A project to develop a business park access scheme at Oban Airport remains 'on track' for completion in November, Argyll and Bute Council has announced.
Over the past two weeks, foundation work has been completed for the carriageway.
This included the installation of a geogrid reinforcement netting which strengthens the existing ground.
Last week, kerbing works got underway, which are set to be complete on 16 October.
The next phase of works involve installing gully pots and outfall pipework before the blacktop is laid the week beginning 26 October.
(LM/MH)