Opening Of £745m AWPR Project Delayed By Six Months

The opening of the £745 million Aberdeen Western Peripheral Route (AWPR) project has been delayed by six month, Economy Secretary Keith Brown has revealed.

The 28-mile project, which had previously been expected to open this spring, is now scheduled to be unveiled in the summer.

Contractor Connect Roads reported a number of issues have resulted in the delay, including the impact of Storm Frank during winter 2015/16, recent extreme weather during early March and the collapse of industry services firm Carillion in January.

-- Advertisement --
NorthernAsbestosServicesLtd

Mr Brown said: "While this revision to the opening date is very disappointing to the people of the North East, we have to accept the expert advice of our contractors on the ground who are delivering this significant project.

"Clearly there has been a huge amount of work that has gone in to getting the project to where we are now. I would like to pay tribute to the effort of the people who are working hard to get this project over the finishing line.

"I understand how highly anticipated this project is for those living and working in the region and the patience local communities have shown during the construction process, I would like to thank them for their continued patience as we enter the final stages of the project. Transport Scotland will continue to work closely with ARL to open sections of the road at the earliest opportunity."

(LM/MH)

Latest Construction News

19/10/2026
The National Trust for Scotland has set out proposals for a new visitor centre at The Hill House in Helensburgh, progressing its strategy to secure the long-term future of Charles Rennie Mackintosh's internationally significant home as conservation work moves towards removing the award-winning prote
Read More
19/10/2026
A volunteer team from SSEN Transmission's Spittal to Peterhead subsea cable link has helped clear and reinstate an overgrown pathway at Staxigoe Playpark in Wick. Staff from SSEN Transmission were joined by key contractors NKT and Caithness-based John Gunn and Son Ltd, spending the day cutting back
Read More
19/10/2026
Amey and HMP Grampian have marked the achievements of the latest group of residents to complete industry-recognised construction training, helping them gain qualifications, develop practical skills and prepare for employment. An awards event at the prison celebrated those who finished a tailored pr
Read More
19/10/2026
Progress on the access route to the new University Hospital Monklands at Wester Moffat, Airdrie, has accelerated after North Lanarkshire Council granted planning permission and the Scottish Government confirmed its support. The council this week approved a 2.3km section in Airdrie, known as the Tow
Read More
19/10/2026
Essential drainage improvements on the A91 at Blairlogie will begin on Tuesday 20 October and are scheduled to run for five weeks. A full road closure will be in place from Manor Loan to the Blairlogie Orchard Dumyat Car Park for the duration, with access maintained for emergency services. The twin
Read More
19/10/2026
Newburgh-based KR Group has been shortlisted for two industry accolades for its role in the transformation of Macduff Marine Aquarium. The steel fabrication, cladding and sheet metal specialist is a finalist at the Façade Awards UK 2026 in the Best Use of a Rainscreen System Using Aluminium categor
Read More
19/10/2026
A heritage-led regeneration initiative in Buckhaven has secured £1.2 million from The National Lottery Heritage Fund, launching a five-year programme to restore significant buildings and open up new opportunities in training, skills and community activity for local residents. The Buckhaven Heritage
Read More
19/10/2026
Applications open on today, 19 October, for Irvine-based groups to bid for grants of up to £5,000. Grassroots community groups, voluntary organisations and charities are being encouraged to submit proposals that help shape the future of their neighbourhoods. Funded through the UK Government’s Prid
Read More
19/10/2026
Overnight crack-sealing works will take place on sections of the A702 between Biggar and Melbourne Crossroads over three nights from today, 19th to Wednesday 21st October 2026. Transport Scotland's operating company BEAR Scotland will carry out the programme between 19:30 and 06:00 each night. Duri
Read More
19/10/2026
BEAR Scotland, working on behalf of Transport Scotland, will carry out daytime drainage upgrades on the A84 at Straid House, south of Callander, from Monday 19 October. The scheme will run between 8am and 4pm each day and is scheduled to finish by Friday 6 November. For the safety of road users an
Read More
SEEIT3DJames Macqueen Building Contractors LtdHodge Plant LimitedNick Ives JoineryListers Concrete PumpingADAM Roofing Services GlasgowCarla MacKay InteriorsKFP Services LTDWindow StoreAberroof Aberdeen