Opening Date Confirmed For Fourth Phase Of Bishopbriggs Relief Road

Morrison Construction is continuing work on the multi-million pound Bishopbriggs Relief Road project in East Dunbartonshire.

With the project having faced a number of challenges due to the construction of a new bridge over the Edinburgh-Glasgow rail line, the council has confirmed the £6.5m fourth phase of the scheme will open to traffic by 12 June.

Overall, the project includes;

• A new bridge over the main Edinburgh-Glasgow railway line

• new two-lane road between Wester Cleddens Roundabout and a new roundabout, with another 100 metres of road on the north side of the railway

-- Advertisement --
NorthernAsbestosServicesLtd

• Wester Way – a dedicated walking/cycling route on the old Westerhill Road

• A new access road into Cadder Yard

• Sustainable Urban Drainage ponds

Cllr Billy Hendry said: "I am pleased that the opening of Bishopbriggs Relief Road Phase 4 is firmly in sight and look forward to seeing traffic flow improve as a result.

"On behalf of the Council and everyone involved with the project I want to say a huge thank-you to residents and businesses in Bishopbriggs who have showed incredible patience during this challenging build.

"Large infrastructure projects are complex by their very nature and the close proximity of the busy railway line – coupled with the ongoing Edinburgh Glasgow Improvement Programme – has led to unavoidable delays.

"I'm pleased that the new road and active travel corridor will help to reduce congestion, support businesses, improve air quality and encourage people of all ages to take steps towards healthier lifestyles."

(LM)

Latest Construction News

19/10/2026
The National Trust for Scotland has set out proposals for a new visitor centre at The Hill House in Helensburgh, progressing its strategy to secure the long-term future of Charles Rennie Mackintosh's internationally significant home as conservation work moves towards removing the award-winning prote
Read More
19/10/2026
A volunteer team from SSEN Transmission's Spittal to Peterhead subsea cable link has helped clear and reinstate an overgrown pathway at Staxigoe Playpark in Wick. Staff from SSEN Transmission were joined by key contractors NKT and Caithness-based John Gunn and Son Ltd, spending the day cutting back
Read More
19/10/2026
Amey and HMP Grampian have marked the achievements of the latest group of residents to complete industry-recognised construction training, helping them gain qualifications, develop practical skills and prepare for employment. An awards event at the prison celebrated those who finished a tailored pr
Read More
19/10/2026
Progress on the access route to the new University Hospital Monklands at Wester Moffat, Airdrie, has accelerated after North Lanarkshire Council granted planning permission and the Scottish Government confirmed its support. The council this week approved a 2.3km section in Airdrie, known as the Tow
Read More
19/10/2026
Essential drainage improvements on the A91 at Blairlogie will begin on Tuesday 20 October and are scheduled to run for five weeks. A full road closure will be in place from Manor Loan to the Blairlogie Orchard Dumyat Car Park for the duration, with access maintained for emergency services. The twin
Read More
19/10/2026
Newburgh-based KR Group has been shortlisted for two industry accolades for its role in the transformation of Macduff Marine Aquarium. The steel fabrication, cladding and sheet metal specialist is a finalist at the Façade Awards UK 2026 in the Best Use of a Rainscreen System Using Aluminium categor
Read More
19/10/2026
A heritage-led regeneration initiative in Buckhaven has secured £1.2 million from The National Lottery Heritage Fund, launching a five-year programme to restore significant buildings and open up new opportunities in training, skills and community activity for local residents. The Buckhaven Heritage
Read More
19/10/2026
Applications open on today, 19 October, for Irvine-based groups to bid for grants of up to £5,000. Grassroots community groups, voluntary organisations and charities are being encouraged to submit proposals that help shape the future of their neighbourhoods. Funded through the UK Government’s Prid
Read More
19/10/2026
Overnight crack-sealing works will take place on sections of the A702 between Biggar and Melbourne Crossroads over three nights from today, 19th to Wednesday 21st October 2026. Transport Scotland's operating company BEAR Scotland will carry out the programme between 19:30 and 06:00 each night. Duri
Read More
19/10/2026
BEAR Scotland, working on behalf of Transport Scotland, will carry out daytime drainage upgrades on the A84 at Straid House, south of Callander, from Monday 19 October. The scheme will run between 8am and 4pm each day and is scheduled to finish by Friday 6 November. For the safety of road users an
Read More