create hundreds of skilled jobs throughout the supply chain to support a green recovery from the coronavirus pandemic."

Given the scale of the project, stakeholders have made it clear the replacement line should anticipate future electricity generation looking to connect in the years ahead, avoiding an iterative approach to network development and associated local impacts and disruption this would cause. This 'do it once do it right' approach, which the Electricity System Operator's own independent Cost Benefit Analysis (CBA) supports, will greatly reduce the need for additional major works in the future, responding positively to stakeholders asks.

To meet the required increased capacity of the replacement line, steel structures will be required from Fort Augustus to Edinbane; with wooden pole remaining from Edinbane to Ardmore.  Upgrades to the existing substations at Broadford and Edinbane will also be required as part of the Skye reinforcement.

SSEN Transmission continues to progress the detailed design for the replacement line and expects to consult on its preferred route and technology later in the autumn. As part of this and in response to stakeholder feedback, SSEN Transmission is actively exploring potential mitigations. This includes assessing the potential for undergrounding as the line passes the Cuillin Hills and where it connects to Fort Augustus substation; and alternative routes as it passes Kylerhea.

Separately, work to progress a 600MW HVDC connection to the Western Isles continues with SSEN Transmission committed to continuing to work constructively with Ofgem, Government, Western Isles generators and wider stakeholders to overcome barriers to unlock the islands vast renewables potential.

Latest Construction News

19/10/2026
The National Trust for Scotland has set out proposals for a new visitor centre at The Hill House in Helensburgh, progressing its strategy to secure the long-term future of Charles Rennie Mackintosh's internationally significant home as conservation work moves towards removing the award-winning prote
Read More
19/10/2026
A volunteer team from SSEN Transmission's Spittal to Peterhead subsea cable link has helped clear and reinstate an overgrown pathway at Staxigoe Playpark in Wick. Staff from SSEN Transmission were joined by key contractors NKT and Caithness-based John Gunn and Son Ltd, spending the day cutting back
Read More
19/10/2026
Amey and HMP Grampian have marked the achievements of the latest group of residents to complete industry-recognised construction training, helping them gain qualifications, develop practical skills and prepare for employment. An awards event at the prison celebrated those who finished a tailored pr
Read More
19/10/2026
Progress on the access route to the new University Hospital Monklands at Wester Moffat, Airdrie, has accelerated after North Lanarkshire Council granted planning permission and the Scottish Government confirmed its support. The council this week approved a 2.3km section in Airdrie, known as the Tow
Read More
19/10/2026
Essential drainage improvements on the A91 at Blairlogie will begin on Tuesday 20 October and are scheduled to run for five weeks. A full road closure will be in place from Manor Loan to the Blairlogie Orchard Dumyat Car Park for the duration, with access maintained for emergency services. The twin
Read More
19/10/2026
Newburgh-based KR Group has been shortlisted for two industry accolades for its role in the transformation of Macduff Marine Aquarium. The steel fabrication, cladding and sheet metal specialist is a finalist at the Façade Awards UK 2026 in the Best Use of a Rainscreen System Using Aluminium categor
Read More
19/10/2026
A heritage-led regeneration initiative in Buckhaven has secured £1.2 million from The National Lottery Heritage Fund, launching a five-year programme to restore significant buildings and open up new opportunities in training, skills and community activity for local residents. The Buckhaven Heritage
Read More
19/10/2026
Applications open on today, 19 October, for Irvine-based groups to bid for grants of up to £5,000. Grassroots community groups, voluntary organisations and charities are being encouraged to submit proposals that help shape the future of their neighbourhoods. Funded through the UK Government’s Prid
Read More
19/10/2026
Overnight crack-sealing works will take place on sections of the A702 between Biggar and Melbourne Crossroads over three nights from today, 19th to Wednesday 21st October 2026. Transport Scotland's operating company BEAR Scotland will carry out the programme between 19:30 and 06:00 each night. Duri
Read More
19/10/2026
BEAR Scotland, working on behalf of Transport Scotland, will carry out daytime drainage upgrades on the A84 at Straid House, south of Callander, from Monday 19 October. The scheme will run between 8am and 4pm each day and is scheduled to finish by Friday 6 November. For the safety of road users an
Read More
SEEIT3DPro Vent ComplianceKelly TanksDiscount Kitchens and Bathrooms LtdDunedin Stone LtdMaterials Market UK Trading LtdForde Training Services LtdGreater Good Glass LtdCountryside KitchensDenfind Stone Limited