Transport Scotland Announces A725 Road Closures

Construction News Image
Transport Scotland have announced a road closure for the A725 northbound or southbound at various locations between Bothwell Bridge Junction and Shawhead Junction (North Road) for up to five nights.

The A725 carriageways will only be closed in one direction at any given time.

These closures are required for the safety of road users and the workforce during road surfacing works and white lining works.

This series of overnight closures is scheduled to take place from Tuesday 1 October to Saturday 5 October 2019, from 8 PM to 6 AM, at the following locations: 

Tuesday 1 October

A725 northbound between Bothwell Bridge and Bellziehill Junction, including Raith underpass.

As a result, the following slip roads will be closed:

• A725 northbound Raith Junction on-slip road from Raith roundabout

-- Advertisement --
NorthernAsbestosServicesLtd

• A725 northbound Orbiston Junction off-slip road

• A725 northbound Orbiston Junction on-slip road

• A725 northbound Bellziehill Junction off-slip road

Wednesday 2 October

A725 northbound carriageway between Bellziehill Junction on-slip and Diamond Junction off-slip.

As a result, the following slip roads will be closed:

• A725 northbound Bellziehill Junction on-slip road

• A725 northbound Diamond Junction off-slip road (James Street)

Thursday 3 October

A725 southbound between Shawhead Junction (North Road) and Bellziehill Junction off-slip.

As a result, the following slip roads will be closed:

• A725 southbound Diamond Junction off-slip road (James Street)

• A725 southbound Bellziehill Junction off-slip

Friday 4 October

A725 southbound between Bellziehill Junction on-slip and Raith Junction off-slip to Raith roundabout.

As a result, the following slip roads will be closed:

• A725 southbound Bellziehill Junction on-slip road

• A725 southbound Orbiston Junction off-slip road

• A725 southbound Orbiston Junction on-slip road

The works are subject to favourable weather conditions and will be undertaken in the above sequence on the planned date or the day after only.

Where necessary due to adverse weather or unforeseen circumstances a stage of works will be cancelled if not undertaken within these two days.

Signed diversion routes will be in place during these overnight closures, therefore please allow extra time for your journey.

(MH/JG)

Latest Construction News

03/05/2024

The Wheatley Group has been given planning permission from Glasgow City Council to convert the 1930s B-listed Bellgrove Hotel into 14 modern, energy-efficient and affordable flats – eight of which will be wheelchair accessible. Permission has also been granted for a further 56 flats to be built on ...
03/05/2024

Renewable energy leader Drax has announced that it will invest £80 million in a major refurbishment of its iconic 'Hollow Mountain' Cruachan pumped storage hydro power station in Scotland. Global hydropower technology supplier ANDRITZ has been appointed as the main contractor for the Cruachan ...
03/05/2024

Clark Contracts has welcomed the news that the former Dalmarnock Purifier Studios, now branded as EastWorks, has been awarded the Refurbished/Recycled workplace award at the prestigious British Council for Offices (BCO) Awards 2024. The 120-year-old former purifier shed, owned by Clyde Gateway, ...
03/05/2024

Stirling Council has launched a public consultation to shape future developments at the Viewforth and Burghmuir Road areas. The new draft framework and planning brief for Viewforth and Burghmuir covers a key area of the city centre that includes the Viewforth site, existing council buildings, ...
03/05/2024

Morrison Community Care (CCG) Holdco has secured planning permission or its latest project in South Queensferry, marking its third consecutive success. Forming part of a wider 44-hectare masterplan that will include 980 new homes, a primary school and commercial premises on Builyon Road, south of ...
03/05/2024

The Highland Council's Economy and Infrastructure Committee have carried out a review of the last two years of the Community Regeneration Funding Programme, ahead of agreeing changes to how the 2024/25 programme will be delivered. Committee Chair, Cllr Ken Gowans said: "Following a successful two ...
03/05/2024

Perth and Kinross Council and partners are set to progress community-led projects aimed at revitalising homes and improving rural transport links, following a winning bid for Innovate UK Pathfinder Places funding. Funding of £150,000 has been secured following a successful Phase 1 Pathfinder ...
03/05/2024

SGN engineers working on the H100 Fife project have helped support the Methilhill Community Children's Initiative (MCCI) by building an eco-toilet in the charity's learning garden. MCCI provides a safe and engaging space for local children to participate in various outdoor activities, including ...
03/05/2024

SNIPEF, the Scottish and Northern Ireland Plumbing Employers' Federation, has published a draft of its 2024 election manifesto detailing six strategic policy proposals designed to support its members and the broader plumbing and heating profession. Once finalised, the manifesto will be central to ...
03/05/2024

The Scottish Environment Protection Agency (SEPA) have published their 2024-25 Annual Operating Plan, detailing how they will protect and improve Scotland's environment over the next 12 months. The publication follows the launch of a new Corporate Plan at the end of March, which set out the ...
Morris & Spottiswood LtdRBT Underfloor LimitedMaterials Market LtdToner Damp Proofing SuppliesNo HydroBurnside Plant Hire LtdKattrak International Hidromek SalesScotdeck LtdThe Big Block Co LtdSafe Access (Highland) Ltd.
Terms and Conditions
2024/05/05 12:56:47