Site clearance has begun on the Luncarty to Pass of Birnam section of the A9 road.
The work is part of the major upgrade project from a single to dual carraigeway.
Transport Scotland has informed road users that traffic restrictions will come into force today, 30 July, for approximately eight weeks.
Traffic management including occasional lane closures, reduced speed restrictions and the installation of traffic signals will take place.
A spokesperson for Transport Scotland said: "These advance works allow seasonal activities to be undertaken before the main construction contract is awarded which can help reduce the risk of delays to the construction programme, assisting the main contractor when appointed.
"We will work closely with the contractor to minimise any disruption to traffic and would like to thank road users in advance for their patience."
(CM/MH)