28/09/2017

Midlothian Council To Embark On School Building/Extension Programme

Construction News Image
Midlothian Council is to carry out a school building and extension programme across the region.

A total of 17 recommendations, including plans to progress a new, two stream primary in Easthouses and a replacement for Lasswade Primary, were approved at a council meeting on Tuesday, 26 September.

Work to be carried out up until 2023 includes;

• Build a three stream replacement Danderhall Primary School, as agreed by  Council in February 2017, required for August 2020.

• Build a new two stream primary school in Dalkeith with the capacity to extend to three stream, required for August 2019.

• Build a new two stream primary in Easthouses to be located on the old Newbattle High School site, required for August 2019.

• Bring the capacity of Newtongrange Primary School up to two stream, required for August 2021.

-- Advertisement --
NorthernAsbestosServicesLtd

• Expand Burnbrae Primary School to three stream by building additional capacity at the school campus on Rosewell Road, as approved by Council on 29 August 2017, planned for August 2019.

• Enhance core facilities, such as toilets and changing facilities, at Lasswade High School to provide capacity for 1,600 pupils, required immediately.

• Build a new primary school in Bonnyrigg on Hopefield Farm 2 housing development site (Hs12), required for 2022.

• Build a three stream replacement Lasswade Primary School on a new site, required for 2023.

• Extend Rosewell Primary School from single stream to a two stream primary school, required for 2022.

• Extend and refurbish Sacred Heart Primary School, including early years’ expansion.

• Extend Cuiken Primary School to two stream.

• Present a report to Council when a potential site has been identified for a secondary school along the A701.

• Extend and adapt Penicuik High School.

• Extend Bilston Primary School to two stream, required by 2023.

• Build a new primary school at Auchendinny to replace Glencorse Primary School, required by 2023.

• Extend Strathesk Primary School, one class extension, required for 2022.

• Progress the review of denominational school provision across Midlothian and bring a report back to Council early in 2018.

The local authority agreed on the short term strategy and asked officers to do further work on the financial implications of the short term strategy, so these can be considered as part of the Council’s Capital Strategy and General Service Capital Plan report which is expected to be presented to the council in November 2017.

(LM/MH)

Latest Construction News

02/05/2024

Malin Group has secured planning permission in principle for its proposed development of the Scottish Marine Technology Park (SMTP). Malin Group's vision for the site is to deliver a state-of-the-art marine excellence hub which will bring together manufacturers with marine and renewables ...
02/05/2024

Fleming Building has officially broken ground on the development of the multi-million pound Bishopton Dargavel Satellite Facility. Working alongside Hub West Scotland and NHS Greater Glasgow & Clyde through a detailed pre-construction period, designs were developed to meet a range of requirements ...
02/05/2024

Aberdeenshire Council has announced the installation of a downstream defender as part of ongoing works to restore and improve the ponds at Denman Park in Westhill. The popular ponds in Denman Park are home to a wide variety of pondlife and wildlife but have been subject to pollution from a range ...
02/05/2024

Contractors RJ McLeod are on schedule to complete the construction of a new Largs seawall in North Ayrshire. The £4.6m project is almost complete with the northern section of the promenade expected to re-open to pedestrians before the summer season gets under way. The project has seen the ...
02/05/2024

Scottish Water has announced the successful completion of a major technological transformation of Glasgow's Victorian era Partick Pumping Station. Built some 120 years ago, the pumping station remains a key part of the city's waste water infrastructure and still serves 170,000 people. It is one of ...
02/05/2024

SSEN Transmission has committed to consider community and landowner proposed alignments as part of its Kintore-Tealing 400kV project. These alignments - which will be assessed in parallel with other alignment options within the refined routes SSEN Transmission recently consulted on - are around ...
02/05/2024

SSEN Distribution has announced that it has chosen Electron's 'ElectronConnect' platform to streamline and expand its procurement of Flexibility Services. The company's DSO Acceleration Action Plan identified the selection of a new Flexibility Market Platform during the Spring of 2024 as a key ...
02/05/2024

West Dunbartonshire Council has declared a housing emergency, highlighting the unprecedented pressures on the ability to meet the needs of those in social housing or seeking a Council property. Councillor Gurpreet Singh Johal, who is the Convener of Housing and Communities, made the declaration ...
02/05/2024

The Highland Council has submitted its response to the Scottish Government's consultation on Masterplan Consent Areas (MCA), developed by members of the Economy and Infrastructure Committee. The Scottish Government is proposing the introduction of discretionary powers to establish Masterplan ...
02/05/2024

As part of its ongoing efforts to improve biodiversity across the region, Perth and Kinross Council has announced an extension of its Grassland Management Trials, following successes at 42 other sites. These areas of longer grass will create space for nature and help attract bees, butterflies and ...
RBT Underfloor LimitedMorris & Spottiswood LtdMaterials Market LtdToner Damp Proofing SuppliesNo HydroBurnside Plant Hire LtdKattrak International Hidromek SalesScotdeck LtdThe Big Block Co LtdSafe Access (Highland) Ltd.
Terms and Conditions
2024/05/03 08:16:00