Update On Wick Schools Development

Construction News Image
The Wick Schools' Stakeholders Group has been advised that the new £39m Community Campus building will be handed over to the Highland Council in February 2016.

The campus is expected to open from Easter 2016.

Initially, the scheduled handover date had been summer 2015.

However, the new £14m Primary School north of the river remains on course to be handed over to the Council in June 2015, with its doors opening in August 2015 as originally planned.

The revised date for the secondary school was agreed with representatives with Hub North Scotland Limited and Miller Construction UK in Inverness late last week.

The revised handover date will ensure that high quality facilities will be delivered.

The reasons for the programme slipping behind schedule were explained to the Group and included:

• Achieving a design that meets the authority's requirements in relation to natural ventilation and lighting. Planning approval was granted in mid-August which represented significant progress, while detailed design work is on-going, particularly in relation to the roof area.

-- Advertisement --
NorthernAsbestosServicesLtd

• A complicated contract structure which involves significant legal and financial specialist input and which relies heavily on external funders.

• Ensuring that during the tendering of over 60 work packages, local suppliers will be provided with every opportunity to bid for work across the community campus and north of the river projects. Local Members have consistently emphasised the importance of local contractors being provided with every opportunity to bid for work packages.

Now, with the Council having considered the various factors, a decision was made to push back the handover date to ensure the best outcome for the school communities.

Councillor Gail Ross, Chair of the Stakeholders Group, said: "It's well known that big build projects like this often encounter delays for one reason or another but that doesn't make this any less disappointing.

"It's worth pointing out that an Easter 2016 opening does give more leeway for teachers to get the classrooms ready and leaves the final term for more fun integration for the kids, instead of having to focus entirely on the curriculum.

"I am satisfied that this new entry date will not cause interruption to the children's learning- that's what we need to focus on. We need to make sure we deliver a top quality school, not a rushed job with potential cut corners.

"The council will continue to work closely with Hub North and Miller Construction to ensure there are no further delays and that we deliver the building that our community expects."

(JP/CD)

Latest Construction News

01/05/2024

GRAHAM has announced the start of construction work on a new £59m low-carbon development in Edinburgh which combines student flats, build-to-rent and affordable homes. The Burnet Point scheme in Abbey Lane is the first-ever mixed-use residential development of its kind by Unite Students, one of ...
01/05/2024

A groundbreaking ceremony has marked the start of the next major phase of works on the replacement development at Liberton High School. Contractor Balfour Beatty welcomed Head Teacher Alison Humphreys, current high school and primary school pupils who will be educated at the new school, and ...
01/05/2024

Scottish housebuilder, Springfield Properties, has signed a new £10 million contract to deliver affordable housing for Moray Council. The Group will receive funds from the sale of the land to Moray Council in the current financial year and the design and build phase, which accounts for the vast ...
01/05/2024

Consulting and engineering firm, Wood, has been awarded a new decarbonisation contract by TotalEnergies (TEPUK) to support flare gas recovery in the North Sea. The 23-month contract, part of the Elgin-Franklin Flare Gas Recovery System Project, follows Wood's successful completion of a field study ...
01/05/2024

The CCG Group has welcomed the news that they have received seven nominations across six categories at this year's Scottish Home Awards. The Scottish Home Awards is one of the most prestigious in the Scottish housing sector and are set to take place at a glitzy award ceremony on the 13th of ...
01/05/2024

SSEN Distribution has announced month-long programme of infrastructure upgrade works at Loch Ness, to improve the reliability of supplies to over 1,300 homes and businesses, as well as boosting network capacity. The project starts on 2 May and is scheduled to finish by the end of the month. Teams ...
01/05/2024

SSEN Transmission has announced the successful completion of the final phase of the new Port Ann to Crossaig electricity transmission line, after almost three years of construction. Supported on 148 new steel-lattice towers, the new line is designed to be more resilient in extreme weather events, ...
01/05/2024

National Manufacturing Institute Scotland (NMIS) has been announced as a double winner at this year's British Council of Offices (BCO) Regional Awards for Scotland. The project – developed by Morrison Construction on behalf of University of Strathclyde – was successful in the Corporate Workplace ...
01/05/2024

Perth & Kinross Council has announced that a restoration project on Crieff's 130-year-old Murray Fountain will get underway this month, The improvement project, which was announced last year, will see the James Square landmark's masonry repaired and repointed, as well as electrical works to ...
01/05/2024

The Scottish Government has launched a public consultation on proposals to replacing the UK Government's Industrial Injuries Scheme in Scotland. Views are sought on how the Scottish Government's planned Employment Injury Assistance should be delivered and on the next steps for introducing this ...
RBT Underfloor LimitedMorris & Spottiswood LtdArdent Consulting EngineersScaffolding & Access Supplies LtdAll UPVC Windows & DoorsThe Water PointA.G.S Steel Erectors LtdJGasJohnston Oils LimitedFour Seasons Scotland Design & Build Ltd
Terms and Conditions
2024/05/02 05:43:41