The Highland Council has said it will need to extend the closure of Bank Street, between Fraser Street and Friars Lane, until May in order to allow the River Ness Flood Alleviation and Streetscape Scheme to get back on track.
Initially, the local authority had planned to reopen Bank Street to through traffic between Ness Bridge and Academy Street on 10 February. This would have coincided with work commencing on the second phase of the Kessock Bridge Resurfacing Project.
However, the flood scheme has fallen behind schedule after encountering problems.
The decision to extend the closure has been based on an agreement with the Council and local businesses which is to try and complete the flood alleviation scheme and streetscape works as quickly as possible and to avoid the peak summer months.
In addition to the above, the local authority has said that on the opposite side of the river, Huntly Street is currently closed to traffic between Young Street and Greig Street and also between Celt Street and Balnain Street to allow flood wall construction works to take place.
Works will continue in sections with phased closures between side streets until the works have been completed.
(JP/CD)
Construction News
03/02/2014
Update On River Ness Flood Alleviation Scheme


13/06/2025
The first completed section of Glasgow's ambitious £120 million-plus Avenues programme, the Holland and Pitt Street Avenue, has officially opened, marking a significant milestone in the ongoing regeneration of the city centre.
The newly completed avenue features a comprehensive transformation, incl

13/06/2025
Construction has officially commenced on the Dumfries Zero Waste Park (Dumfries ZWP), marking a significant milestone in Dumfries and Galloway Council's commitment to its Waste, Recycling and Reuse Strategy 2023–2030.
The £11.197m investment, drawn from the Council's approved 10-year Capital Invest

13/06/2025
Scotland's newest green wastewater treatment works (WWTW) in Winchburgh has been honoured with a prestigious sustainability award from The Royal Academy of Engineering.
The £35 million facility, owned and operated by Scottish Water and officially opened in October 2024, is designed to support a pr

13/06/2025
Forestry and Land Scotland (FLS) has initiated two public consultations on its proposed Land Management Plans for Glenbranter Forest and Strathlachlan Forest, both located on the Cowal Peninsula.
These consultations are part of FLS's routine ten-year review process for all land management plans, e

13/06/2025
Clark Contracts has been appointed by Fife Council to construct a new council housing development on Lochgelly Road in Lumphinnans.
The project, comprising 97 new homes, is expected to commence works in July 2025 with an anticipated completion in summer 2027.
The development will provide a divers

13/06/2025
JCB's groundbreaking hydrogen-fuelled engine is set to make its public debut at a UK agricultural event at the Royal Highland Show, running from Thursday, 19 June, to Sunday, 22 June, at Ingliston.
The innovative engine will be a central exhibit within the Royal Highland and Agricultural Show Socie

13/06/2025
Glasgow City Council has approved the disposal of a significant number of properties and land parcels across the city, paving the way for a wide range of new developments including social, mid-market, and private housing, supermarket expansion, student accommodation, retail spaces, and advanced manu

13/06/2025
The demolition of the multi-storey car park in Kilmarnock is progressing well, despite encountering a number of complex issues since work began. The structure is now expected to be fully removed by the end of July, with site tidying scheduled throughout August.
The ongoing demolition has inevitably

13/06/2025
Energy giant SSE has welcomed the UK Government's commitment to Carbon Capture and Storage (CCS) infrastructure in its recent Comprehensive Spending Review, specifically highlighting the positive implications for the Scottish Cluster and the Peterhead Carbon Capture Power Station.
Finlay McCutcheon

13/06/2025
Jaimie Steele, a Trainee Design Manager at GRAHAM Building, has been honoured with the Student of the Year award at City of Glasgow College for his outstanding performance in the HNC Architectural Technology with Digital Construction programme.
The award recognises students who excel in attendance,